1 / 29

R&D ERL Meeting Accelerator Safety Order (ASO) Requirements

R&D ERL Meeting Accelerator Safety Order (ASO) Requirements. E. Lessard, Associate Chair for ESSHQ Collider-Accelerator Department. February 17-18, 2010. Meeting ASO Requirements. O 420.2B CRD 1.a. (Complete). R&D ERL Hazard Screening Report, NEPA Review, Safety Assessment Document (SAD)

gerd
Télécharger la présentation

R&D ERL Meeting Accelerator Safety Order (ASO) Requirements

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. R&D ERLMeeting Accelerator Safety Order (ASO) Requirements E. Lessard, Associate Chair for ESSHQ Collider-Accelerator Department February 17-18, 2010

  2. Meeting ASO Requirements

  3. O 420.2B CRD 1.a. (Complete) • R&D ERL Hazard Screening Report, NEPA Review, Safety Assessment Document (SAD) • Ionizing Radiation • Oxygen Deficiency • Electrical Hazards • Fire Hazards • Industrial Hazards

  4. Ionizing Radiation ERL Hazards • Unshielded dose rates • Bremsstrahlung dose rates of 4x107rad/h in the forward direction at 1 meter and 5x105rad/h in the transverse direction • neutron dose equivalent rates range between 6x103 and 1x105rem/h at 1meter ERL Controls • Shielded enclosure • Interlocked gates

  5. Ionizing Radiation ERL Hazards ERL Controls • Interlocking area-radiation monitors

  6. Oxygen Deficiency ERL Hazards ERL Controls • ODH alarms • ODH exhaust fans

  7. Laser Radiation, RF and X-rays ERL Hazard • Class IV laser system • 1 MW klystron source ERL Controls • Access to laser area controlled with door interlocks • Protective housing for laser and laser shutter interlock • Laser beam transported in pipe • Coordinated key system preventing access to klystron enclosure • RF transported in pipe • Steel shield housing around the klystron tube and tube base to attenuate x-rays

  8. Electric Shock/Arc Flash ERL Hazards • Energized conductors • Operation ofbreakers and disconnects ERL Controls • Exposed conductors and terminals are covered or barriered for protection of personnel • Training for workers • Use of work planning, LOTO and Permits • Use of proper PPE and compliance with NFPA 70E • Magnets de-energized when routine work is done • Electrical equipment is NRTL registered or equivalent

  9. Fire ERL Hazards • The maximum credible fire incident was determined to be a fire in one magnet and damage to the two adjacent magnets • While the klystron’s 100 kV transformers have 800 gallons of oil, it was felt that smoke detectors, interlocks to turn off power to the 100 kV transformers, fire sprinklers, low-flammability oil in the transformers, secondary containment and onsite fire responders would result in a less credible fire incident ERL Controls • Combustible loading was minimized in design • Periodic safety inspections • Fire detection and suppression system • Design reviewed by BNL Fire Protection Engineer • Design meets NFPA requirements • On-site fire responders • Interlocks to turn off power

  10. O 420.2B CRD 1.d. (Complete) • R&D ERL SAD

  11. O 420.2B CRD 2.a. (Complete) • ASE Approved by DOE February 3, 2009 • Bounding conditions • BNL Safety Envelope Limits • Corresponding Safety Envelope Parameters • Prototype ERL Beam Limits • Control of Beam Loss • Access Controls • Fire Protection • Engineered Safety Systems Requiring Calibration, Testing, Maintenance, and Inspection • Operations Envelope / Administrative Controls

  12. O 420.2B CRD 3. (Complete) • C-AD practices used to identify USIs • Design review • Experimental safety review • Accelerator systems safety review • Identified USI Process • 1.10.1 Procedure for Documenting Unreviewed Safety Issues • 1.10.1.a CA USI Form

  13. O 420.2B CRD 4. (ARR Open) • ARR process defined in SBMS Accelerator Safety Subject Area • Draft Commissioning Plan for ARR of R&D ERL • Module 1: G5 Test Module 3-15-11 • Module 2: Full System Testing 10-24-11

  14. O 420.2B CRD 5.a. (Partially Complete) • C-AD OPM 1.12 Training and Qualification Plan • Applies to all C-AD employees, visitors and users • Responsibilities, qualification requirements, training requirements and records system defined • C-AD Training Manager coordinates program

  15. O 420.2B CRD 6.c. (Partially Complete) • New or modified C-AD OPMs under development: • ERL Operational Safety Limits (2) • Configuration Management (5, 6, 7) • Lock-Out Tag-Out (2) • Local Emergency Procedure (3) • Emergency Call-Down Lists (3) • Cryogenic Systems Operation (2) • Injecting, Accelerating, Circulating and Dumping Electron Beam (1, 2) • Laser Operations (1, 2) • Access Control System Operation and Testing Procedures (2) • Shutdown Procedure (2, 3) • C-AD OPM 2.28 Work Planning is in use (4)

  16. Summary Authorization Status • ERL Commissioning Plan needs to be finalized • Accelerator Readiness Review needs to be conducted • ERL needs DOE authorization to commission g-5 and ring • Conduct of Operations Agreement needs to be finalized • Procedures and training need to be completed • ERL needs DOE authorization to routinely operate • Questions?

  17. Informational Slides • Remaining contractor requirements identified in DOE Accelerator Safety Order, 420.2B • Additional slides showing all additional completed requirements

  18. O 420.2B CRD 1.b. (Complete) • SAD 4.10.3. Risk Assessment to Workers, the Public and the Environment • SAD 4.10.3.1.Radiation Risks • SAD 4.10.3.2.Environmental Risks from Radiation • SAD 4.10.3.3.Fire Risks • SAD 4.10.3.4.Electrical Risks • SAD Appendix 6, Qualitative Risk Assessments

  19. O 420.2B CRD 1.c. (Complete) • 3.2. ERL Characteristics Related To Safety • SAD 3.5. Design Features That Exclude or Minimize Exposure to Hazards to As Low As Reasonably Achievable (ALARA) During Operation, Maintenance and Facility Modification • SAD 4.8. Selection of Control Measures that Reduce Risks to Acceptable Levels • SAD Table 4.9.a. List of Credited Controls

  20. O 420.2B CRD 1.e. (Complete) • SAD 3.Site, Facility and Operations Description • 3.1. Environment Within Which the ERL is Constructed • 3.3. Management Methods Used In Operating the ERL • 3.4. Design Criteria and As-Built Characteristics, Supporting Systems and Components with Safety-Related Functions • 3.6. BNL, C-AD and R&D ERL Organizational Structure

  21. O 420.2B CRD 2.b. (Complete) • C-AD OPM 2.5 Series of ASE procedures for operators • Separate procedure for each C-AD Accelerator Facility • Defines operator responsibilities and notification steps for unpermitted operating conditions • ASE Authorized Alternatives are listed in ASE procedure • C-AD OPM 1.1 and BNL SBMS Accelerator Safety Subject Area define restart authorizations and includes DOE approval

  22. O 420.2B CRD 1.f. (Complete) • C-AD OPM 13.4.2.d List of C-AD Records • SADs are defined as Controlled Documents • BNL SBMS Document Control Subject Area • 5 year review period • Identified USI process is used to maintain the SAD current during the interim

  23. O 420.2B CRD 5.b. (Complete) • Draft Conduct of Operations Agreement for R&D ERL includes C-AD OPM C of O Procedures: • 2.2 Operating Practices • 2.3 Activities in Control Rooms • 2.4 Operator Trainees • 2.12 Communications Practices • 2.28 Work Planning and Control for Operations

  24. O 420.2B CRD 5.b. (Complete) • C-AD OPM 14.31.2 Occupational Safety and Health Training Summary for C-AD Operations and Maintenance Activities • C-AD Access Training • Job Training Assessments

  25. O 420.2B CRD 6.a. (Complete) • C-AD OPM 1.4.3 Procedure for Implementing New or Revised Permanent Procedures, or Canceling Permanent Procedures • C-AD procedures require Department Chair approval

  26. O 420.2B CRD 6.b. (Complete) • 1.4.1 Format of C-A Policies, Programs and Operating Procedures • Format meets O 420.2B CRD 6.b. requirements

  27. O 420.2B CRD 7.a. (Complete) • C-AD safety review programs include: • Inspections of facilities • Outdoor storage area inspections • Inspection of satellite-waste stations • Tank inspections • 90-day waste area inspections • Testing of engineered safety systems

  28. O 420.2B CRD 7.b. (Complete) • C-AD safety review programs include: • Critiques of off-normal events • QA assessment of procedure implementation • QA assessment of training and qualifications of staff • Manager work observations • Supervisor work observations • Documenting and tracking corrective actions

  29. O 420.2B CRD 8. (Complete) • Shielding Policy for the R&D ERL is the approved C-AD Shielding Policy

More Related