1 / 10

Essa G. Al-Ansari

2nd PMI AGC Energy Forum DMS Debates Project owners should increasingly adopt the Cost Plus Model over LSTK. Essa G. Al-Ansari. The level of involvement & risk profile for project exwcution can be between two extremes of “largely with the Contractor” or “largely with the Owner”.

velma
Télécharger la présentation

Essa G. Al-Ansari

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2nd PMI AGC Energy Forum DMS DebatesProject owners should increasingly adopt the Cost Plus Model over LSTK Essa G. Al-Ansari

  2. The level of involvement & risk profilefor project exwcution can be between two extremes of “largely with the Contractor” or “largely with the Owner”. EXTENT OF INVOLVEMENT & RISK PROFILE • CONTRACTING STRATEGY CONTRACTING STRATEGY Provide services Responsible for cost, schedule and quality PRIME CONTRACTOR EXTENT OF INVOLVEMENT & RISK Provide small team for quality control Responsible for cost, schedule and quality OWNER OWNER Reimbursable Procurementand Construction Fully Reimbursable (C+Model) ReimbursableConstruction (EPCM) LSTK EPC CONTRACTING STRATEGY

  3. A risk/benefit matrix can be developed to evaluate potential strategies. CONTRACTING STRATEGY EVALUATION(Risk/Benefit Matrix) AVOID RISKY RISK PREFERRED BENEFIT

  4. Client has key focus areas, in terms of risks and benefits that influence the selection of the most appropriate strategy. BENEFITS RISKS • Poor quality/safety control • Conflicts • Insufficient Owner capabilities • Approval process cycle time impacting performance • Poor initial price definition • Poor initial schedule definition • Risk of high levels of refinery “changes” • Quality/safety • Price (in terms of value) • Financing requirements • Schedule • Ability to influence Contractor selection

  5. General contracting strategy can be guided by a “decision-tree” DETAILED ENGINEERING Step 1 Lump sumE only Is theregoodtechnicaldefinition L U M P S U M Yes (P&C to be decided) PROCUREMENT Step 2 Is theequipmentindustrystandard Lump sumE & P Lump sumEngineering Yes No CONSTRUCTION Are therespecific localcircumstances Step 3 No, LSTK No E,P&C - all reimbursable Lump Sum EP&C - reimbursable Lump Sum E & PC – to be decided Yes RE-IMBURSABLE

  6. Decisions have the greatest impact during initial Phases 1 & 2 when the project scope is defined and value identified Value Identification Value Realization Good Project Execution Good Project Definition A B VALUE Poor Project Execution C Poor Project Definition D Phase 1 Opportunity Identified Phase 2 Generate & Select Alternatives Phase 3 Develop Preferred Alternative Phase 4 Execute Phase 5 Operate

  7. Thank You

  8. LSTK implementation strategies offer certain advantages and disadvantages • Transfer of risk to the Contractor, via Single Point responsibility • Clear and enforceable guarantees are in place for cost and schedule • Can result in lower cost and shorter time for project implementation • “Small” client team required to control quality • Strong capability to be debt financed KEY ADVANTAGES --------------------------------------------------------------- DISADVANTAGES • Implementation of “scope” changes can be less flexible and more costly. • Restricted opportunity for Owner to influence vendor/subcontractor selection. • Requires a well defined ITB Package – high front-end loading

  9. Fully reimbursable approaches Fully reimbursable approaches are typically adopted when the Contractor is required to provide services that cannot be accurately pre-defined. ADVANTAGES • Client retains control of all aspects of the project, including vendors and subcontractors • Flexibility in implementing changes

  10. Fully reimbursable approaches ….Cont’d DISADVANTAGES • Can result in longer project implementation, and resultant higher costs. • Extensive demand on the client’s technical and managerial resources, requiring a larger team. • Contractor will not provide completion guarantees (in terms of cost/schedule), as it is only providing services. • Limited capability to be debt financed • Project cost will only be known with certainty towards project completion • Risks rest primarily with Owner

More Related