1 / 18

Hybrid Status

Hybrid Status. Carl Haber 12-Aug-2008 UCSC. Prototypes and Designs. 60 cm, 9 cm strip, 6 segments/side. Stave-06. 1 meter, 3 cm strip, 30 segments/side 192 Watts (ABCD chip), ~2.4 % Xo + support structure. Stave-07. 6 x 3 cm, 6 chips wide.

leif
Télécharger la présentation

Hybrid Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hybrid Status Carl Haber 12-Aug-2008 UCSC

  2. Prototypes and Designs 60 cm, 9 cm strip, 6 segments/side Stave-06 1 meter, 3 cm strip, 30 segments/side 192 Watts (ABCD chip), ~2.4 % Xo + support structure Stave-07 6 x 3 cm, 6 chips wide 1.2 meter, 2.5 cm strip, 48 segments/side ~250-300 Watts (@0.25 W/chip) 1.7 – 2.4 % Xo + support structure, depends upon coolant and hybrid design Stave-08 10 x 10 cm, 10 chips wide

  3. Intro • We have developed a 6 chip ceramic ABCD hybrid for the Stave-2007 program • In use for ongoing studies of stave and transmission • A new flex version of this will be fabricated as well. Layout complete, check prints • This will used to test substrate issues (PM talk) • Beyond this a hybrid series is needed for the ABC-Next and Stave-2008 program • Liverpool will lead this program • July 30-31 I met with the Liverpool and Oxford groups, in the UK, to discuss this program • Includes hybrid development and data transmission studies

  4. ceramic flex

  5. Ongoing Program • More in PM talk • Individual hybrids/modules work well electrically • Main issue has been data transmission on the stave with multiple modules. • Lack of robust response to LVDS commands • Significant work on test bench with D.Nelson (many thanks for this…) • While we have made a number of improvements we are not there yet • This has delayed further mounting of modules on Stave-2007

  6. Hybrid for Stave-2008, ABC-next • Oxford Meeting July 30-31, 2008 • Phil Allport, Ashley Greenal, Tony Affolder, CH, Richard Nickerson, Tony Weidberg, Todd Huffman, Peter Phillips, Mike Tyndel • A key issue has been how to accommodate robust early testing of the ABC-next and Stave-2008, considering the lack of a MCC • Drive towards a minimum area design • Concern for data transmission problems • Parallel bus testing program • Follow-up meeting in US, late Sept, proposed

  7. Conclusion of Meeting • A plan was developed to systematically address these various needs • Liverpool will under take the design and fabrication of a series of hybrids over the next 6-9 months • Various design choices will be made as options are understand further.

  8. Proposal • Hybrid-1: for ABC-next test in legacy mode. • Can 20 ABC-next operate as a system? • Not compatible with stave and bus cable • Large connector, control with modified Mustard • Interface to various powering options • To be ready this Fall along with ABC-next

  9. Hybrid Powering and Readout • Proposal • A single PCB which can accommodate 2 hybrid fingers (with sensor) • All module connections to PCB made using wire bonds (as done by US) • Fusing current for 25µm Al wire is ~500mA • Topology of connections will be similar to that presently used on US Stave • Power/DCS towards one end and Data I/O at the opposite end of hybrid • For module readout & configuration make use of SCTDAQ (Mustard+SLOG+LV3) • Requires ABCns to operate in Legacy Mode (1 x Master/column) with data rate limited to 40MHz • Mustard firmware will be modified to accept increased ChipID field • AC-coupled LVDS data transmission to/from module • LVDS RX (CLK, COM, etc.) powered parasitically off module VDD (2V5) • LVDS TX (Module data) powered from LV3 power supply VDD (4V) • Make use of plug-in boards to provide the various powering scheme – the main PCB is simply a carrier • One plug-in per finger, coming in different flavours • SPi plug-in, Pseudo SPi (with own shunt regulation and bypass circuitry) • DC-DC powering • Requirement for floating power supply I/P • SPi will be(?) configurable using SCTDAQ • Direct connection to hybrid VDD/VCC for auxiliary powering • Allows for more thorough testing of ABCn powering • Over/under voltage scenarios + direct current monitoring Ashley Greenall 9 Module Integration Working Group 17th July 2008

  10. Powering and Readout Conceptually Auxiliary Power connections Plug-in Circuit Plug-in Circuit Floating Power Supply Shunt Regulator Shunt Regulator Power In Power Out/In Power Out VDD VDD Linear Regulator Linear Regulator VCC VCC Pseudo-SPi Sensor SPi DC-DC Hybrids are floating w.r.t. each other Hybrid connections made using wire-bonds Hybrid 0 Hybrid 1 ABCn’s Operate in Legacy mode Data rate limited to 40MHz M M M M LVDS RX (CLK,COM, etc.) Powered from Module VDD LVDS TX (Module Data) Powered from SCTDAQ TX TX RX RX LV3 SCTDAQ 10 Module Integration Working Group 17th July 2008

  11. A Tentative Roadmap Consider using 18µm instead? • July’08 begin layout of hybrid • Will be fabricated as a Cu Kapton flex circuit • Using 35µm Cu (final version will use 12µm Cu) – build will otherwise be identical • Removes any uncertainty regarding asic/hybrid operation • Circuit will be laminated to rigid base board (FR4, carbon, ??) • Expect hybrid circuit(s) to start to become available Oct’08 • Circuits are being designed for both ASIC and Power evaluation • ABCns due back Oct’08? • First testing begins of asics • Expect release of ABCn’s Nov/Dec’08? 11 Module Integration Working Group 17th July 2008

  12. Proposal - continued • Hybrids for staves are challenged by available area at ends • Hybrid-2: for testing on stave • Assume MCC(s) is not available • Provide MCC function with either COTS chips or an FPGA, real-estate issue • Can consider a very wide hybrid (35 mm) to accommodate this, which still fits on stave • Aim for early 2009 • Hybrid-3: on stave with MCC(s) • Push for minimum area • Impact on MCC aspect ratio

  13. Bus cable access aperture 1.7 3.05 Bus Cable (Power+DCS) Hybrid Extension (?) 5.0 Kapton Hybrid 7.6 100.00 (Sensor) 96.3 110.00 (Bus cable width) ABCn 2.1 0402 Decoupling capacitor 7.5 3.05 Hybrid Extension (?) Bus Cable (Digital I/O) >24.0 What it means – hybrid on sensor (unbridged) with integrated bus cable • Notes: • Min. length of hybrid is 96.3mm • <2mm real estate available at ends, assuming sizing is to 100mm sensor • Where to locate MCC etc? (tape topology means 2 devices: 1 for power and 1 for digital I/O?) • Consider reducing gap between ABCns doesn’t help. A reduction of 0.5mm/gap increases asic-to-sensor bonding angle to 35º (max is 18º) • Necessary to increase hybrid length, will overhang sensor (rigidise?) • Dimensions fixed – no other option! Critical dimensions Ashley Greenall

  14. Simplified hybrid scheme without a real MCC ABCnext, 2 strings of 10 dataout 40 MHz Beam Clock x2 dataclock U1 multiplier x4 U2 Data interleave takes 2 80 MHz streams into 1 160 MHz stream

  15. Required Die • U1: clock multiplier: candidate identified • U2: data MUX: candidate identified • 3 channels of LVDS receiver • 1 channel of LVDS driver • Serial powering components

  16. Area • Strongly advocate an aggressive minimum area design for Hybrid-3 • Goal would be 97+? mm x 20 mm • Consider running bus work under the chips, not just in the space between chips (asymmetric design) • Driven by ceramic hybrid experience • Impact on location of pads in ABCnext Ver2? 5mm

  17. Layer (from bottom up) • Static shield layer • Traces and power • Traces and ground • Component and bond pads Hybrid real estate 20 mm 5mm 100 mm A goal would be to fit all the required die, and on-hybrid buswork in the 5mm zone or (lines) under the chips

  18. ABCnext, 2 strings of 10 dataout com clk 40 MHz Beam Clock x2 dataclock multiplier x4 mux bco L1 Data mux takes 2 80 MHz streams into one 160 MHz stream Wiring scheme for minimum area hybrid, route below chips

More Related