1 / 48

PPL Plaza Allentown, PA

PPL Plaza Allentown, PA. Timothy Stauffer Construction Management. Project Overview. Location: Allentown, PA Size: 260,000 SF Cost: $30 million Height: 8 floors Occupancy: Commercial Office, Retail Building Features: Downtown Location LEED Gold Rating (tentative) Green Roof

brosh
Télécharger la présentation

PPL Plaza Allentown, PA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PPL PlazaAllentown, PA Timothy Stauffer Construction Management

  2. Project Overview • Location: Allentown, PA • Size: 260,000 SF • Cost: $30 million • Height: 8 floors • Occupancy: Commercial Office, Retail • Building Features: • Downtown Location • LEED Gold Rating (tentative) • Green Roof • Winter Gardens • 8 Story Central Atrium • High Tech Energy Trading Floors

  3. Presentation Outline • Existing Building Conditions • Areas of Investigation • Raised Access Floor - (AE Breadth Area) • Raised Core: Structural Redesign - (AE Breadth Area) • Green Roof Construction • Rainwater Retention System • Construction Manager Involvement Research • Conclusions

  4. Presentation Outline • Existing Building Conditions • Areas of Investigation • Raised Access Floor - (AE Breadth Area) • Raised Core: Structural Redesign - (AE Breadth Area) • Green Roof Construction • Rainwater Retention System • Construction Manager Involvement Research • Conclusions

  5. Project Team • Owner: Liberty Property Trust • Main Tenant: PPL Resources (30 year lease) • Architects: • Design Architect: R.A.M Stern Architects • Architect of Record: Kendall Heaton Associates • Engineers: • Structural: Thornton Thomasetti Engineers • MEP: H.T. Lyons (design-build) • Construction Manager: L.F. Driscoll, Co. • Project Delivery Method: CM at Risk • Main Contract: GMP (Guaranteed Maximum Price)

  6. Project Estimate

  7. Project Schedule

  8. Project Schedule • Construction Dates: Feb 1, ‘02-Mar 19, ’03 • Compressed Construction Schedule: 14 months • High liquidated damages • $15,000 per day

  9. Presentation Outline • Existing Building Conditions • Areas of Investigation • Raised Access Floor - (AE Breadth Area) • Raised Core: Structural Redesign - (AE Breadth Area) • Green Roof Construction • Rainwater Retention System • Construction Manager Involvement Research • Conclusions

  10. Raised Access Flooring(AE Breadth) • Existing design: • Raised access floor design floors 7 & 8 • Mechanical: underfloor supply air on floor 8 • Why? • Suggested by Kendall Heaton Associates • High tech energy trading floors needing frequent upgrades • Limited to floors 7 & 8 due to cost impact

  11. Raised Access Flooring(AE Breadth) • Proposed redesign: • Raised access floor design extended to include all office floors (floors 2-8) • Mechanical: underfloor supply air on floors 2-8 • Benefits: • Simplified MEP construction • Quicker renovation • Reduced office churn costs • Indoor Air Quality improvements • Improved occupant comfort

  12. Raised Access Flooring(AE Breadth) Raised Floor Design • 12” high floor • 24”x24” flooring tiles • Modular carpeting tiles Electrical/Communication • Modular Components • Control boxes • Utility boxes • Quick connect cables • Shared distribution

  13. Raised Access Flooring(AE Breadth) HVAC Design • Displacement distribution system • Supply at floor, return at ceiling • Convection system – air rises as it warms • Carries contaminants away from occupants • Supply Air • Lower velocity • Higher temperature • 55° -> 65°

  14. Raised Access Flooring(AE Breadth) HVAC Design • Base building system • Keep current fans and chillers • Decreased fan load due to decreased ductwork • VAV boxes with reheat required on each floor • Higher supply temp • Dehumidification

  15. Perimeter Zone Raised Access Flooring(AE Breadth) HVAC Design • HVAC zones – at least 9 • Central • Unducted • Static air terminals – constant volume • Perimeter • Semi-ducted • VAV air terminals & reheat boxes • Corner • Similar to perimeter • Enclosed office (perimeter) • Enclosed office(non-perimeter) • Conference Room • Fully ducted Perimeter Corner Corner Perimeter Perimeter Central Corner Corner Perimeter

  16. Raised Access Flooring(AE Breadth) System Concerns • Problem: • Increased floor to floor height • Solution: • Bulkheads around girders • Problem: • Drafts/Cold feet • Solution: • Use air terminals with manual air volume control • Locate air terminals between workspaces

  17. Raised Access Flooring(AE Breadth) Initial Cost and Schedule Impact • First Costs • $3.67 per SF • $820,000 total • Schedule • Raised floor construction • Original: 24 days • Revised: 94 days • Additional: 70 days • MEP construction • 40% mechanical and electrical labor reduction • Original: 179 days • Revised: 145 days • Savings: 34 days • No impact to overall schedule

  18. Raised Access Flooring(AE Breadth) Churn Cost Savings • Materials costs virtually eliminated • 40% renovation schedule reduction • Churn Cost savings: • $11.81 per SF • Initial cost increase: • $800,000 • Office churn costs savings: • $1 million per year • 80% cost reduction • Payback Period: • 10 months

  19. Presentation Outline • Existing Building Conditions • Areas of Investigation • Raised Access Floor - (AE Breadth Area) • Raised Core: Structural Redesign- (AE Breadth Area) • Green Roof Construction • Rainwater Retention System • Construction Manager Involvement Research • Conclusions

  20. Raised Core Structural Redesign(AE Breadth) • Why? • Building core must be raised to be even with raised floor • Current Design • “filler” slab • 7th & 8th floors • Proposed new design • Beam and girder elevation adjustment • 2nd-8th floors

  21. Raised Core Structural Redesign(AE Breadth) Design • Beam and girder elevation increased within building core area • Welded angle connections between beams and girders • Beam and girder sizes remain the same • No change in live and dead loads • Fireproofing needed • Poured Concrete

  22. Raised Core Structural Redesign(AE Breadth) Cost and Schedule Impact • Schedule: • Increase due to field welding • Reduction due to reduced slab pours • Cost: • Increased labor cost

  23. Presentation Outline • Existing Building Conditions • Areas of Investigation • Raised Access Floor - (AE Breadth Area) • Raised Core: Structural Redesign - (AE Breadth Area) • Green Roof Construction • Rainwater Retention System • Construction Manager Involvement Research • Conclusions

  24. Green Roof Construction Green Roof Purpose • Reduce rainwater runoff • Reduce urban heat island effect • Improve aesthetics • Provide urban park

  25. Green Roof Construction Green Roof Types • Intensive • Thick growth medium • Traditional garden plants • Lawn grass, shrubs, trees • Requires constant maintenance • Extensive • Thin growth medium • Hardy plants • Grasses, flowers, other low vegetation • Largely maintenance free • Green roof on Plaza is Extensive

  26. Planting/drainage layer Filter layer Moisture Retention Matt Board insulation Separating layer Waterproofing layer Concrete slab Green Roof Construction Green Roof Composition

  27. Green Roof Construction Construction issues and difficulties • Roof leakage • High tech data floors below • Waterproofing layer most important • Surface conditioner • Hot applied waterproofing • Protection course • Testing necessary • Flood testing • EFVM (electric field vector mapping) • Can be used for periodic future testing as well

  28. Green Roof Construction Construction issues and difficulties • Freeze/thaw cycle • Three locations for water storage • Plants • Growth medium (topsoil) • Moisture retention mat • The only standing water • Roof underneath moisture retention mat functions as traditional roof • No standing water to freeze • Excessive weight on structure • Avoid topsoil piling and storage on roof

  29. Green Roof Construction Construction issues and difficulties • Damage/death of plants • Important that plants survive for success of green roof • Potential causes of death • Insufficient irrigation • Frost • Trampling

  30. Green Roof Construction • Cost Implications • Precautions are less costly than liabilities!

  31. Presentation Outline • Existing Building Conditions • Areas of Investigation • Raised Access Floor - (AE Breadth Area) • Raised Core: Structural Redesign - (AE Breadth Area) • Green Roof Construction • Rainwater Retention System • Construction Manager Involvement Research • Conclusions

  32. Rainwater Retention System Purpose • Environmental Impact • Reduced runoff • Reduced city water usage • Public Awareness • Impact to LEED rating

  33. Rainwater Retention System Public Awareness • Project already in the limelight due to urban redevelopment interest • Showcase the green designs of the Plaza • “Information Station“ • Located next to building entrance • Informational plaques • Description of the rainwater retention system • Reclaimed water volume gauge • Overview of the other green design aspects of the project

  34. Rainwater Retention System System Design and Environmental Impact • Cistern Size: 15,000 gallons • Water Reclaimed: 550,000 gallons • Percentage of total building usage: 52%

  35. Rainwater Retention System

  36. Rainwater Retention System • Impact to LEED • Three possible LEED points • Code Considerations • Appeal process necessary to allow for water reuse • Appeal already approved for waterless urinals

  37. Rainwater Retention System Cost and Schedule Implications • Cost • Total cost increase: $70,000 • 0.2% of total building cost • Retention system: $40,000 • Information Station: $30,000 • Schedule • Decision to utilize the system needs to be made early

  38. Presentation Outline • Existing Building Conditions • Areas of Investigation • Raised Access Floor - (AE Breadth Area) • Raised Core: Structural Redesign - (AE Breadth Area) • Green Roof Construction • Rainwater Retention System • Construction Manager Involvement Research • Conclusions

  39. Contractor Involvement for LEED Buildings • When should a contractor or construction manager become involved in LEED green building projects?

  40. Contractor Involvement for LEED Buildings Research survey of building professionals • Four questions regarding LEED points • Which phase is most appropriate for CM input and involvement? • Conceptual Design • Schematic Design • Design Development • Construction Documents • Construction • Rank from 1-5 according to the importance of CM input and involvement in the main decision making process. • Rank from 1-5 the significance of early CM involvement with respect to the cost of earning this LEED point. • Rank from 1-5 the significance of early CM involvement with respect to the schedule of earning this LEED point.

  41. Contractor Involvement for LEED Buildings Results of Survey • LEED points requiring the most contractor involvement

  42. Contractor Involvement for LEED Buildings Results of Survey • LEED points requiring the most contractor involvement when cost is critical

  43. Contractor Involvement for LEED Buildings Results of Survey • LEED points requiring the most contractor involvement when schedule is critical

  44. Contractor Involvement for LEED Buildings Results of Survey • Overall timeframe for contractor involvement of a LEED project: Design Development/Construction Documents

  45. Conclusions • Raised Access Flooring • Added value through increased re-configurability and reduced churn costs • System pays for itself almost immediately • Raised Building Core • Raised structural supports impractical • “filler” slab is preferable solution • Green Roof • Proper precautions will greatly increase the green roof’s chance of success while reducing the CM’s liability risk • Proper instruction of owner is critical • Rainwater Retention • Provides up to half of the Plaza’s toilet flush water • Improves public awareness of green design • Construction Manager Involvement on LEED projects • Design development is the most appropriate time for CM’s to become involved on LEED projects

  46. Acknowledgements • George Schaefer • Ed Jackowski • Franz Fernley • George Ledwith • Jim Bash • Dr. David Riley • Dan Mattern • Bill & Lois Stauffer • Shannon Stonesifer

  47. Questions?

More Related