An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. VIABILITY – A LOCAL AUTHORITY PERSPECTIVE Jim Cliffe Planning Obligations Manager Bristol City Council

  2. Areas covered • Implementing CIL • Approach to site specific viability appraisals • Why the affordable housing policy compliant percentage is not always achieved

  3. CIL – Implementation • Keep it simple – there are not many benefits to making CIL complicated but there are dis-benefits: • Higher risk of successful challenge • It will almost certainly take longer to implement • Higher chance of errors in calculating, monitoring and enforcing CIL

  4. CIL - Implementation Don’t be greedy – be generous with developers costs, cautious with sales values, and leave a significant viability buffer

  5. CIL - Implementation • When setting residential CIL rates we followed the following mantra “Our CIL rates will be set at a level that will not make residential development that is currently policy compliant and viable, unviable” ….. • ….. and we didn’t worry too much about residential development that was unviable even with no CIL

  6. CIL - Implementation Think very carefully about how to deal with strategic sites – they may well need a lower or even a £nil CIL rate due to the level of on-site infrastructure required. Swindon and South Gloucestershire are good examples of Councils that have taken this approach

  7. What the inspector wants

  8. CIL viability information – how it helps you Your CIL viability study will provide large amounts of information on costs and values that you can use as a reference point in dealing with site-specific viability appraisals.

  9. Other viability information available due to CIL • Once CIL is implemented you need access to BCIS data, which provides up to date costs data • Sales prices are available on the Land Registry web site, and for all consents granted after CIL was implemented, the GIA is known. Therefore you can start building up a dataset of sales values per square metre

  10. Site Specific Viability – Issues for Bristol • We had no structured process in place for dealing with viability appraisals • We spent lots of time and resource disputing viability appraisals, whilst making little progress towards resolving differences • We sometimes forgot the bigger picture and spent too much time and effort focussing on the cost of taps and flooring

  11. 3 Stage approach – Stage 1 • Identify issues of concern • Commission consultant • Consultant assesses viability appraisal and reports back to Council – no meetings with applicant at this stage • If necessary, consultant undertakes their own appraisal based on nil affordable housing, to see what excess there is that could be applied to affordable housing

  12. 3 Stage approach – Stage 1 • If the consultant agrees with the level of affordable housing the applicant claims can be afforded the issue is concluded. • Stage 1 is completed within a month

  13. 3 Stage approach – Stage 2 • Meetings held with applicant to try to understand areas of difference and see if an agreed position can be reached • Stage 2 has a cut off time of a month

  14. 3 Stage approach – Stage 3 • If agreement cannot be reached, the Council offers independent arbitration to look solely at the areas of disagreement, and agrees to accept the view of the arbiter • Council and applicant each put their case to the arbiter in writing and have the option of one meeting with the arbiter • Stage 3 is completed within a month

  15. Benefits of the staged approach • We don’t spend months arguing about areas of difference whilst making no progress • Applicants know where they stand • Helps the Council deliver consents in a timely manner • Offer of arbitration lessens the chances of appeals on viability grounds

  16. Why do we not always secure policy compliant levels of affordable housing? • Challenging sites • Government Initiatives • Impact of RICS Professional Guidance • Rising GDV often goes hand in hand with rising Site Values and Build Costs

  17. Brownfield Sites • Urban brownfield sites often have high Existing Use Values, which translates to high Site Values • There is less of an uplift in value on such sites for residential uses. • Development costs tend to be higher due to the constrained nature of the sites • Therefore there is less potential to secure affordable housing from brownfield sites

  18. Greenfield Sites • Suburban and rural greenfield sites often have low Existing Use Values. • There is more of an uplift in value on such sites for residential uses. • Sites tend to be large and less constrained meaning that there are economies of scale and fewer abnormal design costs, therefore costs tend to be lower • Consequently there is more potential to secure affordable housing from greenfield sites

  19. Government Policy / Initiatives The following have all had an adverse impact on the ability of Local Authorities to secure affordable housing: • National Planning Policy Framework (2012) • Section 106 BA (2013) • Vacant Building Credit (2014) Also, and most significantly: • RICS Professional Guidance (Financial Viability in Planning) (2012)

  20. Market Value / Site Value • Market Value = the price agreed for the land between a willing buyer and a willing seller • Site Value = Market Value but taking account of Development Plan Policies

  21. Impact of RICS Guidance – General Hospital example Had the General Hospital viability been before publication of the RICS Guidance, the Site Value would have been approx£2,500,000 (Existing Use Value of £2,000,000 plus £500,000 incentive for the landowner to bring the site forward). As it was after publication of the RICS Guidance, the Site Value was approx£6,250,000, as that was the price paid for the site, and other bidders were prepared to pay a similar price.

  22. Rising Residential Values Increasing residential values help viability but: • Profits are based on value so the actual profit also increases • Build Costs are also increasing (up 13% nationally in the past two years) • Fees and contingency are based on a percentage of costs so these also increase • Land is changing hands for higher prices (up 15% nationally in the past two years) as house-builders are competing for a scarce resource

  23. Hypothetical ExampleScheme value increases by 17% / Site value increases by 15% / Build costs increase by 13%

  24. General Observations • Flatted developments may deliver less affordable housing than estate developments as they contain approx 20% unsellable floorspace (lift shafts, stairwells, corridors etc) and have higher build costs • Experience suggests it is possible in the current market to secure 30% affordable housing on suburban estate developments on clean sites, but in and around the City Centre viability is much more challenging