1 / 38

7 - Manufacturing Resource Planning

7 - Manufacturing Resource Planning. Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240. How do we. System for organizing WIP releases Consider LT for each item Look at BOM to see what parts needed Release so they will arrive just as needed Example Figure 7.2 Order quantity is 50 units

vida
Télécharger la présentation

7 - Manufacturing Resource Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 7 - Manufacturing Resource Planning Dr. Ron Tibben-Lembke pp. 222-234, 236-7, 240

  2. How do we • System for organizing WIP releases • Consider LT for each item • Look at BOM to see what parts needed • Release so they will arrive just as needed • Example Figure 7.2 • Order quantity is 50 units • LT is one week • I’ve added “Net requirements” and “scheduled releases” rows to Figure for clarity

  3. Fig 7.2 6 units short

  4. Fig 7.2 Order 50 units week earlier

  5. Fig 7.2 Ending inventory

  6. Terminology • Projected Available balance • Not on-hand (that may be greater) • Tells how many will be available (in ATP sense) • Planned order releases ≠ scheduled receipts • Only when material has been committed to their production • Move to scheduled receipts as late as possible • Preserves flexibility

  7. Figure 7.3 1605 Snow Shovel 1605 Snow Shovel 062 Nail (4) 13122 Top Handle Assy 048 Scoop-shaft connector 14127 Rivet (4) 314 scoop assembly 118 Shaft (wood)

  8. 314 scoop assembly 314 scoop assembly 019 Blade (steel) 14127 Rivet (6) 2142 Scoop (aluminum)

  9. 13122 Top Handle Assembly 13122 Top Handle Assembly 11495 Welded Top handle bracket Assembly 457 Top handle (wood) 1118 Top handle Coupling (steel) 129 Top Handle Bracket (steel) 082 Nail (2)

  10. BOM Explosion • Process of translating net requirements into components part requirements • Take into account existing inventories • Consider also scheduled receipts

  11. BOM Explosion Example • Need to make 100 shovels • We are responsible for handle assemblies.

  12. 13122 Top Handle Assembly 13122 Top Handle Assembly 11495 Welded Top handle bracket Assembly 457 Top handle (wood) 1118 Top handle Coupling (steel) 129 Top Handle Bracket (steel) 082 Nail (2)

  13. Net Requirements Sch Gross Net Part Description Inv Rec Req Req Top handle assy 25 -- 100 75 Top handle 22 25 Nail (2 required) 4 50 Bracket Assy 27 -- Top bracket 15 -- Top coupling 39 15

  14. Figure 7.5 Sch Gross Net Part Description Inv Rec Req Req Top handle assy 25 -- 100 75 Top handle 22 25 75 28 Nail (2 required) 4 50 150 96 Bracket Assy 27 -- 75 48 Top bracket 15 -- Top coupling 39 15

  15. 13122 Top Handle Assembly 13122 Top Handle Assembly 11495 Welded Top handle bracket Assembly 457 Top handle (wood) 1118 Top handle Coupling (steel) 129 Top Handle Bracket (steel) 082 Nail (2)

  16. Figure 7.5 Sch Gross Net Part Description Inv Rec Req Req Top handle assy 25 -- 100 75 Top handle 22 25 75 28 Nail (2 required) 4 50 150 96 Bracket Assy 27 -- 75 48 Top bracket 15 -- 48 33 Top coupling 39 15 48 --

  17. Timing of Production • This tells us how many of each we need • Doesn’t tell when to start • Start as soon as possible? • Dependent events (oh no, not that!) • Front schedule Cutting approach (Fig. 7.6) • Back schedule Fig. 7.7

  18. Fig 7.8 – 13122 Top Handle Assy p. 233

  19. Fig 7.8 – 13122 Top Handle Assy-2

  20. Fig 7.8 – 13122 Top Handle Assy -3

  21. 457 Top Handle One handle for Each assembly

  22. 457 Top Handle

  23. 457 Top Handle

  24. 082 Nail (2 required) Two nails for Each assembly

  25. 082 Nail (2 required)

  26. 082 Nail (2 required)

  27. 082 Nail (2 required)

  28. 11495 Bracket Assembly One bracket for Each assembly

  29. 11495 Bracket Assembly One bracket for Each assembly

  30. 11495 Bracket Assembly One bracket for Each assembly

  31. 11495 Bracket Assembly

  32. 129 Top Bracket

  33. 129 Top handle bracket

  34. 1118 Top handle coupling

  35. 1118 Top handle coupling

  36. 1118 Top handle coupling

  37. Other considerations • Safety stock if uncertainty in demand or supply quantity • Don’t let available go down to 0 • Safety LT if uncertainty in arrival time of supply • Place order earlier than necessary • Order quantities • EOQ, Lot-For-Lot, Periodic Order quantity, more to come in ch. 14

  38. Homework • DQ: 3, 7 • Problems: 3,5,6,7

More Related