1 / 8

Assembly and test Hall.

Assembly and test Hall. Trigger support structure. Done for Yale and Grenoble assembly sites. Trigger light guides. delivered. Ready to be glued to scintillators produced by Yale. To be delivered. Test bench electronic setup. x32. PMT. Analog splitter. DFC. EMCal FEE. …. VME.

otto-barker
Télécharger la présentation

Assembly and test Hall.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Assembly and test Hall.

  2. Trigger support structure. • Done for Yale and Grenoble assembly sites.

  3. Trigger light guides. • delivered. • Ready to be glued to scintillators produced by Yale

  4. To be delivered • Test bench electronic setup. x32 PMT Analog splitter DFC EMCal FEE … VME … Transl. Trigger module NIM Delay Delay CCUSB ADC TDC DAQ/PC CAMAC

  5. DAQ. • DAQ installed by Terry and David last week

  6. 4 SM Platforms: • - Done. • - Successfully load tested and certified. • - Delivery expected next week. (after painting!)

  7. Strip handling tools. • By the end of July, I will send to YALE: • - 1 Strip handling tool fully equipped. • - 1 Strip handling tool support frame. • - all trigger scintillator support and positioning structure.

  8. Strap Foils. • 3600 precutted (Full EU production : 3 SM) • 1200 machined and cleaned (1 SM) Hand precutting station Final cleaning Wire cutting operation (80 straps stack)

More Related