1 / 7

Airport Design Consult ADC

Delhi International Airport Existing International Terminal T2 Re-modelling. Proposed plan. Existing plan. Airport Design Consult ADC. Reconfigure visitor centre. Construct new offices & retail. Decommission & demolish offices Area 1,2 and offices on upper mezzanine. Area 1. Area 2.

foy
Télécharger la présentation

Airport Design Consult ADC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Delhi International Airport Existing International Terminal T2 Re-modelling Proposed plan Existing plan Airport Design Consult ADC

  2. Reconfigure visitor centre. Construct new offices & retail • Decommission & demolish offices Area 1,2 and offices on upper mezzanine Area 1 Area 2 Construction Phasing: Departures Phase 1 (4 months) Week 0 16 Delhi International Airport Existing International Terminal T2 Re-modelling Airport Design Consult ADC

  3. Construct new outer check in desks and belts, landside retail, airside toilets, new transfer routes • Construction check in desks and belts line 2 • Construction check in desks and belts line 7 • Demolish airside toilets Construction Phasing: Departures Phase 2 (4 months) • Construct new Clipper Lounge on mezzanine Week 0 32 16 Delhi International Airport Existing International Terminal T2 Re-modelling Airport Design Consult ADC

  4. Demolish west retail and wall dividing pre departures from gates • Construct new 1st phase emigration, customs & security in sections • Decommission west transit Construction Phasing: Departures Phase 3 (3 months) Week 0 44 32 16 Delhi International Airport Existing International Terminal T2 Re-modelling Airport Design Consult ADC

  5. Decommission existing main security • Hoard off and demolish Clipper Lounge, east retail and wall dividing pre departures from gates • Construct remaining emigration, customs & security in sections Construction Phasing: Departures Phase 4 (3 months) • Commission part completed emigration, customs & security and west transit route Week 0 44 56 32 16 Delhi International Airport Existing International Terminal T2 Re-modelling Airport Design Consult ADC

  6. Hoard off and construct new airside retail Construction Phasing: Departures Phase 5 (2 months) • Commission remaining emigration, customs & security and east transit route Week 0 44 56 32 64 16 Delhi International Airport Existing International Terminal T2 Re-modelling Airport Design Consult ADC

  7. Delhi International Airport Existing International Terminal T2 Re-modelling OVERALL PROJECT SCHEDULE AUG-SEPT’ 06 OCT-NOV’ 06 DEC’ 06 – MAR’ 08 DESIGN, DRAWINGS & SPECIFICATIONS TENDERING & FINALIZING CONTRACTOR CONSTRUCTION IN 5 PHASES Airport Design Consult ADC

More Related