An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. OSHA Crane & Derrick Standard Subpart CC 1926.1400

  2. Items that will impact Everyone

  3. Qualified person means a person who, by possession of a recognized degree, certificate, or professional standing, or who by extensive knowledge, training and experience, successfully demonstrated the ability to solve/resolve problems relating to the subject matter, the work, or the project. Qualified Signalperson

  4. Signals Signal person – when required: Point of operation not in full view of operator View of direction of travel is obstructed Site specific safety concerns 1926.1428 Signal person qualifications Signal Types: Hand, voice, audible or “new” Only time an operator can use a cell phone is while lifting as part of a planned procedure 4

  5. Signals (cont’d.) Signal person qualifications Qualified how Documentation Portable 5

  6. Qualification Requirements: Know & understand signals Competent in using signals Basic understanding of crane operation Verbal or written test + practical test Signals (cont’d.) 6

  7. Qualified Rigger

  8. Qualified Rigger • 1926.1404 (r) • Meets the criteria for a qualified person • Possession of a recognized degree, certificate, or professional standing, or extensive (rigging) knowledge, training and experience • Successfully demonstrated the ability to solve/resolve problems (relating to rigging)

  9. Crane or Not Crane? • Functional description • Can hoist, • Lower and • Horizontally move a suspended load • Forklifts configured to hoist and lower (by means of a winch OR hook) and horizontally move a suspended load are covered • Backhoes are excluded even if used like a crane….1926.1400 (c)(2) Forklift with attached boom. 1926.1400 (c)(8) See 1926.1441 if using equipment with a rated hoisting/lifting capacity of 2,000 pounds or less

  10. 1926.1408 Power Lines • Step 1: Identify Work Zone • Work Zone = Marking boundaries OR • 360 degrees around crane up to maximum working radius • Make the power line hazard assessment 10

  11. Could you get within 20 feet of power line? YES NO Option #1 Deenergize & Ground No further action Encroachment Prevention measures Option #2 20 foot clearance • Planning meeting • If tag lines used Non-conductive • Elevated warning lines, barricade or line of signs • PLUS (Choose one): • Proximity alarm, spotter, warning device, range limiter, or insulating link Option #3 Ask Utility for Voltage and Use Table A (with minimum clearance distance) 11

  12. 12

  13. Intentionally Working Closer Than Table A Zone 1910.1410 • Paragraph (b) requires the employer to consult with the utility owner/operator before deciding that it infeasible to deenergize and ground the lines or relocate them. • Employer can establish this distance by either having the utility owner/operator determine the minimum clearance distance that must be maintained or by having a registered professional engineer who is a qualified person with respect to electrical transmission and distribution determine the minimum clearance distance that must be maintained.

  14. Intentionally Working Closer Than Table A Zone • Must show: • Staying outside zone • is infeasible • Infeasible to • de-energize and • ground All of the following are required: 1926.1410 • PL owner – sets minimum approach distance • Planning meeting – procedures • Dedicated spotter • Elevated warning line or barricade • Insulating link/device • Non-conductive rigging • Range limiter (if equipped) • Non-conductive tag line (if used) • Barricades - 10 feet from equipment • Limit access to essential employees • Ground crane • Deactivate automatic re-energizer 14

  15. Certification of Operators

  16. OPTION 1: Accredited testing organization OPTION 2: Employer qualification program OPTION 3: U.S. military OPTION 4: State/local gov’t license Operator Qualifications and Certifications - 4 Options 16

  17. Operator Qualifications and Certifications (cont’d) Portable Valid 17

  18. Written Certification Tests • Administered in any language understood by the operator candidate. • Test must cover: • Controls/performance characteristics • Calculate capacity (w/ or w/out calculator) • Preventing power line contact • Ground support • Read and locate info in operating manual • Appendix Q subjects

  19. Practical Examination • Must be well designed and sufficiently comprehensive • Must have the demonstrated the skills and knowledge needed to operate the equipment safely. • An operator's ability to handle unusual worksite conditions, such as adverse weather or working on crowded jobsites, are hazards that are not commonly part of this exam.

  20. "Operator in Training" • An Operator who does not have a certification on August 8th, 2014 will be considered an Operator in Training, regardless of previous experience. • Must operate under the direct supervision of a Certified Operator • Establishes the criteria when an Operator in Training may work. • Rules for maximum time operating w/o a Certified Operator.

  21. Ground Conditions • 1926.1402 (b) • Ground conditions must be firm, drained, and graded • Use supporting materials, • Use equipment manufacturer's specifications for adequate support • Use equipment manufacturer's specifications for degree of level of the equipment

  22. Controlling Entity • 1926.1402 (c)(3) • Must ensure that ground preparations are safe • Must inform the user of the equipment and the operator of the location of known hazards beneath the equipment set-up area (such as voids, tanks, utilities) • If there is no controlling entity then the employer that has authority at the site to make or arrange for ground preparations must do so.

  23. Assembly Disassembly • Employers must use a qualified rigger for rigging operations during assembly & disassembly • Two options: • Manufacturer procedures or • Employer procedures (criteria requirements). Employer procedures cannot be used if using synthetic rigging.

  24. Assembly/Disassembly Supervisor • Must understand procedures • Review procedures (unless they’ve used them before) • Check that crew members understand their tasks, hazards • Follow manufacturer’s prohibitions • When using outriggers - fully extended or deployed per the load chart

  25. A/D supervisor addresses 12 key hazards, including: Adequate site and ground conditions Sufficient blocking for load and stability Suitable boom and jib pick points Identify center of gravity Stability for pin removal Consider wind speed and weather Assembly/Disassembly (cont’d) 25

  26. The suitability of blocking material Verification of the loads for assist cranes Snagging of cables or components Struck by counter weights Boom hoist brake failure Loss of backwards stability Assembly/Disassembly (cont’d) 26

  27. Requirements for manufacturers to provide walkways and consider fall protection during design of machines. During non-A/D work employees must be tied off when exposed to a 6’ fall. When moving point-to-point on non-lattice booms On lattice booms that are not horizontal On horizontal lattice booms that have a fall distance of 15’ or more. Fall Protection 27

  28. While at any workstation or any part of the equipment (including any boom), except when the employee is near the draw-works (when running), in the cab or on the deck. For A/D work the employer must supply and ensure that all employees on a walking/working surface with an unprotected edge more than 15’ above a lower level are protected from falls. EXCLUDING when working at or near the draw- works while the machine is running. Fall Protection 28

  29. 1926.1412 Inspections Type of Inspection:Who Inspects: 29

  30. Inspections (cont’d) Shift = visual inspection for apparent deficiencies Monthly = documented shift inspection Annual = comprehensive, every 12 months 30

  31. 1926.1412 (d) Apparent deficiencies Control and Drive mechanisms Hydraulics Hooks Wire Rope Electrical Ground Conditions Levelness of the crane Operator view All Safety Devices Operational Aids are working Each Shift Inspection

  32. Operators • 1926.1417 has many requirements. Some highlights are: • Must not engage in any activity that diverts his/her attention while operating the equipment, • No cell phones (other than when used for signal communications) • Must not leave the controls while the load is suspended,  (four exceptions) • Must verify that the load is within the rated capacity of the equipment (2 methods) • Must obey a stop (or emergency stop) signal, irrespective of who gives it. • Told of any employee entering the crane work area 1926.1424(a)(3)

  33. 1926.1430 Employee Training Issues Powerline safety Signal persons Operators Competent Person Qualified Persons Crush Pinch point hazards Tagout for repair Must confirm that the employee understands the information provided in the training Provide the training at no cost to the employee Employer Training

  34. Work Area Control • 1926.1424 • Train each employee assigned to work on or near the equipment • Erect and maintain control lines, warning lines, railings or similar barriers to mark the boundaries of the hazard area (1 Exception)