1. CLIC cost drivers and mitigation issues 2. Status of the CLIC configuration & cost estimate. Philippe Lebrun CLIC-ILC WG on Costs 26 February 2010. Timeline. Special meeting on 11 December 2009 on CLIC baseline Review the baseline and alternatives

astro
Télécharger la présentation

1. CLIC cost drivers and mitigation issues 2. Status of the CLIC configuration & cost estimate

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 1. CLIC cost drivers and mitigation issues2. Status of the CLIC configuration & cost estimate Philippe Lebrun CLIC-ILC WG on Costs 26 February 2010

  2. Timeline • Special meeting on 11 December 2009 on CLIC baseline • Review the baseline and alternatives • Identify cost drivers and cost mitigation issues • List baseline items and decide between • Adopted for the CDR • Envisaged for the CDR after additional work (until end March 2010) • Alternative mentioned in the CDR, to be developed for the TDR • Not adopted • Special meeting on 29 January 2010 on CLIC baseline modifications • Progress towards definition of CLIC baseline form the CDR • End March 2010 • Baseline frozen for the CDR, enabling consistent cost estimate

  3. Cost drivers & potential saving options Main and drive beam production Cost impact L Order of 10 MCHF M Order of 100 MCHF H Order of 1 BCHF

  4. Cost drivers & potential saving optionsTwo-beam modules [1/2] Cost impact L Order of 10 MCHF M Order of 100 MCHF H Order of 1 BCHF

  5. Cost drivers & potential saving optionsTwo-beam modules [2/2] Cost impact L Order of 10 MCHF M Order of 100 MCHF H Order of 1 BCHF

  6. Cost drivers & potential saving options Interaction regions Cost impact L Order of 10 MCHF M Order of 100 MCHF H Order of 1 BCHF

  7. Cost drivers & potential saving options Infrastructure and services Cost impact L Order of 10 MCHF M Order of 100 MCHF H Order of 1 BCHF

  8. Cost estimate status

  9. CLIC @ 3 TeV

  10. CLIC @ 500 GeV