1 / 14

MTest Pixel Telescope – Status Update

MTest Pixel Telescope – Status Update. David Christian January 8, 2008. Detector Status/Plan. Hybrid development complete 11 good hybrids in hand Balance waiting for LANL PO to VTT Delivery Jan – Feb (less schedule risk than before) Module development

becca
Télécharger la présentation

MTest Pixel Telescope – Status Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MTest Pixel Telescope – Status Update David Christian January 8, 2008

  2. Detector Status/Plan • Hybrid development complete • 11 good hybrids in hand • Balance waiting for LANL PO to VTT • Delivery Jan – Feb (less schedule risk than before) • Module development • 4x HDI prototype received & tested (12 good parts in hand). • Production purchase requisition is working its way through the FNAL bureaucracy (Feb delivery expected).

  3. Detector Status/Plan continued • Plane/Station development: • First prototype plane being tested (one of three pixel modules mounted so far). • SLINK pcb prototype has been received, stuffed, & testing has begun (Nevis). • Box/Area: • Mechanical design to be coordinated with needs of LHCb VELO (1st users) - waiting for MOU to be signed (momentarily).

  4. Plane prototype on CMM

  5. 1st module ready to test

  6. DAQ Status/Plan • DAQ Hardware/Firmware (Nevis) • PCI interface ~90% complete (trigger/timing hooks not written) • Router ~70% complete (trigger/timing, implementation of merges, integration of DUT?) • SLINK • Design complete. • Prototype fabricated; tests begun. • On the optimistic critical path - hoping to begin testing with a prototype station (or at least a plane) ~ Feb 1.

  7. Software Status/Plan • Online software (FNAL, Syracuse, UNM?) • Core low level routines exist & have been tested. • Need to specify online, including online/offline boundary, write & test code. • On the optimistic critical path • Offline software (Syracuse, FNAL?, UNM?) • Data unpacking • Alignment • Tracking, integration of DUT • On the optimistic critical path • This task has lagged. Strategic decisions to be made in the next 2-4 weeks.

  8. Schedule • Focus on full telescope ASAP. February doesn’t look possible. March?

  9. MTest Telescope • Constructed using “BTeV pixels” • Pixel size = 50m x 400m (600m) • Oriented to provide “precision-x” or “precision-y” measurements.

  10. Layout • Aperture ~ 3.5cm x 3.5cm • 4 – 6 stations y y Beam x x

  11. Nomenclature • Station = 2 planes & an SLINK • Plane = 3 modules mounted on a TPG heat spreader • Module = hybrid pixel detector glued & wire-bonded to a High Density Interconnect (Kapton flex circuit) • Hybrid = pixel sensor bump bonded to 4 FPIX2.1 ASICs

  12. DAQ Overview ROUTER SLINK Trigger/timing signals Twin-ax (sATA) Removable disk Fiber PCI Interface LINUX pc Trigger/timing signals

  13. DAQ • SLINK communicates with 2x3x4=24 FPIX2.1 chips & with ROUTER. • Relays commands & responses • Collects data • Deserialize (digital phase follower) • Time order & construct data blocks w/extended time stamp & chip ID headers • Hierarchy of 2-way data merges

  14. DAQ - continued • ROUTER communicates with PCI interface & SLINKs and (optionally) DUTs • 12 sATA ports, 4 RJ45 ports • Relays commands & responses • Collects data • Hierarchy of 2-way data merges (same logic as SLINK) • PCI Interface communicates with ROUTER & pc • Relays commands & responses • Uses 3 CSRs & 3 ring buffers in the pc main memory (64 MB)

More Related