The Reserved Source Point (RSP) process enables Market Participants to terminate and replace existing RSPs, thereby influencing Annual ARR Allocations from June 1, 2020, to May 31, 2021. In 2019, MISO processed 2,113 RSP requests, granting 18.5 GW across various seasons. In Round 2, 71% of BRSS requests were studied, yielding 9.7% awarded, while Round 3 saw 27% of PRSS requests studied with a 12% approval rate. This summary presents a comprehensive overview of RSP requests, awards, and comparisons with previous studies.
E N D
2019 Reserved Source Point (RSP) Results Sep 3, 2019
Background • Reserved Source Point (RSP) process allows Market Participants to terminate and replace existing Reserve Source Points (RSPs) and add new RSPs • The terminated or awarded RSPs will affect the ARR Entitlements of the Annual ARR Allocation for the planning period: 06/01/2020 – 05/31/2021
RSP Results Overview • MISO processed 2,113 RSP requests • 18.5 GW of RSP requests in Round 2 and 3 were granted across the four seasons • BRSS RSP (Round 2) • 71% of BRSS requests were studied • 9.7% of BRSS studied requests were awarded • 1.7 BRSS GW were added/replaced • 13.8 PRSS Option GW were added • PRSS RSP (Round 3) • 27% of PRSS requests were studied • 12% of PRSS studied requests were granted • 3GW were added/replaced
Overall 2019 RSP Result Summary Requested RSP MW => RSP MWs submitted by Market Participants Studied MW => Requested MWs that have passed the validation and studied Awarded MW => Results of SFT