1 / 38

Beach Nourishment Project Town of Kitty Hawk, North Carolina

Beach Nourishment Project Town of Kitty Hawk, North Carolina Coastal Planning & Engineering of North Carolina November 3, 2014 Ken Willson. Project Overview Map. Kitty Hawk Project Area. Kitty Hawk Stated Purpose:.

beachj
Télécharger la présentation

Beach Nourishment Project Town of Kitty Hawk, North Carolina

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Beach Nourishment Project Town of Kitty Hawk, North Carolina Coastal Planning & Engineering of North Carolina November 3, 2014 Ken Willson

  2. Project Overview Map

  3. Kitty Hawk Project Area

  4. Kitty Hawk Stated Purpose: • Reduce the vulnerability of public infrastructure including NC 12, town roads between NC 12 and U.S. Highway 158, and utilities to storm-induced erosion; • Reduce flooding experienced in many non-oceanfront areas throughout the Town during ocean over wash conditions, including portions of NC Highway 12 and U.S. Highway 158; and • Reduce the vulnerability of homes within the Town that front the Atlantic Ocean and are exposed to wave events during nor’easters and other large storm events as well as natural trends.

  5. Storm Damage Reduction to Infrastructure

  6. Flood Damage Reduction to Non-Oceanfront Areas

  7. Storm Damage Reduction to Oceanfront Homes

  8. Storm Damage Reduction Project

  9. Storm Damage Reduction Project Example Berm Width 6.0 ft. NAVD88 Dune Design Beach

  10. Storm Damage Reduction Project Example Constructed Beach Fill

  11. Post-Construction Adjustment in 1-3 years Storm Damage Reduction Project Example

  12. Storm Damage Reduction Project Example Advance Fill Design Beach

  13. Storm Damage Reduction Project Example Berm Width 6.0 ft. NAVD88 Dune Loss of Advance Fill In 5-10 years Design Beach

  14. Storm Damage Reduction Project Example • When structures are seaward of the dune, more sand is required to • construct the design seaward of the structures.

  15. Storm Damage Reduction Project Example Built in front of structures Berm Width 6.0 ft. NAVD88 Dune +13.0 ft. Design Beach • When structures are seaward of the dune, more sand is required to • construct the design seaward of the structures.

  16. Storm Damage Reduction Project Example Tie into existing dune Berm Width 6.0 ft. NAVD88 Dune +13.0 ft. Design Beach • When structures are seaward of the dune, more sand is required to • construct the design seaward of the structures.

  17. 81% Increase

  18. Berm Only Option 50’ Berm Width 6.0 ft. NAVD88 Design Beach

  19. Minimal Dune Design - 12 30’ Berm Width 6.0 ft. NAVD88 10’ Dune Width +12.0 ft. Design Beach

  20. Storm Damage Reduction Analysis • Reduce the vulnerability of public infrastructure including NC 12, town roads between NC 12 and U.S. Highway 158, and utilities to storm-induced erosion; • Minimal simulated impact to the road given existing conditions • No impacts to the road with berm only or MDD-12 design. • Reduce the vulnerability of homes within the Town that front the Atlantic Ocean and are exposed to wave events during nor’easters and other large storm events as well as natural trends; • 122 structures impacted given existing conditions. 48% reduction with berm only and 64% reduction with MDD-12 design

  21. Runup Evaluation Calculated Runup Elevation

  22. Runup Evaluation Calculated Runup Elevation

  23. Runup Evaluation Runup Elevation

  24. Runup Evaluation Calculated Runup Elevation Without Project With Project Design Beach Design Beach

  25. Runup Evaluation Calculated Runup Elevation Without Project With Project Design Beach Design Beach Design Beach Design Beach

  26. Runup Evaluation Calculated Runup Elevation Without Project With Project Design Beach Design Beach Design Beach Design Beach

  27. Runup Evaluation Runup Elevation = Lower Than Elevation of the Road

  28. Annual Event Runup Analysis • 12 ft. Dune Design and 50 Ft. Berm: • 69.8% to 92.7 % reduction in length of shoreline exceeded by calculated runup.

  29. 5 – Year Event • “Kill Devil Hills” Design – 15 ft. high / 20 ft. wide dune, fronted by a 40 ft. berm • Advances Shoreline 100 ft. (Average) • Requires 3.19 Million CY • 100% increase in Volume • Additional $15 Million • 100 – Ft. Berm Only Design • Advances Shoreline 100 ft. • Requires 2.93 Million CY • 84% increase in Volume • Additional $12.5 Million • What could we do with another $2 Million - $3 Million

  30. 5 – Year Event • $ 3 Million = ~ 16 CY/Ft. More Sand • Design: Slightly Over a 60 ft. Design Berm • Annual Event - 73.4% to 98.7 % reduction in length of shoreline exceeded by calculated runup. • 5-Year Event – 39.6% to 72.2% reduction in length of shoreline exceeded by calculated runup.

  31. Runup Evaluation Runup Elevation

  32. 5 – Year Event • $ 3 Million = ~ 16 CY/Ft. More Sand • Design: Slightly Over a 60 ft. Design Berm • Annual Event - 73.4% to 98.7 % reduction in length of shoreline exceeded by calculated runup. • 5-Year Event – 39.6% to 72.2% reduction in length of shoreline exceeded by calculated runup. • With 14.0 ft. NAVD Starter Dune these numbers become 100%

  33. 60 Ft. Berm Design • 60 Ft. Berm; 14.0 ft. NAVD “Starter Dune”; Sand Fencing • Main Fill Length – 18,900 ft. (3.58 miles) • 1000 Ft. Taper on North End • Fill Density ~ 95 cy/ft. to ~100 cy/ft. • Total Volume = ~1.91 Million Cubic Yards • Project Cost = ~$20.5 Million

  34. Schedule

  35. Beach Nourishment Project Town of Kitty Hawk, North Carolina Questions?? Ken Willson – Kenneth.Willson@cbi.com

  36. Kill Devil Hills Project Area

  37. Duck Project Area

More Related