1 / 8

FEE PPS Status

This schedule outlines the critical path for the installation and testing of the FEE PPS hardware and cable plant, including cold and hot checkout procedures. It also includes the status of reviews and upcoming acceptance tests.

ederossett
Télécharger la présentation

FEE PPS Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FEE PPS Status Enzo Carrone June 8, 2009

  2. PPS FEE Schedule

  3. FEE/NEH Schedule

  4. Critical Path “Enhanced” QA/QC activities

  5. FEE PPS Cold Checkout • Cold Checkout • Verifies Hardware and Cable Plant is installed and wired correctly • Verifies No Ground Shorts in the Cable Plant • EEIP Hardware and Racks • 95% Complete

  6. FEE PPS Hot Checkout • Hot Checkout • Verifies Functionality of Hardware, Devices, and PLCs • Hi-Pot Cable Plant • Invasive to LCLS Undulator Complex Operations (2-3 Hours)

  7. PPS Review Status • Final Design Review #2 (April 22, 2009) • Initial Acceptance Test Review • Internal Review (May 15, 2009) - Complete • External Review (near completion)

  8. FEE Initial Acceptance Test Schedule • IAT Validation • June 17 – June 19 • Invasive to Upstream LCLS Operations • IAT Certification • June 22 - June 26 • Invasive to Upstream LCLS Operations

More Related