SPS YETS 2017/2018 Planning meeting (No.1) 13/09/17

SPS YETS 2017/2018 Planning meeting (No.1) 13/09/17. David Mcfarlane. Topics. TS3-SPS-2017. YETS 2017/2018 dates. Key Dates & Schedule for week 1. YETS AUG test draft dates. COORDINATION SECURITE PENDANT LES ARRETS DU SPS ) . Rappel EN-EL. ECRs.

bculp
Télécharger la présentation

SPS YETS 2017/2018 Planning meeting (No.1) 13/09/17

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPS YETS 2017/2018Planning meeting (No.1)13/09/17 David Mcfarlane EN-ACE D. Mcfarlane

  2. Topics • TS3-SPS-2017. • YETS 2017/2018 dates. • Key Dates & Schedule for week 1. • YETS AUG test draft dates. • COORDINATION SECURITE PENDANT LES ARRETS DU SPS). • Rappel EN-EL. • ECRs. • Future meetings & presentation of group planning's. • What information I now need from you. • External visitors. • Access rights and safety equipment. • Important group and project contacts. • A.O.B. EN-ACE D. Mcfarlane

  3. TS3-SPS-2017 • The next technical stop will be on: Tuesday the 19thSeptember. • It will last for 24 hours. • Which means 1 full working day of access. • You can create an IMPACT using the intervention period (TS3-SPS-2017) • If you do not use this intervention period it will not be approved!!!!! • All IMPACTs will be approved by me by the end of this week. • Access will be from 08:30 onwards. • Access will be until 18:00 unless specifically requested. • The Lift at BA1 will be out of service from 08:30 to 11:30. • No access into BA1 and BA2 in the morning. (RP conditions) • The lift at BA5 will be out of service from 13:00 to 17:00. Access can be via the stairs or BA4 or BA6. EN-ACE D. Mcfarlane

  4. SPS Lift Maintenance during TS3

  5. ECX5/ECA5 DO NOT FORCE THE DOORS BETWEEN ECX5 & ECA5

  6. 1470895 4.0 RELEASED • Year-End Technical Stop 2017-2018 References: • 15 weeks beam to beam stop for the LHC • Xenon physics for the North Area • 5 weeks for commissioning (hardware tests + cold check-out + beam commissioning) in the injectors (PSB, PS, SPS) before beam ready for the LHC • 2 to 3 days of diagnostic tests in the injectors with machine closed

  7. YETS 2017/2018AUG Tests Draft Planning Can you please check if these dates are ok with your SPS YETS planning ? (And see if there are some blocking points or not..) EN-ACE D. Mcfarlane

  8. Key dates • Beam off at 06:00 on Monday the 18th December • Access into BA7, TI2, TAG41, TAG42 & TI8: • Monday the 18th December until Friday the 23rd February 2018. • 8 weeks of access. • Access into BA3,4,5 & 6: • Thursday the 21st December until Friday the 23rd February 2018. • 7.4 weeks of access. • NO works are currently planned during the 2 week Xmas vacation. • XMAS holidays: Saturday the 23rd December to Sunday the 7th January inclusive • Access into BA1 & BA2: • Monday the 8th January until Friday the 23rd February 2018. • 7 weeks of access. • 3weeks foreseen for EPC tests and cold-checkout by OP. • SPS will take beam from the PS on Monday the 19th March 2018, followed by 1 week for beam setup. • SPS ready to give beam to the LHC on Monday the 26th March 2018! EN/ACE/OSS BE/OP EN-ACE D. Mcfarlane

  9. Current schedule for week 1(18th to 22nd December) • Monday 18th December • Beam off 06:00Hrs • Access possible in BA7, TI2, TAG41, TAG42, TI8. • All water and power to remain on (Machine is in standby) • SPS ring closed to everyone except: • RP: will survey the tunnel • Magnet team: to remove covers on the magnets. • Tuesday 19th December • Magnet team conduct tests • All water and power to remain on (Machine is in standby) • SPS closed (to everyone except Magnet team) • Wednesday 20th December • Magnet team conduct tests • All water and power to remain on (Machine is in standby) • SPS closed (to everyone except Magnet team) • Thursday 21st December • Water can be cut and the machine electrically isolated • BA1 and BA2 remain closed for RP cool down • BA3, BA4, BA5, BA6, BA7 are open for general access • Friday the 22nd December • BA1 and BA2 remain closed for RP cool down • BA3, BA4, BA5, BA6, BA7 are open for general The SPS is effectively still in run mode. General access into the SPS begins. EN-ACE D. Mcfarlane

  10. RESUME DU FONCTIONNEMENT DE LA COORDINATION SECURITE PENDANT LES ARRETS DU SPS(Reference HSE / GSI – WS-1) Coordination sécurité pour les travaux dans les complexes (PS, SPS et LHC) • Assurée par l’unité organique responsable de la coordination de l’arrêt (EN/ACE/OSS-COS) • Réalisée via • la planification, • la validation des interventions (IMPACT) • la présentation à chaque réunion de coordination d’un tableau de suivi des VIC VIC (visite d’inspection commune) • Organisée par le superviseur de travaux, sur sa propre initiative ou sur demande de l’unité organique en charge de la coordination • Présence obligatoire du superviseur de travaux et de l’intervenant – Présence sur demande d’un représentant d’une fonction de sécurité du CERN (EROS ou expert HSE) • Rédaction d’un compte-rendu de VIC via IMPACT Suivi des travaux • Assuré par le superviseur de travaux. • Retour d’information à l’unité organique, au minimum chaque semaine lors de la réunion de coordination. • Par les représentants de l’unité organique EN-ACE D. Mcfarlane

  11. Rappel EN/EL • Les DIC/DIF/DIR/DFP DEFINITIVES sont à transmettre au plus tard le 15.09.2017 accompagnées des documents nécessaires à la réalisation des travaux. • Les demandes arrivées après se verront dans le meilleur des cas traitées dans un second temps, voir pas du tout.

  12. Rappel EN/EL-FC • Exemple de travaux évoqués mais pour lesquels les DIC n’ont pas encore été reçues ou encore incomplètes donc non traitables: • Fire Safety (sprinkler, autres) • Nouveau GSM (BA3/BA4) • BAF3 câblage vers les bâtiments annexes

  13. SRRs and ECRs for the SPS SPS planning and coordination meeting for YETS 2017-2018 Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

  14. Outline • SPS ECRs for YETS 2017-2018: status • All known activities needing ECRs • ECRs received • ECRs expected -drafts not yet submitted to EN-ACE-CL- • SRRs and ECRs: reminder • Roadmap • Tips Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

  15. SPS ECRs for YETS 2017-2018: status All known activities needing ECRs *The Modification of the SPS sectorization was described in SPS-V-EC-0005 (v.1.0 Released). The sectorisation in BA3 will be performed during the YETS  a different ECR should not be needed. Total number of ECRs needed = 14 Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

  16. SPS ECRs for YETS 2017-2018: status ECRs received 3 ECRs are now under approval. 1 ECR drafted, not yet ready to be sent for approval. Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

  17. SPS ECRs for YETS 2017-2018: status ECRs expected -drafts not yet submitted to EN-ACE-CL- 10 ECRs not yet received!! Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

  18. SRRs and ECRs: reminder Roadmap ECRs submission to configuration team (EN-ACE-CL) 2 months beforethe approval deadline! Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

  19. SRRs and ECRs: reminder Tips • All changes to the machine that will impact the beam shall be documented by SRRs/ECRs: • SRR: Space Reservation Request (“light ECR”) • ECR: Engineering Change Request • Templates available on: • https://quality.web.cern.ch/templates-requests • To be sent to the SPS configuration manager: • Sonia.Bartolome@cern.ch or • ecr-configuration@cern.ch Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

  20. Future meetings It has been requested by the group leaders for each group to present their planned works to the coordinators of each machine. Therefore the table below will show which group will present at what SPS planning meeting. EN-ACE D. Mcfarlane

  21. What I need from you. • I need your planning! • not simply a list of works. • Identify the location of the works • Surface, Underground, which sector (eg, 3-, LSS4 etc.) • Any works under the false floors in the suface BA’s MUST be highlighted! • Identify the duration of the works (in days or weeks) • Try to plan nothing for the final week of the shutdown! • Your target is to complete your works by February 16th! • Identify any impact of your works. • Access blocked, no transport through the zone, must work alone, etc. • Identify what you need. • Power, water, vacuum/transport support etc. • Identify what type of works it is. • LIU, Maintenance, Consolidation. • If you need some information from any other group, explain what you want and WHEN you need this information by. EN-ACE D. Mcfarlane

  22. Other presentations EN-ACE D. Mcfarlane

  23. External Visitors • If you have any external personnel needing to access the SPS for visits before starting works then you need to read the following document: "Etapes à suivre pour organiser des visitesprofessionnellesdans les installations faisceaux" by CHRISTELLE GAIGNANT • Link: https://edms.cern.ch/document/1281098/2.5/TAB3 EN-ACE D. Mcfarlane

  24. Access rights and safety equipment EVERYONE who enters the SPS MUST have the following: • Completed the correct courses. (sir.cern.ch) • CERN Safety Introduction. • Electrical Safety Awareness. (19 choices) • Self Rescue Mask Training. (4 choices) • CERN – Beam Facilities. • SPS – Machine. • The correct access authorisation (via EDH).CHECK YOUR ACCESS RIGHTS HAVE NOT EXPIRED!!!! • Zone Code “SPS” for access into the SPS • Zone Code “NA_TARG” for access into BA80 • Zone Code “TAG41 - AWAKE (ex-CNGS) (TAG41)” for access into the old CNGS areas • Zone Code “SPS-KN-000” for “AutorisationconduiteRTL” • Zone Code “SPS-KN-001” for “SPS Shutdown Padlock” (only used during Long Shutdowns) • Safety shoes. • Biocell. • Electronic dosimetre. • Passive dosimetre. (All contractors must have an additional company passive dosimetre!!) • Helmet plus Light. • A valid approved IMPACT. (with their name included on this IMPACT) • They must know the number of this IMPACT. Please note that personnel are not allowed to work in the tunnel alone!! EN-ACE D. Mcfarlane

  25. Important Contacts • Useful Contact Numbers • SPS Coordination Team • David MCFARLANE- 164247 • Franck BAIS – 165467 • Aurelio Berjillos BARRANCO - 167850 • Control Room • SPS CCC – 77500 • TI CCC – 72201 • CSA - 62511 • RP • Christophe Tromel – 163199 • Angelito Herve – 163168 • Nadine Conan (BA1) – 160641 • Kurt Weiss (BA7) -160759 • EROS Engineering Referent for Operational Safety • Emmanuel Paulat – 163870 • John Etheridge - 164647 EN-ACE D. Mcfarlane

  26. Group contact persons. (1) EN-ACE D. Mcfarlane

  27. Group contact persons. (2) EN-ACE D. Mcfarlane

  28. A.O.B. Salut David, Peux-tu STP montrer l’image jointe cet après-midi en réunion et demander si la structure (qui ne doit plus servir, à confirmer…) peut être démontée ? Merci. Fred. EN-ACE D. Mcfarlane

  29. Useful websites Link to SPS planning meetings on INDICO https://indico.cern.ch/category/8122/ Link to the SPS planning https://pwa.cern.ch/Projects-Accelerator-Complex-Schedules/Projects.aspx Roadmap: Schedule beyond LS1 http://ls1ls2.web.cern.ch/ Next meeting 27/09/2016 30-7-010 EN-ACE D. Mcfarlane

  30. EN-ACE D. Mcfarlane