1 / 25

Pipe Post Installation Inspection Demonstrations

Pipe Post Installation Inspection Demonstrations. Background. More states and municipalities embrace the use of Closed Circuit Television (CCTV) Inspection Storm drain pipes and culverts, Observing cracks in reinforced concrete pipe (RCP)

Télécharger la présentation

Pipe Post Installation Inspection Demonstrations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Pipe Post Installation Inspection Demonstrations

  2. Background More states and municipalities embrace the use of Closed Circuit Television (CCTV) Inspection Storm drain pipes and culverts, Observing cracks in reinforced concrete pipe (RCP) Not armed with enough information to properly interpret the video inspections Uneducated eye will interpret hairline cracks as detrimental to the service and performance. In part do to a lack of understanding How RCP is designed to crack under load What different cracks in RCP mean Also due to the magnification available in modern CCTV Slide 2 - 06.2010 Pipe Inspection Demo

  3. Background (cont.) Standard design procedure Supporting strength of RCP based upon the load required to develop a 0.01” crack. 0.01” crack can be misinterpreted that an installed pipe has reached failure, AASHTO LRFD Bridge Construction Specifications (Section 27) allow cracks up to ten times this width (0.10”) in installed RCP without repair. Slide 3 - 06.2010 Pipe Inspection Demo

  4. Background (cont.) Post Installation Inspection Demonstration Use CCTV inspection equipment that is used in the field Pre-cracked RCP laid above ground Inspectors and other stakeholders to compare cracks Actual cracks in pipe vs CCTV image of crack Allows a better understanding and interpretation of the inspection data. Slide 4 - 06.2010 Pipe Inspection Demo

  5. Planning Start promoting early Engineers – Municipalities – DOT’s The larger the event, the longer it will take to get a suitable date scheduled. Hold the event at a pipe plant if possible. Conduct a tour of the facility Observe a three-edge bearing test Reinforces the strength and attributes of RCP Partner with an inspection company Equipment used in the field will be demonstrated Field experiences will be relevant Actual reports can be provided Slide 5 - 06.2010 Pipe Inspection Demo

  6. Planning (cont.) • RCP • large enough to crawl into and measure the cracks • 36” diameter for setup • 60” or larger for three-edge bearing test • Recommend double cage reinforcement • Large cracks less likely to pass through the wall • Provides a better looking specimen • HDPE • 15”- 24” works well for the flexible pipe • 40 LF - (2) 20’ pieces Slide 6 - 06.2010 Pipe Inspection Demo

  7. Set up • The demo consists of four “stations” • Presentation area • Inspection equipment area • Plant tour of RCP production • Three Edge Bearing test station Slide 7 - 06.2010 Pipe Inspection Demo

  8. Set up Presentation Begin with a short introduction Explain the importance of Post Installation Inspections Include an overview of what the guests will see Conduct in break room or QC lab Equipment Power point presentation and projector. Microphone and P.A. as required 20 minutes presentation - chairs are not needed. Slide 8 - 06.2010 Pipe Inspection Demo

  9. Set up Slide 9 - 06.2010 Pipe Inspection Demo

  10. Set up • Inspection Equipment Area • Need area with pipe joined up on ground. • RCP setup: • Two sections “pre-cracked” for inspections • Two addition uncracked sections for the equipment to crawl through (four total sections) • HDPE setup: • Two sections (40 L.F.) deflected (clamped) • CCTV Setup • Position the inspection van at the end of pipe. • TV monitor outside of the van for group to viewing. • May need a pop up shelter to cut glare from the sun. • Computer monitors not compatible Slide 10 - 06.2010 Pipe Inspection Demo

  11. Set up Slide 11 - 06.2010 Pipe Inspection Demo

  12. Set up • Plant Tour • Establish a staging area • Create manageable group sizes • Staff groups accordingly Slide 12 - 06.2010 Pipe Inspection Demo

  13. Set up • Three Edge Bearing Test • Have TEB Machine preloaded (as large as possible) • Load pipe up to an 0.01” crack (stop loading) • Allow attendees to observe and measure crack • Release load and witness the cracks close back up • After all groups observed 0.01” crack - load to ultimate • Point out ultimate load then continue to failure • Stress the additional strength capacity of the pipe Slide 13 - 06.2010 Pipe Inspection Demo

  14. Set up Slide 14 - 06.2010 Pipe Inspection Demo

  15. Hand out information • Full copy of AASHTO Section 27 • One page “Summary” according to AASHTO Section 27 • ACPA CP Info – “Cracks in Installed Reinforced Concrete Pipe” • Optional 0.01” feeler gages from ACPA Slide 15 - 06.2010 Pipe Inspection Demo

  16. One Page Summary information: AASHTO LRFD Bridge Construction Specifications call for all buried pipe culverts to undergo internal inspection to evaluate issues that may affect long-tern performance. Section 27.6.4 describes potential cracks observed in concrete pipe culverts and a simplified summary is as follows: • Crack less than or equal to 0.01” • These cracks are minor & OK • Crack between 0.01” and 0.10” • Evaluation required: is it detrimental and in a corrosive environment? (PH<5.5) • If non-corrosive or not detrimental – OK • If corrosive and detrimental – Seal crack • Crack equal to or greater than 0.10” • Evaluation required: is crack detrimental to structure? • If not detrimental – OK • If detrimental – repair and seal crack • If not repairable – remediate or replace Slide 16 - 06.2010 Pipe Inspection Demo

  17. Other information • Can purchase shim stock in 0.05”, and 0.10” • (DIMES WORK WELL ALSO – DIME = 0.05” width) • Have a set of feeler gages available for guests. Slide 17 - 06.2010 Pipe Inspection Demo

  18. Dry Run & Set Up • Set up a dry run the day before the event. • Expect last minute updates and setup changes. • Sometimes the inspection equipment is “brand new” and just “out of the box.” Slide 18 - 06.2010 Pipe Inspection Demo

  19. Dry Run & Set Up (cont.) • Try to get an 0.01” crack for inspecting. • May require taking the pipe to or just beyond ultimate on the three edge bearing tester. • For the larger cracks, use dimes to shim open. • 0.05” crack can be measured with the laser micrometer • Half the size referenced in AASHTO Section 27. • Note that the 0.10” crack reference in AASHTO Section 27 would be the width of two dimes stacked together. Slide 19 - 06.2010 Pipe Inspection Demo

  20. Dry Run & Set Up (cont.) • Set up RCP with the spigot end away from the van • Use a gasket hold black plastic sheeting • Provides for proper lighting for the video / laser Slide 20 - 06.2010 Pipe Inspection Demo

  21. Dry Run & Set Up (cont.) • ¾” coil rod and 4”x4”s to deflect the HDPE pipe • The CCTV equipment has a difficult time picking up deflection less than 10% without the use of laser profile equipment • Use a gasket to hold the plastic on the HDPE Slide 21 - 06.2010 Pipe Inspection Demo

  22. Day of event • Two hours is plenty of time for this demo. • Suggest starting at 10:00 am and wrapping up with pizza and soft drinks for all. Slide 22 - 06.2010 Pipe Inspection Demo

  23. Objectives • Guests leave with the following understanding • Post Installation Inspection must be performed on flexible pipes • Laser Profile Equipment will give best results and should be required in the specifications • Post Installation Inspections performed on RCP • Expect to see cracks • Understand what the expected cracks in RCP should look like • CCTV equipment will magnify the cracks • Minor cracks in storm drain concrete pipes are not a concern • Sealing of these cracks should not be required Slide 23 - 06.2010 Pipe Inspection Demo

  24. Post Installation Inspection Demo Don’t be nervous It is not difficult It does take planning It will take time It is effective It is very rewarding QUESTIONS????? Talk to us!!!! Slide 24 - 06.2010 Pipe Inspection Demo

  25. Pipe Post Installation Inspection Demonstrations

More Related