An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CVL608 week 4 Assemblies

  2. Review • When you start a new estimate, the folder in which you setup that estimate should be the same folder as the _______________. • Why should you enter the job size and unit when setting up a new estimate? • it will allow a cost per unit for the entire job • $834.77 / LF • What does the spreadsheet display? (3) • items, quantities and cost. DATABASE

  3. Review • What do several states in the USA have to be aware of with respect to subcontractors? • MWBE, Minority and Women-owned Business Enterprise • What are the four takeoff methods? • item, quick, assembly and one-time • What is a pass when performing a takeoff on an item? • a set of dimensions entered • Where do you include addons as part of your estimate? • total page.

  4. Assemblies • An assembly is a group of items that make up a particular structure or portion of a structure such as drywall partition, concrete slab on grade, sewer, road………. • Assemblies enable you to take-off multiple items with a single operation.

  5. Assembly advantages • Increase the speed of takeoff • you select one assembly that contains the items required, not each item individually • Obtain a cost per unit for the assembly • each item cost is added up and based on the assembly calculation it will give you a cost per unit for all items combined Example for driveway: • form work LF = $350, concrete M3 = $2000, granular CY = $850, finishing SF = $700 • assembly unit cost $3.78 / SF.

  6. Assembly advantages / disadvantages • Advantages • items are not forgotten on an individual basis • less time performing estimates • Disadvantages • takes time to develop and create assemblies.

  7. Creating an Assembly • seven steps for building assemblies • plan it - identify the items to be included • assembly ID • assembly description • assembly unit • assembly calculation method • insert items • modify formula when required for each item.

  8. Planning the assembly • Look at a set of drawings and determine what could be items in an assembly • Items that could be part of an assembly are usually items that have common variables • length’ of slab, width’ of slab • height’ of wall, length’ of wall.

  9. Assembly input • Assembly Unit • used to label the cost per unit for the entire assembly • this is usually the most logical unit when applied to the assembly quantity • sewers could be LF • roads could be SF • building footings could be LF • block walls could be SF.

  10. Assembly input • Assembly calculation • method used to calculate the assembly unit for the entire assembly • click the magnifying glass to set up a calculation for the assembly • the procedure is similar to building an item formula • use common variables that are in your assembly items.

  11. Assembly input • Insert button • use this button to add rows to an assembly using any combination of the following commands • Items - inserts the selected items • Item Tables - inserts the selected item tables (not covered in this course) • select at Takeoff - inserts a placeholder for an item to be selected during takeoff • you must select what type of item to be used • you can select multiple items and drag to the grid.

  12. Assembly input • Check item formula • right pick on item formula to display option window • use custom calculation • allows you to create a new formula for the item, specifically for the assembly • used most of the time • edit formula • changes the original item formula • caution • variables should be consistent between items.

  13. Assembly input • Test • use this button to verify that an assembly includes the appropriate variables • does not do any calculations • Select OK to accept assembly • Select Close to exit assembly window.

  14. Assignment • Create assemblies as defined online and start a new takeoff call your name, assembly • Submit at the beginning of the scheduled class.