1 / 11

Comments on planning

Comments on planning. K. Foraz. Outline. Production schedule Installation schedule – 2012-2013 Conclusion. Production schedule - Tcryo. No safety margin With 10% margin just on production : last collimator available for installation end of March 2013 !!

chace
Télécharger la présentation

Comments on planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Comments on planning K. Foraz LHC collimation upgrade review - K. Foraz

  2. Outline • Production schedule • Installation schedule – 2012-2013 • Conclusion LHC collimation upgrade review - K. Foraz

  3. Production schedule - Tcryo • No safety margin • With 10% margin just on production : last collimator available for installation end of March 2013 !! • Not taking into account final assembly and tests ~ 5-6 weeks ( ) Could the rythm of production be increased ? A priori No, mainly because of internal resources (the production year 2012 is also the IC consolidation year) LHC collimation upgrade review - K. Foraz

  4. Production schedule - others • Shortened CC • Engineering studies finished end of 2010 • CC available end of October 2012 (with a 10% margin on production: mid Dec.) • Cryogenics extension • Should be available end of 2011 • Integration still to be done • DSLC shortening • With a design finished in May next year • Available for IC in August 2011 LHC collimation upgrade review - K. Foraz

  5. Installation Schedule 2012-2013 5 4 6 IC consolidation schedule Several scenari under studies: from where to start ? ~cell 12R3 (but then no pilot sector for eventual tests) / sector 45 7 3 8 2 1 Sector 45 Sector 56 Sector 67 Sector 78 Sector 23 Sector 34 Warm-up LHe emptying Last leak tests & ELQA IC consolidation Powering tests Cool-down LHC collimation upgrade review - K. Foraz

  6. Installation Schedule 2012-2013 Collimation & IC consolidation – several scenari • No dedicated IC team for collimation • Start of the shutdown in December 2011 • Start of the shutdown postponed to minimize the effect of collimation • With a dedicated IC team for collimation Do not forget it is not only the team, but the training, the supervision and the material • Start of the shutdown in December 2011 • Start of the shutdown postponed to minimize the effect of collimation LHC collimation upgrade review - K. Foraz

  7. Installation Schedule 2012-2013 No dedicated IC team for collimation – Start in December 2011 In theory, the IC Train would have to wait 3.5 months !!! (I don’t think that these teams would wait !!! They will jump point 3, and come back later) +~ 2 months Sector 23 Sector 34 Tcryo CC LHC collimation upgrade review - K. Foraz

  8. Installation Schedule 2012-2013 No dedicated IC team for collimation – Start in July 2012 (2 months + 3 months of possible delay during production) Shut-down from July 2012 to October 2013 ~ 1 month additional time will be needed (more work) Sector 23 Sector 34 Tcryo CC LHC collimation upgrade review - K. Foraz

  9. Installation Schedule 2012-2013 Dedicated IC team for collimation – Start in December 2011 + 2 months Transp. & align. & prepar.: 2weeks Reconnection: 5weeks + Leak tests: 2weeks + Prepa. For CD: 2weeks Sector 23 Sector 34 Tcryo CC LHC collimation upgrade review - K. Foraz

  10. Installation Schedule 2012-2013 Dedicated IC team for collimation – Start in April 2012 No impact on duration (impact on maintenance plan and on long-term schedule shall be analyzed) Sector 23 Sector 34 LHC collimation upgrade review - K. Foraz

  11. Conclusion • Tight production schedule (Tcryo and CC) would be compensated by delaying the start of the shut-down • Several scenarios studied: • No dedicated team for IC collimation • Start of shutdown in December 11: +2 mths • Start of shutdown postponed to July 12 : + ~1mth • Impact on maintenance plan and long term schedule to be studied • 3 months margin on collimation production • With a dedicated team for IC collimation • Start of shutdown in December 11: +2 mths • Start of shutdown postponed to April 12 : No impact (or evenbetter in July 11) • Question: according to Ralf, with IR3 collimation a factor 10 can be gained in Intensity. Will it be painful to wait for next shutdown to install Tcryo in IR3? LHC collimation upgrade review - K. Foraz

More Related