An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Next Steps Cybion Srl

  2. Workpackage flow WP1 Methodology definition WP5 Awareness Raising/workshops WP2 Data Collection WP3 Mapping implementation WP4 Database and on-line tools WP5 Awareness Raising/dissemination MAP-IT! Review Meeting

  3. Workpackage flow WP1 Methodology definition WP5 Awareness Raising/workshops WP2 Data Collection WP3 Mapping implementation WP4 Database and on-line tools WP5 Awareness Raising/dissemination MAP-IT! Review Meeting

  4. Task timetable: GANTT MAP-IT! Review Meeting

  5. Achievements overview MAP-IT! Review Meeting

  6. WP2 Ongoing Data Collection Remaining work to be done Task 2.3 Questionnaires distribution • Quest. distribution (started in January ) • Errors analysis and questionnaires redistribution • Follow up actions on target players: phone calls, visits, events participation, etc. • Database population MAP-IT! Review Meeting

  7. WP3 Ongoing Knowledge mapping Remaining work to be done Task 3.2 Mapping Excellence • Planning and organisation of subsequent meetings with detailed agenda definition • Organisation of the 2nd meeting of the two working groups: first analysis of questionnaires; definition of research target areas according to environmental analysis • Distribution of working group meetings minutes • Organisation of the 2nd meeting of the expert panels: analysis of first results from questionnaire, analysis of results from environmental analysis, first identification of potential common convergent priority areas MAP-IT! Review Meeting

  8. WP3 Ongoing Knowledge mapping Remaining work to be done Task 3.2 Mapping Excellence cont’d • Organisation of 3rd Expert panels meeting : final definition of target research areas and analysis of 50 ICT excellent players • Distribution of expert panels meetings minutes • Input structuring to national mapping reports Task 3.2/3.3 Mapping reports • Draft national mapping reports • Results consolidation and validation MAP-IT! Review Meeting

  9. WP4 Ongoing Database and webplatform creation Remaining work to be done Task 4.1 a Database technical implementation - Geographic visualisation access to data Task 4.1 b Database population • Database on-line access to the public Task 4.3 Blog creation and launch - Technical implementation of blog platform MAP-IT! Review Meeting

  10. WP5 Ongoing Dissemination and awareness Remaining work to be done Task 5.2 Newsletter - Ongoing Task 5.3 Workshops – Completed • Follow up on events – fidelisation through newsletters, alerts, blog Task 5.4 Dialogue Launch • Dialogue launch through the blog section of the portal in june • Dialogue refreshing and moderation on blog. MAP-IT! Review Meeting

  11. WP5 Ongoing Dissemination and awareness Remaining work to be done Task 5.5 Final event • Start organisation of final event: speakers and agenda confirmation, preparation of dissemination material (invitations, leaflets, posters, website announcements, etc.) Continue dissemination actions through website, newsletter, database and other communication tools/channels implemented Fidelise target MED ICT players to monitor and update mapping till the end of the project MAP-IT! Review Meeting

  12. MAP-IT! – MED IST Clustering • Informal communications among single partners in covered countries • Plan strategy for single access to database • Reciprocal invitation/participation in workshops • Contribution to newsletter MAP-IT! Review Meeting

  13. MAP-IT! problems • 1) Role change of the Tunisian Partner – MRSTDC - MESRST • 2) Postponement of mapping results MAP-IT! Review Meeting

  14. MAP-IT! Solutions - 1 • Involvement of IST Tunisian contact point, M. Moez Jebara MAP-IT! Review Meeting

  15. MAP-IT! Solutions - 2 • Reschedule mapping activities to absorb delays MAP-IT! Review Meeting

  16. MAP-IT! Changes in planning • Task 2.4 Questionnaire distribution to end at month 15 instead of month 10 • Task 3.2 Mapping excellence to end at month 16 instead of month 13 • Task 3.3 Drafting of mapping reports to end at month 17 instead of month13 • Task 4.3 Blog platform creation to end at month 16 • Task 5.4 Dialogue launch through blog to start at month17 instead of month 13 MAP-IT! Review Meeting