1 / 16

Coordinator MPC with focus on maximizing throughput

Coordinator MPC with focus on maximizing throughput . Elvira Marie B. Aske* , ** Stig Strand** Sigurd Skogestad* *Department of Chemical Engineering, Norwegian University of Science and Technology, Trondheim, Norway ** Statoil R&D, Process Control, Trondheim, Norway. Outline. Background

xaria
Télécharger la présentation

Coordinator MPC with focus on maximizing throughput

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Coordinator MPC with focus on maximizing throughput Elvira Marie B. Aske*,** Stig Strand** Sigurd Skogestad* *Department of Chemical Engineering, Norwegian University of Science and Technology, Trondheim, Norway ** Statoil R&D, Process Control, Trondheim, Norway

  2. Outline • Background • Bottleneck • Back-off • Remaining feed capacity • Coordinator MPC • Case study • Discussion • Conclusion

  3. Background • Conventional real-time optimization (RTO) offers a direct method of maximizing an economic objective function • Identifies optimal active constraints and optimal setpoints • Special case considered here (very important and common in practice): • Maximize production (active constraint) • Challenge: Implement optimal solution in real plant with dynamic changes and uncertainty • Implementation of maximum production • Identify bottleneck • Minimize “back-off” at bottleneck

  4. Often optimal: Set production rate at bottleneck! • "A bottleneck is an extensive variable that prevents an increase in the overall feed rate to the plant" • If feed is “cheap” and available: Optimal to set production rate at bottleneck • If the flow for some time is not at its maximum through the bottleneck, then this loss can never be recovered

  5. Vmax Vs Back-off • Back-off is required for robustness • Trade-off between robustness and acceptable loss • Can be placed on constraints, control targets, range changes etc. Vmax-Vs = Back-off = Loss

  6. Key idea: Remaining feed capacity • Since location of the bottleneck may change, we suggest to monitor the remaining feed capacityin eachunit (local MPC) of the plant • Estimate of the remaining feed capacity in unit k: Jk – current throughput (feed) in unit k Jk, max – found by solving a LP problem with unit constraints included • LP formulation: • Example Jk, maxfor a binary column: • x: vector of the MVs and DVs (reflux rate, boil-up, column feed) • b: vector of contraints (+back-off), (impurities, flooding limit ) • A: from the MPC model for the unit

  7. Coordinator MPC • Task: maximize an objective function • here: max feed rate and make decisions involving several local MPC applications which handle smaller process units • Feedback on minutes basis • Coordinator MPC is placed on the top of the local MPC in the control hierarchy and coordinates the underlying MPCs • Smart decomposition • Avoid one large MPC application which will be over-complex for a complete chemical plant • Can operate both with and without an RTO layer.

  8. Coordinator MPC • MVs (not used by individual MPCs) • Feed to plant Fi • Feed crossovers / split fractions • Maximize weighted overall feed subject to capacity constraints: G represents the dynamic influence from each MV to Rk • G typically obtained from step with MPCs in closed loop.

  9. Case study: Coordinator MPC on Kårstø gas plant • Task: maximize plant throughput within feasible operation (=satisfy constraints) • Selected part of Kårstø plant: 2 separation train • D-SPICE whole plant simulator used as “real plant” • Local MPCs and coordinator MPC: Implemented in SEPTIC

  10. Each column has constraints on max. pressure drop, reflux rate, boilup, etc. • Vapor capacity in the columns limited by max. pressure drop corresponding to flooding • Potential problem: Pressure drop not always a good indicator of flooding • Coordinator MPC MVs: train feed flows, feed splits and crossover • CVs: • remaining feed capacity in each column (10 in total) > Back-off >0 , • ET-100 sump level controller output in allowed range • Total plant feed (max.) • Experimental step-response model G obtained at 80-95% of the maximum throughput (typical flow rate)

  11. Case study:Simulation • The coordinator performance is illustrated with three different cases • t = 0 min: Move the plant to maximum throughput • t = 360 min: Change in feed composition in T100 • t = 600 min: Change in butane splitter T100 MPC CV limit (reducing the remaining feed capacity), which is operated at its maximum • Monitor the following: • Remaining feed capacity in each column (ET100, PT100, …..) • Sump level in ET100 (due to the crossover) • Total plant feed • MV valves

  12. Case study: CVs in the coordinator MPC

  13. Case study: MVs in the coordinator MPC Train feed Train feed Crossover Feed split Feed split

  14. Main potential improvement: Reduce back-off • Include feed forward, especially from feed composition changes • Composition measurements at the pipelines into the plant • Introduce level setpoints (buffer volume) as additional MVs for the coordinator • MV close to bottleneck, avoid loss

  15. Discussion • With existing MPCs: Little extra work to implement coordinator MPC • Max throughput: Common in practice • Column pressure drop is not always a good indicator for flooding, a more detailed remaining feed capacity model may be needed in some cases • Express flow changes as relative (%) changes • All model gains (G) are then 1 • Update nominal flows based on feed composition (“gain scheduling”) • If the feed is limited for a period, the economic optimum is not max. flow • RTO finds the optimal solution • No need to modify the coordinator MPC because we have used “trick” • Maximize feed realized through a (weighted) overall feed rate J as a CV with a high, not reachable set-point with lower priority

  16. Conclusion • Designed and implemented a coordinator MPC with experimental step response models to follow the plant optimum, under influence by disturbances of dynamic character • Implemented on Kårstø Whole plant simulator, D-SPICE® software • Performs well on the simulated challenges • Improvements by including feed forward and manipulating buffer volumes

More Related