An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. present status • test results • with AGATA@GSI Lund York Cologne Calorimeter Thanks to Andreas Wendt !!

  2. Reminder: Detection principle LYCCA-0 ΔE-E-hardware: 12 DSSDs 12x9 CsI (long/short) Sekundary target DSSD Diamond or Plastic DSSD CsI RIB vom FRS (x, y) Time-of-Flight (ΔE, x, y) (E) AGATA @ GSI meeting May 4th 2010, Is University of York Mike Bentley University of Cologne Andreas Wendt

  3. Reminder: Detection principle 37Ca (85 %) 2*103 p/sec 36K (10 %) Double fragmentation reaction: 40Ca (420 MeV/u) + 9Be (4.0 g/cm2) → 37Ca (196 MeV/u ) + 9Be (0.7 g/cm2) Selection by CATE (Energy-loss/Energy) Selection by FRS AGATA @ GSI meeting May 4th 2010, Is University of York Mike Bentley University of Cologne Andreas Wendt

  4. Reminder: Detection principle Simulation: M.J.Taylor et al (assumes 3m flight path and 50ps FWHM)) Mass Selection by Time-of-Flight and Energy • Expected performance: Mass identification (if ~50ps FWHM timing achieved) • Mass separation up to A~70 • Some mass information at A~100 • Depends on specific case (needs simulation) AGATA @ GSI meeting May 4th 2010, Is University of York Mike Bentley University of Cologne Andreas Wendt

  5. Status: mechanics LYCCA chamber: • up to 72 KEL-Feethroughs • 32 SHV+Lemo-FT Vacuum test @ cologne (5·10-5mbar) Feb. 2010 Used as TKE-detector (for S272 @ S4) Mar./Apr. 2010 Preparation and storage @ X7 AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  6. Status: Silicon detectors • - 32 x 32 strips • - Active area 58 x 58 mm² • - Interstrip distance : 75 μm • thickness: 300 μm • 12 ΔE-detector needed for LYCCA-0 • Ordering status: • 18 DSSDs delivered • all T-boards delivered • connectors on-hand • ΔE-detector status: • 10 DSSDs ready! • 8 @ Lund, awaiting bonding • [2 ΔE-detectors tested in-beam] AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  7. Status: CsI-scintillators short 40.0 long • „short“ crystals (13+7mm) • 2 E-Blocks assembled, tested • crystals for another 4 blocks available • mechanics for 12 E-Blocks available • „long“ crystals (33+7mm) • crystals for 13 E-Blocks on hand • 4 E-Blocks (used for S272) ready AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  8. Status: Time-of-flight PLASTIC • Detector constructed for ToF-stop • - New one being constructed for ToF-start • Stop-detector tested in-beam (GSI) • 300 MeV/u 58Ni SC42 180ps FWHM Plastic ToF 40ps FWHM Robert Hoischen et al (Lund/GSI) AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  9. Status: Time-of-flight DIAMOND • Start-detector: 9 x PC 2x2cm wafers (4 strips) • 36 detector segments • Prototype wafers fabricated and tested • 5 wafers will be put in detector in June/July 2010 • Fast DBAIV current pre-amps + V1290 TDC • First tests TEXAS A&M March/April 2010 • ~35MeV/u 40Ar beam • ~20 MeV/u 20Ne beam AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  10. Status: Time-of-flight DIAMOND ~35MeV/u 40Ar beam Best ~90ps FWHM Best achieved ~90ps FWHM ~20 MeV/u 20Ne beam • BUT • …problems with detector reliability (HV breakdown, PCB?) • …and fabrication consistency. 16O 20Ne AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  11. Time-of-flight for AGATA • Two options: • Diamond start AT TARGET (~70ps FWHM required) and Plastic stop (50ps ideal) • OR.. • Plastic start UPSTREAM OF TARGET (~50ps FWHM required) and Plastic stop (50ps ideal) • THESE will be tested in June/July 2010 Plastic DSSD DSSD CsI Plastic Diamond Secondary target Time-of-Flight (ΔE, x, y) (E) (x, y) AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  12. Status: Electronics 16ch 16ch 9ch 9ch 16ch 64ch 64ch 16ch 9ch 9ch 9ch 9ch 16ch 64ch 64ch 16ch 9ch 9ch 9ch 9ch 16ch 16ch 9ch 9ch • 200 MeV: • 18 available • 4 GeV: • prototype tested • 22available (x2 / x4 join-board) 32ch - CSP 64ch +9ch 9ch 9ch 9ch LYCCA for S272: DSSD 64ch + CsI 36ch → 2 + 2 PreAmps LYCCA-0: DSSD 384ch + CsI 108ch → 12 + 4 PreAmps AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  13. Test results: DSSD off-beam Test chamber FWHM: 41 keV @ 5484 keV ~ 0,75 % (241Am) 6 cm AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  14. Test results: LYCCA @ S272 LE 3 LE 4 total LE 1 LE 2 DSSD 6 7 8 3 4 5 Labeling of crystals 0 1 2 Top-left: Hit pattern DSSD Top-right: HP of DSSD, if LE2(4) is hit Bottom-left: HP of DSSD, if LE2(5) is hit Bottom-right: HP of CsI-crystals AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  15. Test results: LYCCA @ S272 ΔE (Σ p-side) Gen. Not calibrated yet ΔE (p2) TKE (Σ LE2) TKE (LE2(6)) AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  16. Timeline Mar./Apr. 2010 Jun./July 2010 Sep. 2010 LYCCA-00 @ S272 LYCCA-0 Comissioning PreSpec I @ FRS Photomontage: view on LYCCA-0 AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  17. LYCCA Simulations NIM A 606 (2009) 589-597 VISIT: LYCCA page at Lund University (type “LYCCA” in Google) !! • LYCCA-0 Simulations • Full MOCADI event generator (realistic beam and reaction profile) • Full implementation of LYCCA-0 detectors • Time-of-flight options (both) now included • Variable parameters (resolutions, flight path etc) AGATA @ GSI meeting April 30th 2010, GSI University of York Mike Bentley University of Cologne Andreas Wendt

  18. LYCCA-Collaboration P. Reiter, A. Wendt, C. Goergen, G. Pascovici, J. Taprogge, S. Thiel University of Cologne D. Rudolph, P. Golubev, R. Hoischen Lund University M. A. Bentley, M. Taylor, B.S.Nara Singh, S.P. Fox University of York J. Gerl, GSI PreSpec Collaboration NUSTAR Simulation group AGATA @ GSI meeting April 30th 2010, GSI University of Cologne Andreas Wendt