Successful Community Engagement Workshop South Hayward BART/Mission Boulevard Concept Design Plan

Successful Community Engagement Workshop South Hayward BART/Mission Boulevard Concept Design Plan. David Rizk , Planning Manager Planning Division Community & Economic Development. Land Use Plan. Concept Design Plan. South Hayward BART Station Area. Dixon Street. Valle Vista Avenue.

eyad
Télécharger la présentation

Successful Community Engagement Workshop South Hayward BART/Mission Boulevard Concept Design Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Successful Community Engagement WorkshopSouth Hayward BART/Mission BoulevardConcept Design Plan David Rizk, Planning Manager Planning Division Community & Economic Development

  2. Land Use Plan

  3. Concept Design Plan

  4. South Hayward BART Station Area Dixon Street Valle Vista Avenue BART Parking Lot BART Parking Lot South Hayward BART Station S A R S A R BART Parking Lot Mission Blvd. Tennyson Road View looking to the south

  5. South of BART Station Area Industrial Parkway Commercial Site BART Tracks Dixon Street … M B R … Valle Vista Avenue Community Center Site Mission Blvd Commercial (Grocery Store Site) View looking to the south

  6. BART’s South Hayward BART Station Development, Design and Access Plan

  7. Community Engagement • Four Community Meetings: • January 2005 • July 2005 • September 2005 (BART Sponsored) • February 2006 • Five City Council/Planning Commission Joint Work Sessions • Project Newsletter Sent to Over 4,400 Addresses • Section of City’s Website Dedicated to Project Information and as a Means of Getting Feedback • Regular Technical Advisory Committee Meetings

  8. Noticing Area for Community Meetings and Newsletter

  9. Newsletter

  10. Dedicated Section of City Website for Info and Feedback

  11. Photosimulations

  12. Video Simulations

  13. Lessons Learned • Identify Key Stakeholders Early in the Process • Provide Easily Accessible Information to the Public • Give Public an Opportunity to Participate and Listen to Input • Obtain Feedback from Policy Makers Throughout Process • Work with Developers to Increase Likelihood of Successful Implementation

  14. Successful Community Engagement WorkshopSouth Hayward BART/Mission BoulevardConcept Design Plan David Rizk david.rizk@hayward-ca.govwww.hayward-ca.gov