1 / 5

Update on Exit Capacity Substitution and Revision

Update on Exit Capacity Substitution and Revision. Distribution Workstream 28 October 2010. Background. Licence Obligation to “substitute unsold NTS baseline exit flat capacity between NTS exit points.…..such that the level of NTS obligated incremental exit flat capacity is minimised”; and

verna
Télécharger la présentation

Update on Exit Capacity Substitution and Revision

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on Exit Capacity Substitution and Revision Distribution Workstream 28 October 2010

  2. Background • Licence Obligation • to “substitute unsold NTS baseline exit flat capacity between NTS exit points.…..such that the level of NTS obligated incremental exit flat capacity is minimised”; and • to “revise the level of NTS baseline exit flat capacity …… in the event that the release of incremental obligated entry capacity changes the availability of NTS exit capacity” • 4 industry workshops held, then • Informal consultation from 30th June to 6th August • Workshop 5 held in September • All workshop and consultation material can be found on our website at: http://www.nationalgrid.com/uk/Gas/Charges/statements/transportation/ExCapSubMS/ • Preference for a simple, transparent methodology. • General agreement on approach, but a few issues remain.

  3. Issues – Substitution prior to Investment Lead-time. • Capacity may be released via ad-hoc and ARCA applications as early as M+7. • If these applications require release of incremental capacity they are likely to be rejected unless they can be satisfied through substitution. • National Grid NTS is considering whether substitution should apply to all enduring capacity applications or whether it should apply only to those with a release date of 1st October Y+4. • Advantage of Y+4 rule • Reduces risk to Users at donor exit points by limiting the time of reduced capacity at an exit point between substitution and recovery of baseline. • Disadvantage of Y+4 rule • May lead to some short-term capacity applications being rejected. Applicant will be reliant on off-peak capacity or project may be delayed. • This specific issue will be raised and put to the industry within the formal consultation on the proposed methodology.

  4. Issues • Interconnectors • Some support for excluding interconnectors from substitution - impact of developing EU regulations and concerns over security of supply • Alternative view is that all offtakes should be treated equally, no discrimination and special arrangements should be avoided unless to comply with specific known legislation • Methodology to propose no special treatment for Interconnectors • Partial Substitution • Partial substitution leads to partial investment requiring a partial revenue driver • Consultation on generic revenue drivers to be issued by Ofgem shortly • Methodology to propose partial substitutions with a caveat to exclude partial substitutionif generic revenue driver is not agreed • Exchange Rate Collars • Industry opposed to collar - concerns a collar would reduce efficiency and transparency by increasing “spare” capacity • National Grid’s concern is whether there is sufficient time to undertake the necessary analysis work for substitution - applying a collar simplifies the process significantly. • Methodology to propose no collar

  5. Indicative Timeline. 04/04/11 Submit ExCS for Approval 14 days after consultation and no later than 4th Jan 2011 7th SeptWorkshop 5 7th AprWorkshop 3 25th MayWorkshop 4 Consultation results 30th June to 6th Aug Informal consultation Approval or veto of proposed ExCS 5th Nov to 3rd DecFormal consultation Ofgem processes; including impact assessment

More Related