An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Navigational Lighting Update Staci Timol, PE November 29, 2012

  2. Districts with Navigable Bridges

  3. Locations Per District *There is a total of 55 navigable bridges in 45 locations

  4. Bodies of Water • OHIO RIVER • TENNESSEE RIVER • CUMBERLAND RIVER • GREEN RIVER • KENTUCKY RIVER • LICKING RIVER • BIG SANDY RIVER • CRAIGS CREEK

  5. Example - Natcher Bridge DS

  6. Downstream Side Pier B Gauge

  7. Downstream Side Lights and Signs Pier B 180° Red Light 2’ x 2’ Red Panel Channel 1 360 ° Green Light 2’ x 2’ Green Panel Pier A 180° Red Light 2’ x 2’ Red Panel

  8. USCG Requirements • Lights • Signs • Gauge Markings

  9. USCG District Contact Eric Washburn Commander, Eight Coast Guard District 1222 Spruce Street St. Louis, MO 63103-2398 314-269-2300 ext2378 Eric.Washburn@uscg.mil

  10. When to Get New Lighting Plan • Moving existing lights • Moving existing signs • Existing lights or signs are not in exact location specified by existing lighting plan • Extra lights or signs in place • Changing from incandescent to LEDs

  11. New Lighting Plans • There are options • USCG wants to cooperate with you • Takes only a few weeks to issue

  12. Inspections • Monthly Inspections • Make sure all of the lights are burning • In-depth Inspections • At least 2 – 4 times annually

  13. Notify USCG of Problems • Notify USCG 1-800 Number • USCG Broadcasts InfoTo Mariners • Fix Problem As Soon As Safely Possible • Traffic Control • Weather • Notify USCG When Problem Is Fixed • USCG Ends Broadcast

  14. Lighting • Emergency Repairs • Major Repairs • Minor Repairs

  15. Signs • Replace Signs Statewide on Navigable Bridges • Solid Signs With No Borders • Signs Will Be At Least 2’x2’ • Some Lighting Plans Specify Larger Signs • Signs Should Be Within 5’ of Lights

  16. Orientation of Sign

  17. Gauges • Responsibility of Maintenance • Redoing All Gauges on Ohio River • Other Rivers As Funds Become Available

  18. Risk Assessment • Assign Score • 100 Max • Higher Number = More Risk • Condition of Navigational Lighting – 25% • Bridge Geometry – 22% • Boat Activity – 22% • Bypass Inconvenience – 22% • Cost – 9%

  19. Condition of Navigational Lighting • 25% of Total Score • District Priority Based on Condition • Compliance With Current Lighting Plan • Lights • Signs • Markings

  20. Bridge Geometry • 22% of Total Score • Data From Pontis • Piers in Water • Scour Critical • Structure Type • Clearances • Horizontal Clearance • Vertical Clearance

  21. Boat Activity • 22% of Total Score • River Crossed • Allision History

  22. Bypass Inconvenience • 22% of Total Score • Twin Bridges • Bypass Length • ADT • % Trucks • Truck Network • NHS • STRAHNET

  23. Cost • 9% of Total Score • Estimated Cost • Border Bridges

  24. Statewide Ranking

  25. Statewide Ranking Continued

  26. District 1 Rankings

  27. District 2 Rankings

  28. District 5 Rankings

  29. District 6 Rankings

  30. District 9 Rankings

  31. Changes To KEPT • Other – Navigable Bridge • New Category • Customized to Our Data Needs • Automatically Populate Data • PONTIS • HIS • Calculate Risk Assessment • Input From Districts

  32. Training • Spring 2012 • Regular Schedule • Materials Available for New Hires

  33. Questions?