1 / 26

Lansing Board of Water & Light REO Town Headquarters & Cogeneration Plant

Lansing Board of Water & Light REO Town Headquarters & Cogeneration Plant. REO Town Cogeneration: Concept to Commercial Operation. Agenda. BWL Background REO Town Firsts Steam Production Study & Recommendations Selecting the Design, Build, Startup and Commission team What we built

Télécharger la présentation

Lansing Board of Water & Light REO Town Headquarters & Cogeneration Plant

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lansing Board of Water & LightREO Town Headquarters & Cogeneration Plant REO Town Cogeneration: Concept to Commercial Operation

  2. Agenda • BWL Background • REO Town Firsts • Steam Production Study & Recommendations • Selecting the Design, Build, Startup and Commission team • What we built • Starting Up & Commissioning your own Plant!? • Questions

  3. BWL Background • The BWL is the largest municipal utility in Michigan and is owned by the citizens of Lansing. • Largest groundwater sourced drinking water system in Michigan (54,900 Customers) • Number of electric customers • 82,823 Residential • 12,708 Commercial • 272 Industrial • Also serve the Lansing downtown district with steam heating and chilled water

  4. BWL Background (cont’d) • Major steam customers in downtown Lansing include: • GM Grand River Assembly plant • State of Michigan buildings • Cooley Law School • Lansing Comm. College • Accident Fund National HQ • Peak seasonal load of 300,000 lbs/hr of steam • Over 12 miles of steam distribution piping

  5. REO Town Firsts • First new utility power plant built in Michigan in 25 years • First power plant built by the BWL in 40 years • BWL’s first natural gas-fired electric generating plant • BWL’s first cogeneration plant • Among the cleanest and most efficient plants operating in Michigan and the US

  6. Steam Production Study • 2010 Steam Production Study identified the following: • Four stoker, coal fired boilers ranging in age from 43 to 55 years have exceeded their design life • $32 Million in capital expenditures to replace: • External skin on 3 of 4 boilers • Soot blowers • Economizer and superheater tubes • Upgrade boiler controls

  7. Steam Production Study (cont’d) • $35-$107 Million in environmental upgrades to comply with forth coming regulations • No guarantee the environmental upgrades to the Moores Park boilers will meet pending EPA regulations, resulting in a loss of $67 - $139 million investment (boiler and emissions control upgrades) • Need for additional electric generating capacity by 2017 due to aging electric units

  8. Steam Production Study Recommendations • Build a new CHP (Combined Heat & Power or Cogeneration) plant • Beneifts include: • Diversify fuel mix (mostly PRB coal) • Avoid burning 351,000 tons of coal a year • Reduce Mercury & SO2 emissions 99% • Improved efficiency • Lowers NOx emissions by 85% and CO2 by 50%

  9. Steam Production Study Recommendations (cont’d) • Help exceed the EPA goal of reducing greenhouse gases by 17% by 2020 • Major work on the Moores Park boilers could trigger New Source Review • Replace 100 MW of aging coal fired electric generation

  10. Selecting the Design, Build, Startup and Commission team • BWL Project Director and Project Manager • Hire an Owner’s Engineer • Architectural & Engineering firm to design the plant • Construction firm to build the plant.  Also had the responsibility to hire a Startup and Commissioning Team • BWL Operations staff to participate in startup and early operation of the equipment

  11. What we built • Plant specifications • (2) GE LM6000 PF/DLE units capable of 50 MW each • (2) Once Through Steam Generators (OTSG) 175 klbs/hr each • (1) Gas Fired Package Boiler 175 klbs/hr • (1) 14.4 MW topping Steam Turbine Generator • (2) 100% Reciprocating Gas Compressors • (3) 50% Boiler Feed and Condensate Pumps • (2) 100% Circulating Water Pumps • (2) 100% Aux Cooling Pumps • (2) 100% Plant Air Compressors • (3) 50% Reverse Osmosis Trains

  12. 14.4 MW Steam Turbine (Elliott/Hyundai)

  13. 175 klbs/hr package boiler (Victory Energy)

  14. Boiler Feed Pumps (Goulds) & OTSG 2 (IST)

  15. Condensate, Aux Cooling & Circulating Water Pumps

  16. Reverse Osmosis Trains (US Water)

  17. Duct Burners on OTSG 1

  18. GE LM6000 PF/DLE Gas Turbine Package(Unit 1)

  19. Mezzanine Level Deaerators and Cooling Tower Piping

  20. Starting Up & Commissioning your own Plant!? • Construction firm lost Startup and Commissioning Manager 2.5 months before Commercial Operation date • Project team elected to have the Plant Engineer assume the role of Startup and Commissioning Manager • Due to project schedule challenges, BWL supplemented the startup and commissioning team with Operators, Instrument Controls Specialists, Controls Engineer, Project Engineer, Maintenance Supervisors, Plant Manager and a Trainer.

  21. Starting Up & Commissioning your own Plant!? (cont’d) • Major equipment suppliers (ie. GE gas turbines, Boilers, Reverse Osmosis trains, etc.) commissioned their equipment with field technicians supported by the BWL team • We made it!  $182 million plant built on time and on budget with a commercial operation date of July 1, 2013.

  22. Thank you Questions? Rob Hodge Plant Manager rah1@lbwl.com

More Related