from ANNEX 02 to NCR/FM/INFN/RM2/003

Preventive Cuts (Pcut) Procedure. originally thought to prevent delaminations in TVAC only performed on 8 tower0 trays on W-side (8layers). 26.5 cm/tile 4.24 m/layer ~34 m total length of tower0 preventive cut. from ANNEX 02 to NCR/FM/INFN/RM2/003. Bubble Cuts (Bcut) Procedure.

halil
Télécharger la présentation

from ANNEX 02 to NCR/FM/INFN/RM2/003

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Preventive Cuts (Pcut) Procedure • originally thought to prevent delaminations in TVAC • only performed on 8 tower0 trays on W-side (8layers) • 26.5 cm/tile • 4.24 m/layer • ~34 m total length of tower0 preventive cut from ANNEX 02 to NCR/FM/INFN/RM2/003

  2. Bubble Cuts (Bcut) Procedure Small (<2mm) cut far from bias lines (>1mm) using an edged scalpel Insulation test (OL) with an ohm-meter between tray and shield plane Used for tower0 trays and # TowerA trays Estimate of total bubble-cut for tower0 = 17layers x 2bubbles x 2mm <~ 7cm

  3. Tower0 trays summary chart

  4. Conclusions – risk assessment • 0 short on shield lines • 4 HV short on trays Pcut and Hand-Sanded W • 23 layers OK on HV line (6 Pcut, 15 Bcut) • 27 layers OK on shield line (8 Pcut, 17 Bcut) •  all shorts due to W whiskers generated from tiles hand-sanding which entered long, deep Pcuts – such whiskers were actually observed • on towerA: • NO Pcuts • W tiles are etched and primed, therefore very flat, clean and whiskers-free • Bcuts are superficial (see procedure) • Let’s calculate anyway a conservative HV-short probability: • a HV short would cause 1 ladder loss (on tower0 trays with HV-short we disconnected HV resistors on MCM boards for all 4 ladders to avoid current flow) Prob(1ladder-loss/Bcut) = 4 / 34 m x 2mm = 0.23 10-3 , i.e. 1ladder-loss every 4250 Bcut or 1 ladder with HV-short every 2150 ladders (assuming 1 Bcut every 2 ladders)

  5. Conclusions – schedule constraints List of available trays 3 trays without Bcut and MCM pocket deep enough to hold MCM  GA flow will be slowed until new trays are available without Bcut