1 / 16

GLAST Large Area Telescope LAT Pre-Shipment Review Thermal Vacuum Test Jesse Armiger

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope LAT Pre-Shipment Review Thermal Vacuum Test Jesse Armiger Thermal Vacuum Test Director Stanford Linear Accelerator Center. Agenda. Test Overview and Major Test Event Log Compliance To Requirements Correlation Results

admon
Télécharger la présentation

GLAST Large Area Telescope LAT Pre-Shipment Review Thermal Vacuum Test Jesse Armiger

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope LAT Pre-Shipment Review Thermal Vacuum Test Jesse Armiger Thermal Vacuum Test Director Stanford Linear Accelerator Center Thermal Vacuum Test

  2. Agenda • Test Overview and Major Test Event Log • Compliance To Requirements • Correlation Results • Thermal Test Observations • Summary Thermal Vacuum Test

  3. Test Picture Thermal Vacuum Test

  4. Test Overview Thermal Vacuum Test

  5. Compliance to Requirements • LAT successfully completed Thermal Vacuum Testing • 40 day test was successfully completed with only EGSE issues • Successfully tested LAT at Proto-Qual levels • Verified thermal subsystem performance • Heaters • Heat pipes • Temperature sensors • Thermal Interface/Unit Mounting • Thermal analysis correlation • No abnormal observations • Complete by October 30 Thermal Vacuum Test

  6. Heater System Verification • Survival heater system maintained all temperatures within limits during Survival Thermal Balance • Unregulated and regulated feeds at minimum voltage • Unregulated feed at 25v and regulated feed at 27v • Grid heaters cycled at primary set points • Radiator Antifreeze heater duty cycle under review • Demonstrated primary VCHP heaters could close Radiators at 70% power • Functionally demonstrated all primary and redundant Radiator antifreeze and Grid heaters • Demonstrated TCS could maintain RIT at all operational levels Thermal Vacuum Test

  7. Heat Pipes and Thermal Interfaces • Heat Pipes • All Heat Pipes functioned normally • DSHP and XLATs operated as expected • VCHPs opened/closed Radiators as designed • Interfaces • No baseplate outliers Thermal Vacuum Test

  8. Unit Temperature Distribution Hot Thermal Balance Thermal Vacuum Test

  9. Preliminary Correlation 1/2 • Test results show good correlation between sink temperature predictions and input Watrod power • ACD model received from GSFC uncorrelated – ACD MLI effectiveness needs evaluation • ACD temperatures have impact on LAT correlation • Generally ACD tile temperatures higher than predictions (>5o C) in all cases • Higher tile temperatures lead to higher tracker temperatures • Grid heaters need to be modeled with individual thermostat set points for each circuit Thermal Vacuum Test

  10. Preliminary Correlation 2/2 • Hot Case - Temperatures generally lower than predicted • Cold Case – • Temperatures generally higher than predicted • Radiator Anti-freeze and grid survival heaters off • VCHP heaters • 9.7 watts to maintain RIT between -6oC and -5oC (23% duty cycle) • Locked on to maintain RIT between -1oC and 0oC • Survival Mode • Temperatures generally higher than predicted • Radiator Anti-freeze and grid survival heater use about 7 amps • Heater Power use higher than predicted Thermal Vacuum Test

  11. Test Predictions vs. Actuals Thermal Vacuum Test

  12. Thermal Test Observations • ACD temperature sensor exceeded its red alarm limit of 40C (unit proto-qual = 40C) • This sensor reached a maximum of 42C; the temperature excursion may have been caused by sensor malfunction • This was not unexpected because the ACD is bounded by a thermal blanket on one side and Tracker Towers with goal temperatures of 40-45C • The ACD project manager has indicated that this temperature poses no risk to the ACD • Recommend an ACD red limit of 45C for the observatory test Thermal Vacuum Test

  13. Thermal Test Observations • LAT start up sequence from cold survival NCR #? • The normal start up sequence involves incrementally powering up the LAT in a manner which does not exceed the power budget • The planned sequence involved powering up the TCS last but it turned out that this step had to be performed earlier in order to stay within the budget • This minor change will be documented and implemented in the normal turn on sequence to be performed during observatory level testing Thermal Vacuum Test

  14. Summary • The LAT thermal vacuum test was accomplished ahead of schedule and without any major incident. Three thermal balances (hot, cold and survival) and four thermal cycles were performed. • Thermal data readout by VSC was very noisy and inaccurate; this caused hardship during the test. • Minor incidents were corrected efficiently. • Complete LAT Thermal Vacuum test report by October 31. • Include thermal model correlation Thermal Vacuum Test

  15. Major Thermal Vacuum Test Events 1/2 Performance Testing Thermal Vacuum Test

  16. MajorThermal Vacuum Test Events 2/2 Thermal Cycling Thermal Vacuum Test

More Related