LMS Selection Project: Update to UCIST

LMS Selection Project: Update to UCIST. 25 June 2010 (postponed from 28 May) Andrea Chappell, for the project team. Update topics. Project timeline RFP status Open Systems - issues, policy decisions, etc. Who/What, Why, 3 rd party support, migration OLE student survey results

chaz
Télécharger la présentation

LMS Selection Project: Update to UCIST

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LMS Selection Project: Update to UCIST 25 June 2010 (postponed from 28 May) Andrea Chappell, for the project team

  2. Update topics • Project timeline • RFP status • Open Systems - issues, policy decisions, etc. • Who/What, Why, 3rd party support, migration • OLE student survey results • Other notes • 6 areas for input from UCIST

  3. First: 6 areas for UCIST input • RFP evaluation criteria. Need approval. • Open systems. Reasons NOT for UW? • Develop or not? If so, what governance? • Add-on functionality – who decides? • Externally hosted versus locally installed. • Opinions or comments? • Migration/pilot – will ask for resources.

  4. Project timeline • Phase I – end with recommendation to UCIST Feb. 2011 • RFI: April – June 2010 • RFP: July – Nov 2010 (submit mid July, review by Nov) • Info collect: Jun – Nov 2010 (Contact schools, add-on tools, etc.) • Policy decisions: Jun 2010 – Jan 2011 (open systems, dev, hosting, procedures changes, etc.) • Test and assess short list: Nov – Dec 2010 • Phase II – implementation planning, pilot, migration, to May 2012 • Pre-pilot (very small group): Winter 2011 • Pilot (real use): Mar. 2011 – July 2011 • First wave of migration: July – Aug 2011 (for Sep 2011) • Final migrations: Sept 2011 – March 2012

  5. Pre-pilot (Winter 2011) • Evaluate criteria in practice, processes, CEL templates, etc. • CEL committed to W11 pilot of short list (1 or 2 systems), 3 courses in each. • CEL will assign 1-2 FTEs in F10/W11 to this assessment pilot. • IST/CTE need to determine parallel campus course plan.

  6. RFP - status • Re-developing criteria, developing demo scenarios (vendor/products through paces) • Evaluation assessment weightings • Functionality (25%) • Interface Design (20%) • System Integration (20%) • Service and Support (15%) • Cost (10%) • Other (10%)

  7. Open systems: Who/what • Western: RFI in fall, consider Bb NG, open source. • UVic: Moodle since 2007, from Bb (WebCT since 4.1). Small pocket of Sakai. • Queen’s: To Moodle from WebCT after a year in 2 pilots, 10+ courses, 1000’s students. • Windsor: Sakai 2.5 since 2006, to 2.7 in Fall; moved from homegrown Notes app. • Virginia Tech: Had Sakai for 1-2 years for collab and project groups. To be sole LMS in Fall 2010.

  8. Open systems: Why (drivers)? • No vendor lock-in • Customization • No license fee (but adoption not free) • Products adhere to industry standards • Development contributes to global benefit • Philosophical alignments • Poor support from Blackboard (VTech, UVic)

  9. Open system: Use of 3rd party • Not much use of 3rd party company for implementation, migration, support • Almost all in-house, using own staff • Not much development happening for respondents, only Windsor • Much development by community (650 modules for Moodle, many for Sakai)

  10. Migration (not unique to OS) • Drain on resources. • Main obstacles are differences in structure, data format, modules. • Most data type not converted. Quizzes, discussion forums must be recreated. Significant course redesign. • Used existing staff, some student hires, varied a lot. Generally, need lots of help!

  11. OLE student survey results Sneak peak … • Look and feel (some awkwardness of interface) • Tech (frames are so 90s, Javascript) • Integration with Quest, Nexus (hm, portal-like) • Access to materials (all syllabi, materials from other courses, access after end of course) • Discussion forums not as good as others outside ANGEL • Mobile access • More from calendar (integrated with other calendars) • Better live/synchronous tools, such as chat

  12. Other notes • Shahed’sManSci course project (option) • Communications – web site coming! • Increase transparency • Web site under development, then a launch and keep up to date with progress • Staffing • Liwana’s contract extended; Jan will start a gradual return on July 19th

  13. 6 areas for input from UCIST • RFP evaluation criteria. Need approval. • Open systems. Reasons NOT for UW? • Develop or not? If so, what governance? • Add-on functionality – who decides? • Externally hosted versus locally installed. • Opinions or comments? • Migration/pilot – will ask for resources.

  14. Questions or Comments?