1 / 25

PROJECT STATUS SUMMARY Presented to Work Environment Committee by Deba P. Mohapatra Interim Project Director June 26,

400 W. Washington Blvd. Learning Resource Center – Basement, Room 14 Los Angeles, CA 90015 Tel: (213) 763-3689 Fax: (213) 763-5990. PROJECT STATUS SUMMARY Presented to Work Environment Committee by Deba P. Mohapatra Interim Project Director June 26, 2006.

phallon
Télécharger la présentation

PROJECT STATUS SUMMARY Presented to Work Environment Committee by Deba P. Mohapatra Interim Project Director June 26,

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 400 W. Washington Blvd. Learning Resource Center – Basement, Room 14 Los Angeles, CA 90015 Tel: (213) 763-3689 Fax: (213) 763-5990 PROJECT STATUS SUMMARY Presented to Work Environment Committee by Deba P. Mohapatra Interim Project Director June 26, 2006

  2. Project Phasing July 2006 to Dec 2006 1 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  3. Project Phasing July 2006 to Dec 2006 2 LEGEND IN CONSTRUCTION IN DESIGN • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • Campus improvements - Removal of Existing Underground Fuel Tanks • South Campus – General • Campus Improvements – New Fuel Tanks • Liberal Arts Bldg – Utility Tunnel Repair • Construction Technology Bldg – Misc Finish Upgrade • Fashion & Cosmetology Bldg – Misc Finish Upgrade • Math & Science Bldg – Fire Life Safety • Fashion & Cosmetology Bldg - HVAC Upgrade • Campus Security Systems • Construction Technology Building – Upgrade Toilet Facilities • Auto/Metal Building – Structural Repairs Phase 2 • Learning Resource Center and Library – Phase 2 • Auto/Metal Building – Solar Photovoltaic System • Arts and Culinary Arts Building • Math and Science Bldg – Pumps & Others • Liberal Arts Bldg – Ceiling Mitigation Phase 2 • Child Development Center • South Campus – Demolition • Olive Street Parking Structure • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • Campus Improvements – Removal of Existing Underground Fuel Tanks • South Campus – General • Campus Improvements – New Fuel Tanks COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade

  4. Project Phasing Jan 2007 to June 2007 3 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  5. Project Phasing Jan 2007 to June 2007 4 LEGEND IN CONSTRUCTION IN DESIGN • Fashion & Cosmetology Bldg - HVAC Upgrade • Campus Security Systems • Construction Technology Building – Upgrade Toilet Facilities • Auto/Metal Building – Structural Repairs Phase 2 • Learning Resource Center and Library – Phase 2 • Auto/Metal Building – Solar Photovoltaic System • Arts and Culinary Arts Building • Child Development Center • Olive Street Parking Structure • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • South Campus – General • Campus Improvements – New Fuel Tanks • Liberal Arts Building – Utility Tunnel Repair • Construction Technology Building – Misc. Finish Upgrades • Fashion & Cosmetology Building – Misc. Finish Upgrades • Math & Science Bldg – Fire Life Safety • Transportation & Accessibility Improvements – On Site • Fashion & Cosmetology Bldg – HVAC Upgrade • Campus Security Systems • Construction Technology Bldg – Upgrade Toilet Facilities COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade • Math & Science Bldg – Pumps and Others • Liberal Arts Building - Ceiling Mitigation Phase 2

  6. Project Phasing July 2007 to Dec 2007 5 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  7. Project Phasing July 2007 to Dec 2007 6 LEGEND IN CONSTRUCTION COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade • Math & Science Bldg – Pumps and Others • Liberal Arts Building - Ceiling Mitigation Phase 2 • Child Development Center • Olive Street Parking Structure • Campus Improvements – Removal of Existing Fuel Tanks • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • South Campus – General • Liberal Arts Building – Utility Tunnel Repair • Construction Technology Building – Misc. Finish Upgrades • Fashion & Cosmetology Building – Misc. Finish Upgrades • Math & Science Bldg – Fire Life Safety • Transportation & Accessibility Improvements – On Site • Fashion & Cosmetology Bldg – HVAC Upgrade • Campus Security Systems • Construction Technology Bldg – Upgrade Toilet Facilities • Auto/Metal Bldg – Structural Repairs Phase 2 IN DESIGN • Auto/Metal Building – Structural Repairs Phase 2 • Learning Resource Center and Library – Phase 2 • Auto/Metal Building – Solar Photovoltaic System • Arts and Culinary Arts Building

  8. Project Phasing Jan 2008 to June 2008 7 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  9. Project Phasing Jan 2008 to June 2008 8 LEGEND IN CONSTRUCTION COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade • Math & Science Bldg – Pumps and Others • Liberal Arts Building - Ceiling Mitigation Phase 2 • Child Development Center • Olive Street Parking Structure • Campus Improvements – Removal of Existing Fuel Tanks • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • Liberal Arts Building – Utility Tunnel Repair • Construction Technology Building – Misc Finish upgrades • Fashion & Cosmetology Building – Misc. Finish Upgrades • Math & Science Bldg – Fire Life Safety • Fashion & Cosmetology Bldg – HVAC Upgrade • South Campus – General • Transportation & Accessibility Improvements – On Site • Campus Security Systems • Construction Technology Bldg – Upgrade Toilet Facilities • Auto/Metal Bldg – Structural Repairs - Phase 2 IN DESIGN • Learning Resource Center and Library – Phase 2 • Auto/Metal Building Building – Solar Photovoltaic System • Arts and Culinary Arts Building

  10. Project Phasing July 2008 to Dec 2008 9 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  11. Project Phasing July 2008 to Dec 2008 10 LEGEND IN CONSTRUCTION COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade • Math & Science Bldg – Pumps and Others • Liberal Arts Building - Ceiling Mitigation Phase 2 • Child Development Center • Olive Street Parking Structure • Campus Improvements – Removal of Existing Fuel Tanks • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • Liberal Arts Building – Utility Tunnel Repair • Construction Technology Building – Misc Finish upgrades • Fashion & Cosmetology Building – Misc. Finish Upgrades • Math & Science Bldg – Fire Life Safety • Fashion & Cosmetology Bldg – HVAC Upgrade • Transportation & Accessibility Improvements • Campus & Security System • Construction Technology Bldg – Upgrade Toilet Facilities • Auto/Metal Bldg – Structural Repairs – Phase 2 • South Campus – General IN DESIGN • Learning Resource Center and Library – Phase 2 • Auto/Metal Building – Solar Photovoltaic System • Arts and Culinary Arts Building

  12. Project Phasing Jan 2009 to June 2009 11 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  13. Project Phasing Jan 2009 to June 2009 12 LEGEND IN CONSTRUCTION COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade • Math & Science Bldg – Pumps and Others • Liberal Arts Building - Ceiling Mitigation Phase 2 • Child Development Center • Olive Street Parking Structure • Campus Improvements – Removal of Existing Fuel Tanks • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • Liberal Arts Building – Utility Tunnel Repair • Construction Technology Building – Misc Finish upgrades • Fashion & Cosmetology Building – Misc. Finish Upgrades • Math & Science Bldg – Fire Life Safety • Fashion & Cosmetology Bldg – HVAC Upgrade • Transportation & Accessibility Improvements • Campus & Security System • Construction Technology Bldg – Upgrade Toilet Facilities • Auto/Metal Bldg – Structural Repairs – Phase 2 • South Campus – General • Learning Resource Center & Library – Phase 2 IN DESIGN • Auto/Metal Building – Solar Photovoltaic System • Arts and Culinary Arts Building

  14. Project Phasing July 2009 to Dec 2009 13 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  15. Project Phasing July 2009 to Dec 2009 14 LEGEND IN CONSTRUCTION COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade • Math & Science Bldg – Pumps and Others • Liberal Arts Building - Ceiling Mitigation Phase 2 • Child Development Center • Olive Street Parking Structure • Campus Improvements – Removal of Existing Fuel Tanks • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • Liberal Arts Building – Utility Tunnel Repair • Construction Technology Building – Misc Finish upgrades • Fashion & Cosmetology Building – Misc. Finish Upgrades • Math & Science Bldg – Fire Life Safety • Fashion & Cosmetology Bldg – HVAC Upgrade • Transportation & Accessibility Improvements • Campus & Security System • Construction Technology Bldg – Upgrade Toilet Facilities • Auto/Metal Bldg – Structural Repairs Phase 2 • South Campus - General • Learning Resource Center & Library – Phase 2 • Auto/Metal Building – Solar Photovoltaic System IN DESIGN • Arts and Culinary Arts Building

  16. Project Phasing Jan 2010 to June 2010 15 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  17. Project Phasing Jan 2010 to June 2010 16 LEGEND IN CONSTRUCTION COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade • Math & Science Bldg – Pumps and Others • Liberal Arts Building - Ceiling Mitigation Phase 2 • Child Development Center • Olive Street Parking Structure • Campus Improvements – Removal of Existing Fuel Tanks • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • Liberal Arts Building – Utility Tunnel Repair • Construction Technology Building – Misc Finish upgrades • Fashion & Cosmetology Building – Misc. Finish Upgrades • Math & Science Bldg – Fire Life Safety • Fashion & Cosmetology Bldg – HVAC Upgrade • Transportation & Accessibility Improvements • Campus & Security System • Construction Technology Bldg – Upgrade Toilet Facilities • Auto/Metal Bldg – Structural Repairs Phase 2 • South Campus - General • Learning Resource Center & Library – Phase 2 • Auto/Metal Building – Solar Photovoltaic System IN DESIGN • Arts and Culinary Arts Building

  18. Project Phasing July 2010 to Dec 2010 17 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  19. Project Phasing July 2010 to Dec 2010 18 LEGEND IN CONSTRUCTION COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade • Math & Science Bldg – Pumps and Others • Liberal Arts Building - Ceiling Mitigation Phase 2 • Child Development Center • Olive Street Parking Structure • Campus Improvements – Removal of Existing Fuel Tanks • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • Liberal Arts Building – Utility Tunnel Repair • Construction Technology Building – Misc Finish upgrades • Fashion & Cosmetology Building – Misc. Finish Upgrades • Math & Science Bldg – Fire Life Safety • Fashion & Cosmetology Bldg – HVAC Upgrade • Transportation & Accessibility Improvements • Campus & Security System • Construction Technology Bldg – Upgrade Toilet Facilities • Auto/Metal Bldg – Structural Repairs Phase 2 • South Campus – General • Auto/Metal Bldg – Solar Photovoltaic System • Learning Resource Center & Library – Phase 2 • Arts and Culinary Arts Building

  20. Project Phasing Jan 2011 to June 2011 19 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  21. Project Phasing Jan 2011 to June 2011 20 LEGEND IN CONSTRUCTION COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade • Math & Science Bldg – Pumps and Others • Liberal Arts Building - Ceiling Mitigation Phase 2 • Child Development Center • Olive Street Parking Structure • Campus Improvements – Removal of Existing Fuel Tanks • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • Liberal Arts Building – Utility Tunnel Repair • Construction Technology Building – Misc Finish upgrades • Fashion & Cosmetology Building – Misc. Finish Upgrades • Math & Science Bldg – Fire Life Safety • Fashion & Cosmetology Bldg – HVAC Upgrade • Transportation & Accessibility Improvements • Campus & Security System • Construction Technology Bldg – Upgrade Toilet Facilities • Auto/Metal Bldg – Structural Repairs Phase 2 • South Campus – General • Auto/Metal Bldg – Solar Photovoltaic System • Learning Resource Center & Library – Phase 2 • Arts and Culinary Arts Building

  22. Project Phasing July 2011 to Dec 2011 21 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  23. Project Phasing July 2011 to Dec 2011 22 LEGEND IN CONSTRUCTION COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade • Math & Science Bldg – Pumps and Others • Liberal Arts Building - Ceiling Mitigation Phase 2 • Child Development Center • Olive Street Parking Structure • Campus Improvements – Removal of Existing Fuel Tanks • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • Liberal Arts Building – Utility Tunnel Repair • Construction Technology Building – Misc Finish upgrades • Fashion & Cosmetology Building – Misc. Finish Upgrades • Math & Science Bldg – Fire Life Safety • Fashion & Cosmetology Bldg – HVAC Upgrade • Transportation & Accessibility Improvements • Campus & Security System • Construction Technology Bldg – Upgrade Toilet Facilities • Auto/Metal Bldg – Structural Repairs Phase 2 • South Campus – General • Auto/Metal Bldg – Solar Photovoltaic System • Learning Resource Center and Library – Phase 2 • Arts and Culinary Arts Building

  24. Project Phasing Jan 2012 to June 2012 23 STRUCTURAL REPAIRS CEILING MITIGATION EU SOUTH CAMPUS OLIVE ST. PARKING STRUCTURE CDC

  25. Project Phasing Jan 2012 to June 2012 24 LEGEND IN CONSTRUCTION COMPLETED • Construction Technology Yard (CTY) • Auto/Metal Building (F) – HVAC, Hazmat & Modernization • Learning Resource Center and Library – Phase 1 • Auto/Metal Building – Reroofing • Arts and Culinary Arts Building – Garden Room • Liberal Arts Building – Electrical Upgrade • Construction Technology Building – General • Information Technology (IT) Conduit Installation • Auto/Metal Building – Structural Upgrade • Math & Science Bldg – Pumps and Others • Liberal Arts Building - Ceiling Mitigation Phase 2 • Child Development Center • Olive Street Parking Structure • Campus Improvements – Removal of Existing Fuel Tanks • Electrical Site Distribution • RWGPL – “F” Ramp • Gymnasium • Liberal Arts Building – Utility Tunnel Repair • Construction Technology Building – Misc Finish upgrades • Fashion & Cosmetology Building – Misc. Finish Upgrades • Math & Science Bldg – Fire Life Safety • Fashion & Cosmetology Bldg – HVAC Upgrade • Transportation & Accessibility Improvements • Campus & Security System • Construction Technology Bldg – Upgrade Toilet Facilities • Auto/Metal Bldg – Structural Repairs Phase 2 • South Campus – General • Auto/Metal Bldg – Solar Photovoltaic System • Learning Resource Center and Library – Phase 2 • Arts and Culinary Arts Building Note: Scheduled for completion March 2012

More Related