An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Unitarian Church of Calgary Facilities Transformation Task Force Town Hall Update April 10,2011

  2. Facility Vision Our congregational home evokes and supports our values. Our space enhances and accommodates the diverse activities and ages in our community, physically, acoustically, and aesthetically. Our building reflects environmental leadership, is cost-effective, and is well maintained. We serve selected needs of the larger community, generating recognition and revenue.

  3. A Growing Congregation • Support average Service attendance of 125 • Peak Attendance of 200 • Would need approximately 240 seats • Support average church school attendance of 70 • Would require at least one more classroom

  4. Growing Congregation continued • 90-100 parking spaces • Office space for 6 staff members

  5. What our facility says • Welcome • We take pride in our surroundings • We are growing in spirit • We support our community

  6. What kind of building? • Attractive • Functional • Energy efficient • Fully accessible • Family friendly

  7. Current Challenges • Parking is limited • Church School in basement • Office space is limited and inefficient • Panabaker Hall roof needs replacing • Wickenden Hall Floors need replacing • Requires continual maintenance needed by Physical Plant

  8. Challenges continued • Entrances all need upgrading • Main entrance requires climbing stairs • Movement in and out of Panabaker is very restricted • Sanctuary Seating is uncomfortable

  9. Possible Options (with thanks to CHET) • Do required long term maintenance • Renovate • Modest Renovation • Major Renovation • Build new Church on existing site • Sell current building • Build new Church • Purchase an existing building

  10. Projected Facility Costs • To 2020 the projected cost is $265,000

  11. Do required long term maintenance • Panabaker Roof - $70,000 (2014) • Wickenden Hall Floor - $11,000 (2013) • Soffit and other painting - $5,000 (2013) • Miscellaneous ongoing jobs - $13,000 (2011 budget)

  12. Do required long term maintenance continued • Money spent would not be recovered • Would not address limitations of space or Parking • Leaves us with an aging facility

  13. Build New on Existing Site • Would allow us to redesign building to our needs • Probably requires zoning change • A new building may require on-site parking • Set back from 16th Avenue • Estimated Cost w/o parking- $1,500,000 plus

  14. Build New on Existing Site continued • Would need to rent while building • Would be required to provide onsite parking • Underground parking est. at $10,000 - $20,000 per space

  15. Sell and purchase an existing building • Plusses • Could realize value of current building • Minuses • We don’t know value of building • Building might not sell • Need to find a facility that meets our needs • Can we find one? Net cost would be ??

  16. Sell and build New Facility • Plusses • Design facility to our requirements • Create an architectural statement • Don’t move until new building is ready • Solve the parking problem • Uncertainties • If we sell building might have to move early • Cost??

  17. Renovation Options • Expand Panabaker Hall to 240+ seats • Upgrade entrance • Improve building flow through • More office spaces • Carry out required long term maintenance

  18. Major Renovation to existing building • Estimated cost up to $750,000 • Time Frame to commence – 3 to 5 years • Avoids zoning changes?

  19. Renovation Plusses • Stay in current location • Some potential for phased implementation • Increased seating in Panabaker • Better aesthetics and functionality

  20. Limitations • Do not realize the value in our current building • Parking does not improve • Church School remains in basement • Limited changes to offices and meeting spaces

  21. FTTF Going Forward • Limitations of current site and facility suggest moving • Leaning to recommending selling and purchasing existing building

  22. FTTF Going Forward • Continue to keep the congregation informed and involved • Presentation to AGM – May 1 • More Town Hall Meetings in Fall • Plan for a special congregational meeting when ready • Consider joining Task Force?

  23. FTTF Going Forward • Determine value of current building • Investigate availability and cost of other buildings • Conduct a capital campaign - $1,000,000 plus • Put building up for sale – determine interest