CHCAT: F/A 18 E/F Drag Brace and NLG Testing. . Drag Brace Piston Status. Fatigue testing 50% complete. Endurance testing is 27% complete. When endurance testing is 50% complete, a tear down will occur for a formal inspection. Visual inspection has seen NO defects. NLG Testing.
E N D
Drag Brace Piston Status. • Fatigue testing 50% complete. • Endurance testing is 27% complete. • When endurance testing is 50% complete, a tear down will occur for a formal inspection. • Visual inspection has seen NO defects.
NLG Testing. • Testing will start the week of August 20/01
Tour • Both test rigs will be available for display on the Wed. August 29/01 tour.