Make Every day count Accelerating Bridge Construction with Prefabricated Bridge Elements & Systems

Make Every day count Accelerating Bridge Construction with Prefabricated Bridge Elements & Systems. Every Day Counts Mission. To identify and deploy readily available innovation and operational changes that will make a difference, incorporating a strong sense of urgency.

zalman
Télécharger la présentation

Make Every day count Accelerating Bridge Construction with Prefabricated Bridge Elements & Systems

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Make Every day countAccelerating Bridge Construction with Prefabricated Bridge Elements & Systems

  2. Every Day Counts Mission • To identify and deploy readily available innovation and operational changes that will make a difference, incorporating a strong sense of urgency. • To identify policy or operational changes required to advance system innovation in the longer term.

  3. Core Elements Every Day Counts core elements: • Shortening Project Delivery • Accelerating Technology and Innovation Deployment • Going Greener

  4. Shortening Project Delivery • Accelerating Project Delivery Methods • Design-build • Construction Manager/General Contractor • Shortening Project Delivery Toolkit • Planning & Environmental Linkages • Legal Sufficiency Enhancements • Expanding Use of Programmatic Agreements • Use of In–Lieu Fee and Mitigation Banking • Clarifying the Scope of Preliminary Design • Flexibilities in ROW • Flexibilities in Utility Relocation • Enhanced Technical Assistance on Stalled EISs

  5. Project Delivery Methods Design-Bid-Build CM/GC Design-Build

  6. Technology & Innovation • Adaptive Signal Control • Geosynthetic Reinforced Soil Integrated Bridge System • Prefabricated Bridge Elements & Systems • Safety Edge • Warm-Mix Asphalt

  7. Technology & Innovation GeosyntheticReinforced Soil • Fast, cost-effective bridge support method using alternating layers of compacted fill and sheets of geotextile reinforcement to provide bridge support. • Lots of Benefits: • Eliminates approach slab or construction joint at the bridge-to-road interface • Reduced construction time (complete in10 days) • 25 - 60 % less cost depending on standard of construction • Less dependent on weather conditions • Flexible design – easily modified for unforeseen site conditions • Easier to maintain because of fewer parts • Built with common equipment and materials

  8. PBES Technology Orientation • PBES vision, mission, concepts, & components • The reasons for using PBES • The major benefits of PBES • The status of PBES deployment • PBES performance goals for the U.S.

  9. Accelerated Bridge Construction Components Foundation & Wall Elements Continuous Flight Auger Piles Geosynthetic Reinforced Soil (GRS) Integrated Bridge System Rapid Embankment Construction EPS Geofoam • Prefabricated Bridge Elements & Systems • Prefabricated Elements •   Superstructure • Substructure • Prefabricated Systems • Superstructure • Substructure • Total Bridge Structural Placement Methods Self-Propelled Modular Transporters (SPMTs) Longitudinal   launching Horizontal sliding or skidding Other heavy lifting equipment & methods Conventional lifting equipment & methods Fast Track Contracting Innovative Contracting - Best value - CMGC method - Design Build - A+B - A+B+C - Warranties

  10. Definition of PBES PBES consists of bridge structural elements & systems that are built off the bridge alignment to accelerate onsite construction time relative to conventional practice.

  11. What is PBES? Moving more cast-in-place construction to off-site location

  12. How does PBES accelerate bridge construction? Building the bridge first before you set cones, then quickly move it into place – like in hours or a weekend!

  13. What is PBES? • Elements • Deck Panels: Partial & Full-Depth • Beams: More Efficient Shapes • Pier Caps, Columns, & Footings • Abutment Walls, Wing Walls, & Footings • Systems • Superstructure • Substructures • Total Bridge

  14. How do we accomplish this?Structural Placement Methods • Self-Propelled Modular Transporters (SPMTs) • Longitudinal launching • Horizontal sliding or skidding • Other heavy lifting equipment & methods • Conventional lifting equipment & methods

  15. CONTINUOUS LAUNCHING

  16. Fort Lane/I-15South Layton Interchange Longitudinal Launching Utah

  17. Fort Lane/I-15South Layton Interchange

  18. TRANSVERSE LAUNCHING

  19. I-80 EBL / 2300E Easy Site I-80 WBL / 2300E Difficult Site Conditions Transverse Sliding

  20. What Success Looks Like:FDOT Graves Ave. over I-4 Bridge Replacement - 2006 143-ft long, 59-ft wide 1,300-ton replacement spans built in adjacent staging area Half-hour rolling roadblocks on I-4 to remove 71-ft long, 30-ft wide, 250-ton spans

  21. FDOT Graves Avenue over I-4 Bridge Replacement - 2006 Each new span installed in few hours overnight I-4 closed two partial nights for installations

  22. George P. Coleman Bridge, VA - 1995

  23. Virginia DOT I-95 Bridge over James River, 2002 102 superstructure spans replaced in 137 nights … … with no lane closures during rush-hour traffic

  24. Maryland SHA MD Rt. 24 Bridgeover Deer Creek, 2001 122.5-ft long, 33-ft wide historic through-truss bridge 3 days to install FRP deck! 10 week bridge closure before school started

  25. Wells Street Bridge, Chicago – 2002 Even Good for Railroad/Transit Bridges 111-ft long, 25-ft high, 425-ton truss span installed over a weekend

  26. Baldorioty Castro Ave. – San Juan, Puerto Rico 1992 Two 700-ft and two 900-ft bridges, each installed in 21-36 hrs

  27. Badhoevedorp, Netherlands April 2004 Prefabricated Bridges International Scan Superstructure Roll-In: 390-ft Length, 3300 M Tons 2 Hours to Move - 1 Weekend Road Closure

  28. SPMTs Install Complete Multiple-Span Railroad Bridge RR Bridge 1309, Nohant le Pin, Normandy 2,200 tons moved using SPMTs!

  29. Benefits of Using ABC/PBES This process offers significant advantages over on-site construction, resulting in: • Reduced onsite construction time • Minimized traffic disruption – months to days • Reduced Environmental impact • Improved work zone & worker safety • Positive Cost-Benefit ratios when user costs are considered • Improved product quality – controlled environment, cure times, easier access, etc.

  30. Reduces On-Site Construction Time • Less time spent on-site • Traditional tasks can be done off-site • Minimal impact from weather conditions

  31. Minimizes Traffic Impacts • Minimizes traffic delay and community disruption • Reduces detours, lane closures, and narrow lanes I-59 and I-65 Interchange, AL US 59 under Dunlavy, TX

  32. Minimizes environmental impact • Keep heavy equipments out of sensitive environment Linn Cove Viaduct, NC

  33. Improves Work Zone Safety • Minimizes work near traffic and power lines, at high elevations, or over water. Meylan Pedestrian Bridge, France

  34. Improves Constructability • Prefabricated elements & Systems • Minimal impact from environmental constraints • Relieves constructability pressure. San Mateo-Hayward Bridge, CA

  35. Increases quality • Prefabricated in a Controlled environment • Increases quality control George P. Coleman Bridge, VA

  36. PBES: Improves Quality & Lowers Life-Cycle Costs – to “Stay Out” • Controlled environment • Reduced dependence on weather • Established materials suppliers for consistent quality of materials • Standardized plant operations for consistent quality of production • Optimum concrete curing

  37. IsPBES more cost-effective? Yes, in many cases. • It depends on type of structure and elements or systems used. • Many systems can cost less than conventional construction like adjacent slab or box girders. • First implementation of new elements may cost more. • Need a program of projects--economy of scale. • Life cycle cost analysis is favorable to PBES and provides a positive Cost-Benefit Ratio when user costs are considered.

  38. Declining Cost of Deploying Innovative Technology First time costs more < Potential for new methods to cost less < Promise of time savings < Positive cost-benefit ratios < Promise of programmatic cost savings

  39. Costs of PBES

  40. Costs of PBES

  41. State-of-the-Practice? • Senior management is committed to • Every Day Counts technology deployments • 40+ States: 1 or more projects • 7 States: 20+ projects • 11 States actively pursuing as standard practice • Opportunity for much greater PBES deployment

  42. FHWA PBES Deployment Goals for U.S. • By December 2012, 100 cumulative bridges have been designed and/or constructed rapidly using PBES. • By December 2012, 25 percent of single- or multi-span replacement bridges authorized using Federal-aid have at least one major prefabricated bridge element that shortens onsite construction time relative to conventional construction.

  43. Why Use PBES Technologies? • It offers Major Advantages: • Faster (offsite & off critical path) • Safer (public, construction & inspection) • Better Quality (controlled environment) • Positive Cost-Benefit Ratios when user costs are considered.

  44. Questions? FHWA Contacts: PBES Innovation Team • Claude Napier, Team Leadclaude.napier@dot.gov • Louis Triandafilou, Team Leader, TFHRC Bridge & Foundation Engineering Team lou.triandafilou@dot.gov • FHWA Resource Center Structures Technical Service Team • Website Link • http://www.fhwa.dot.gov/everydaycounts/index.cfm

  45. Make Every day countAccelerating Bridge Construction with Prefabricated Bridge Elements & Systems