1 / 34

PMBOK Chapter 7 Project Cost Management

PMBOK Chapter 7 Project Cost Management. Cost management is:. The process involved in estimating, budgeting, and controlling costs so that the project can be completed within the approved budget. It includes the following. Cost Management processes. 7.1 Estimate cost

Télécharger la présentation

PMBOK Chapter 7 Project Cost Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PMBOK Chapter 7 Project Cost Management

  2. Cost management is: • The process involved in estimating, budgeting, and controlling costs so that the project can be completed within the approved budget. • It includes the following

  3. Cost Management processes • 7.1 Estimate cost • The process of developing an approximation of the monetary resources needed to complete project activities • 7.2 Determine Budget • The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline • 7.3 Control Costs • The process of Monitoring the status of the project to update the project budget and managing changes to the cost baseline

  4. Cost Management Plan Definitions • Level of accuracy • Unit of Measure • Organizational procedures links • Control Thresholds • Rules of performance measurement

  5. Estimate Costs • Inputs, Tools, Techniques and Outputs

  6. Estimate Cost Flow Diagram

  7. Estimate cost inputs • Scope baseline • Scope statement • Work breakdown structure • WBS dictionary • Project Schedule • Human Resources Plan • Risk Register

  8. Estimate cost inputs • Enterprise Environmental Factors • Market conditions • Published commercial information • Organizational Process Assets • Cost estimating policies • Cost estimating templates • Historical information • Lessons learned

  9. Estimate Costs tools and techniques • Expert Judgment • Analogous Estimating • Parametric Estimating • Bottom-Up Estimating • Three-Point Estimates (PERT) • Most likely • Optimistic • Pessimistic • Expected = Optimistic + 4 * Most likely + Pessimistic 6

  10. Estimate Costs tools and techniques • Reserve Analysis • Cost of Quality (COQ) • Project management Estimating Software • Vendor Bid Analysis

  11. Estimate Costs Outputs • Activity costs estimates • Basis of Estimates • Documentation of the basis of the estimate (i.e., how it was developed), • Documentation of all assumptions made, • Documentation of any known constraints, • Indication of the range of possible estimates (e.g., $10,000 (+/- 10%) to indicate that the item is expected to cost between a range of values) • Indication of the confidence level of the final estimate • Project Document Updates

  12. Q: Analogous estimating: • a. Uses bottom-up estimation techniques • b. Is used most frequently in the executing phase of the project • c. Uses top-down estimation techniques • d. Uses actual detailed Historical costs • Answer C

  13. Determine Budget ProcessInputs, Tools, Techniques and Outputs

  14. Determine Budget ProcessFlow Diagram

  15. Determine Budget Inputs • Activity Cost Estimates • Basis of Estimates • Scope Baseline • Scope Statement • Work breakdown structure • WBS dictionary

  16. Determine Budget Inputs • Project Schedule • Resource Calendars • Contracts • Organizational process Assets • Existing policies • Cost budgeting tools • Reporting methods

  17. Determine Budget Tools and Techniques • Cost Aggregation • Work packages within WBS are aggregated • Reserve Analysis • Contingency reserves • Management reserves • Expert Judgment • Other units within Organization • Consultants • Stakeholders, including customer • Professional and technical associations • Industry groups • Historical Relation • Funding limit Reconciliation

  18. Determine Budget outputs • Cost Performance Baseline • S-Curve

  19. Determine Budget outputs • Project funding requirements • Project document updates • Risk register • Cost estimates • Project schedule

  20. Control Costs process • The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline • Any changes to the budget should be approved only through the perform integrated change control process.

  21. Control Costs process • Project cost control includes: • Influencing the factors that create changes • All change requests are acted on in a timely manner • Managing the actual changes when they occur • Isolate an d Understand variance from approved cost baseline • Inform stakeholders of all approved changes and associate cost • Acting to bring cost overruns within acceptable limits

  22. Control Costs processInputs, Tools, Techniques and Outputs

  23. Control Costs process Flow Diagram

  24. Control Costs: Inputs • Project Management Plan • Cost Performance baseline • Cost management plan • Project Funding Requirements • Work Performance Information • Organizational Process Assets • Existing policies • Cost control tools • Monitoring and reporting methods to be used.

  25. Control Costs Tools and Techniques • Earned Value Measurement (EVM) To measure • The Planned Value =PV = BCWS, what is the estimated value of the work to be done? • The Earned Value = EV = BCWP, What is the estimated value of the work actually accomplished? • Actual Costs = AC = Actual Cost of Work Performed.

  26. Control Costs Tools and Techniques

  27. EVM Formulas

  28. Control Costs Tools and Techniques • Forecasting • EAC forecast for ETC work performed at the budgeted rate • EAC= AC+BAC- EV • EAC forecast for ETC work performed at the present CPI • EAC = BAC / Cumulative CPI to date • EAC forecast for ETC work considering both SPI and CPI factors • EAC = AC+[(BAC-EV) / (Cumulative CPI * Cumulative SPI)].

  29. Control Costs Tools and Techniques • To-Complete Performance Index (TCPI)

  30. Control Costs Tools and Techniques • Performance Reviews • Variance analysis • Trend Analysis • Earned Value Performance • Variance Analysis • Project Management Software

  31. Control Costs Outputs • Work Performance measurements • Budget Forecasts • Organizational Process Assets Updates • Causes of variances • Corrective actions chosen and the reasons • Lessons learned • Change Requests • Project management Plan Updates • Cost Performance baseline • Cost management plan • Project Document Updates • Cost estimates • Basis of estimate

  32. Q: If Earned Value (EV) = 350, Actual Cost (AC) = 400, Planned Value (PV) = 325, what is the Cost Variance (CV) ? • a. 350 • b. -75 • c. 400 • d. -50 • Answer D

  33. Q: The Schedule performance index (SPI) of 0.76 means: • a. We are over budget • b. We are ahead of schedule • c. We are only progressing at 76% of the rate originally planned • d. We are progressing at 24% of the rate originally • Answer C

  34. Play Time

More Related