An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Responding to Wind Farm Applications Ian Aikman Major Applications, Review & Enforcement Manager Scottish Borders Council

  2. Scottish Borders Wind Energy • Commercial Windfarms: - Approved - 318 turbines generating 689MW - Public Inquiry/ Appeal - 3 sites for 61 turbine (213 MW) - 8 Applications lodged for further 121 turbines (329WM) - PAN’s for further 60 further turbines (147MW) • Feed In Tariff Schemes (less than 5MW) - Approved 88 turbines (5.55MW) - Applications for further 21 turbines (3.08MW) • Screening Opinions - 49 • Scoping Opinions - 47

  3. Information Overload • Number of applications • Environmental Impact Assessment • Technical nature of information lodged • Available on Public access and CC’s get hard copy • Information available on web

  4. The Planning Act • Section 25 Planning Act “Where in making any determination under the planning Acts, regard is to be had to the development plan, the determination shall be made in accordance with the plan unless material considerations indicate otherwise.” • Consolidated Structure Plan 2001 – 2018 & Local Plan 2011 - Policy D4

  5. Material Considerations • Scottish Planning Policy (para 182 – 195) • Web based Planning Guidance (Replacing PAN45) – SG and SNH • Supplementary Planning Guidance on Wind Energy May 2011 • Views of Consultees • Planning history • Legitimate public concern or support – provided expressed on relevant planning matters

  6. Non Material Considerations • Protection of Private Interests • Loss of views • Loss of property value • Competition between businesses • Personal Circumstances of Applicant • Moral Considerations • The Applicant’s lack of ownership of a site. • Issues governed by other legislation • Title Issues

  7. Key Planning Issues • Landscape character impact – Landscape Assessment • Visual impact – receptors, cumulative impact • Traffic or access problems • Residential amenity (noise, visual impacts, shadow flicker) • Associated infrastructure impact – access roads etc • Impact on the natural or built environment

  8. Conclusions • Focus of key significant impacts of the development • Avoid wider policy reference • Clear and concise comments on planning grounds • Discuss with case officer • Landscape and visual impact will be most critical issues

  9. Questions?