1 / 14

March 14, 2019

March 14, 2019. Updates. Phase 1.1 Remaining items Phase 1.2 Construction activities Partner coordination Additional Funding Phases 1.3 and 2 Design Activities. Phase 1.1 Remaining Items. Additional railing at Travis Gatehouse Installation underway Inlet lighting

yul
Télécharger la présentation

March 14, 2019

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. March 14, 2019

  2. Updates • Phase 1.1 • Remaining items • Phase 1.2 • Construction activities • Partner coordination • Additional Funding • Phases 1.3 and 2 • Design Activities

  3. Phase 1.1 Remaining Items • Additional railing at Travis Gatehouse • Installation underway • Inlet lighting • Installation underway • Trash screen at inlet pump station • Work postponed until late 2019 • Santa Rosa Pedestrian Crossing • Work to begin next week

  4. Phase 1.2 Construction • Houston to Commerce • Concrete pours for channel bottom and walls • 8-inch waterline installation under Commerce Street bridge • Concrete pours for bridge rail curb and terminal ends • Commerce to Dolorosa • Concrete pours for building underpinning • Drilled shaft installation • Dolorosa to Nueva • Drilled shaft installation • Commerce Street Bridge

  5. Phases 1.3 and 2 Design

  6. Phase 1.3 and Phase 2 Design • Coordination with Mario Schjetnanunderway • Design team developing strategy to address direction from Bexar County • Desired design completion October 2019

  7. Partner Coordination • SAISD administration building • SARA/SAISD coordination • Camaron Street construction • Travis to Houston block to be completed in May • Remainder to begin in late winter 2019 • Alameda Theater • Project team coordination • Texas Public Radio • Demolition started • Coordination ongoing

  8. Partner Coordination • Commerce Street • Construction Proposals under review • Construction to begin May/June • UTSA downtown campus expansion • SPC design files shared • Coordination meeting to scheduled • Federal Courthouse (GSA) • Coordination ongoing

  9. Partner Coordination • Executive Committee • David Smith, County Manager, Bexar County • Lori Houston, Assistant City Manager, City of San Antonio • Razi Hosseini, Interim Director, Transportation and Capital Improvements, City of San Antonio • Suzanne Scott, General Manager, San Antonio River Authority • Next Meeting – March 15, 2019

  10. QUESTIONS & COMMENTS

More Related