1 / 8

Nacogdoches to Lufkin SS 345 kV Line Project

Nacogdoches to Lufkin SS 345 kV Line Project. James Teixeira Manager, Regional Planning. Description of Project. Add new conductor to existing structures for 13 miles from Nacogdoches Southeast to Herty North

kylesmith
Télécharger la présentation

Nacogdoches to Lufkin SS 345 kV Line Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Nacogdoches to Lufkin SS 345 kV Line Project James Teixeira Manager, Regional Planning Technical Advisory Committee

  2. Description of Project • Add new conductor to existing structures for 13 miles from Nacogdoches Southeast to Herty North • Build new 10 mile double circuit capable with one circuit in place 345 kV line on new ROW from Herty North to Lufkin Switch • Needed in service ASAP (estimated 2012 peak) • Estimated cost : $29.2 M Technical Advisory Committee

  3. Location of Project Existing Structures/ROW New Structures/ROW Technical Advisory Committee

  4. Reliability/Economic Needs for Project • Solves overloading/congestion at Nacogdoches Southeast 345/138 kV autotransformer • Adds 2nd 345 kV source to Nacogdoches and Lufkin • Allows exit of existing Mt. Enterprise SPS • Identified as economic in the 2007 Five-Year Plan with production costs savings of $ 13.4 M in 2012 Technical Advisory Committee

  5. Alternative Considered • Move the Mount Enterprise to Martin Lake 345 kV circuit off of the Mount Enterprise to Trinidad 345 kV circuit structures so that single tower outage does not cause loss of both circuits • Reconfigure Mount Enterprise Switch Station so that single breaker failure does not cause loss of both circuits • Solves overloading/congestion on Nacogdoches Southeast 345/138 kV autotransformer for one contingency but not all • Production cost savings of $ 7.2 M in 2012 • Capital cost estimates were not calculated Technical Advisory Committee

  6. RPG Review • RPG Comment Period • July 25, 2008 through August 15, 2008 • No dissenting comments submitted Technical Advisory Committee

  7. ERCOT Support for the Project ERCOT will be requesting that this project be endorsed by the ERCOT Board Of Directors. Technical Advisory Committee

  8. Questions QUESTIONS? Technical Advisory Committee

More Related