An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tracking Electronics Marvin Johnson

  2. SEQ SEQ SEQ platform HV / LV Monitoring Control 3/6/8/9 Chip HDI 3M Low Mass IB Optical Link 1Gb/s Sensor NRZ / CLK 1 5 5 3 VRB VRB VRB VRB VBD 68k Bit3 VME VRB Controller PC MPM L3 DØ Silicon Data Flow Silicon Graphics

  3. Silicon System • Cables • Utilities • Bias voltage • DC power • Interlocks and alarms • Signal conditioning • Downloading • SVX sequencer • VME readout system • System testing

  4. 6 types of Cables • Kapton film from the detector (low mass, 8 ft long) • Clock is on separate twin coax • 80 conductor 3M pleated foil to interface card (30 ft) • Clock is on separate twin coax • 50 conductor 3M pleated foil to Sequencer (30 feet) • Fiber optic line from platform to MCH 2 (60 meters)

  5. Cable installation • Low mass cables come with the silicon • Connector adapter boards • 480 units • 2 ETF for 2 weeks + 10% supervisor • July 00 (aftr waveguides) • 80 conductor 3M cables • 456 units • 3 ETF for 5 weeks + 10% suoervisor • July -Aug 00 • 50 conductor 3M cables • 456 units • 3 ETF for 5 weeks + 10% supervisor • Jan - Feb 00 • Fiber optic cables • 600 units (includes CFT) • 3 ETF for 3 weeks • Dec 99 - Jan 2000 • Crew is E Podschweit + 2 new people

  6. Utilities • Interface crates • Provide utilities for silicon (signal conditioning, power, bias voltage etc.) • Located at the base of the calorimeter in all 4 quadrants • 2 ETF for 3 weeks • V. Martinez + new person • Jan 00 • Bias supplies • Uses existing D0 HV supplies • MCH work mostly complete • Patch panels on platform & jumpers to interface crate • 1 ETF for 3 weeks • J. Geralds • March 00

  7. DC power • Use common Vicor supplies (same as cal and other groups) for platform supplies • Interface supplies require mag. Shielding so use existing calorimeter design - all drawings exist • Sequencer power design is complete, drawings exist, supplies are on order. • 2 MTF for 3 weeks • Mar 00 • VRB system in MCH reuses supplies from run one including the control hardware. • 1 ETF for 3 weeks • V. Martinez

  8. Interlocks etc. • Interlock and control is the same as run 1 (1553 link to rack monitors). Almost all of this is already in place. • Downloading is also via the 1553 link. About 10 additional cables need to be installed from MCH to platform.

  9. Sequencer • Crates are here • Module production should start this week. • Testing • Iowa State - ETU 5 weeks • Mid Dec 99 • Installation • 1 ETF, 1EEF for 3 weeks • J. Green • M. Utes • Jan - Feb 00

  10. VRB’s • All modules are here and tested • 2 of 6 racks are being installed • All monitoring and control reuses run 1 equipment. • Installation • 2 EEF for 3 weeks • R. Angstadt • J. Anderson • Dec 99 - Jan 00

  11. System Test • U of Michigan is building an ‘SVX Emulator’ board • Completely emulates the digital part of the SVX. • Allows down loading of fake events and read out at full speed. • Includes readout of bias voltage, supply voltage and downloaded parameters, • Building enough for 1/8 of the detector. • Can connect at the sequencer, interface crate or adapter crate on CC • Allows complete system testing all the way through L3 including the online software and monitoring. • Commissioning • PF, EEF for 4 weeks • M. Utes + New Physicist • Jan - Mar 2000

  12. Fiber tracker • Analog processing • Digital processing • Trigger (covered by G. Blazey) • VRB Read out (same as silicon)

  13. Fiber electronics

  14. Analog Front End • Located on cryostat • Uses trigger pickoff chip in front of SVX II chip • Difficult design (5 fC trigger level) • 2 versions 8 and 12 chip • First layout of 8 chip finished but extensive revisions • Expect next prototype feb 1,2000 • If no revisions, 10 boards in April, 2000 • 12 chip is delayed (difficult layout) • probably 2 months beyond the 8 chip • Infrastructure (crates, backplanes, power etc) are designed and most are on order

  15. Analog testing • LED pulser for board and system test • Pulse individual fibers with variable amplitude and time. • 512 channels are available. • Can test both fiber and preshower systems • Can test boards either in a test station or on the cryostat • Mixer board precludes trigger testing • Pulser system is done except for the connection to the test stand. • Board testing either by Iowa State or Fermilab.

  16. Analog boards • Installation • Limited by Cassette production • 2 ETF for 4 weeks • O. Payne • V. Martinez • May - Sept 00 • Commissioning • 2 EEF, 2 PF for 8 weeks • P. Sheahan • J. Anderson • S. Gruenendahl • detector groups • May - Sept 00

  17. Digital boards • one board + 2 daughter boards for all L1 and L2 front end data • Mother board and first daughter board nearly complete • Second daughter board in layout • Prototype communications system works very well • Design is basically large FPGA chips and comm links so low risk.

  18. Digital testing • Reprogram the digital front end board to send out test patterns. • Can test all down stream systems all the way to L3 • Use same boards as pattern generators for board testing • Request into PREP for initial testing and maintenance • Comm. link uses serial protocol so modest number of cables • Power supply, backplanes etc. are designed and most are on order. A

  19. Digital boards • Installation • 2 ETF for 4 weeks • O. Payne • V. Martinez • Mar - Apr 00