Folsom Dam Joint Federal Project (JFP)

Central Valley Flood Protection Board Approval of Project Cooperation Agreement Amendment No. 3, Acceleration of Partner Funds for the Folsom Dam Joint Federal Project . Folsom Dam Joint Federal Project (JFP). Multi-agency effort under the CVFPB approved Folsom Dam Modifications Project

reya
Télécharger la présentation

Folsom Dam Joint Federal Project (JFP)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Central Valley Flood Protection BoardApproval of Project Cooperation Agreement Amendment No. 3, Acceleration of Partner Funds for the Folsom Dam Joint Federal Project

  2. Folsom Dam Joint Federal Project (JFP) • Multi-agency effort under the CVFPB approved Folsom Dam Modifications Project • Design and construct the JFP to meet Federal, State, and local objectives for Folsom Dam • Improves the ability to manage large flood events by lowering the spillway elevation to allow more water to be released earlier in a flood event

  3. Project Status and Schedule 8. 2017/Q3: TESTING, COMMISSIONING & SITE RESTORATION CONSTRUCTION 9. 2017/Q3: Water Control Manual Complete 4. 2014/Q3: Control Structure Construction Complete 7. 2017/Q3: Upstream & Downstream Construction Complete 5. 2014/Q2: Cutoff Wall Construction Complete

  4. Project Partnering Agreement (PPA) PPA (11-Feb-05) Amendment 1 (24-Aug-09) Amendment 2 (28-Apr-10) Amendment 3 – Acceleration of Funds Project Partnering Agreements- CVFPB Partner Commitments: • October 2017 Optimal Completion • Actively seek opportunities to accelerate the schedule

  5. Annual Expenditure & Projected Funding

  6. Accumulated Expenditure & Projected Funding

  7. FY 12 Funding and Obligations(Oct 2011 – Sept 2012) Funding: • FY12 USACE Optimal Capability = $28M • FY12 President’s Budget = $21M • House Sub-Committee Budget = $19.028M • Continuous Resolution Ending Nov 18 = $8.1M Obligations:

  8. Staff Recommendation Staff recommends that the Board approve Resolution No. 11-30 (Attachment C) and: • Approve Amendment No. 3 (Attachment A) to the PCA authorizing the acceleration of funds to the USACE in an amount not to exceed the current estimate of the non-federal sponsors’ required cash contribution for the JFP, less any funds previously contributed, for the immediate use by the USACE and; • Delegate to the Board President the authority to execute the amendment in substantially the form attached hereto.

  9. Questions? CVFPB: Kent Zenobia, PE, DEE kzenobia@water.ca.gov Wilbur Huang, PE, CFM whuang@water.ca.gov USACE: Elizabeth Salyers, PE Elizabeth.A.Salyers@usace.army.mil

  10. Extra Slides for Reference

  11. What is the JFP? • A new auxiliary spillway adjacent to the main dam, including: • approach channel • control structure • spillway chute • stilling basin • Improves the ability to manage large flood events by lowering the spillway elevation to allow more water to be released earlier in a flood event.

  12. Background JFP will work in conjunction with upgraded levees downstream to achieve a 200-year level of protection.

  13. Background Schedule History • Original schedule – 2015 completion • 35% design • accepted as baseline schedule • Revised schedule – 2018 completion • More detailed design • Reviewed & recommended by consultants • Unsatisfactory to all parties • Joint task force revised schedule – 2017 completion

  14. Commitments • October 2017 completion: Optimal Completion Date • Aggressive • Realistic • Weighs risks and rewards developed by Task Force • The USACE will continue to seek opportunities to accelerate the schedule

  15. Folsom Dam & new Auxiliary Spillway

  16. Schedule: Milestones & Critical Path Final Design and Deliverables: • Cut-off Wall 95% Review 13 April 2012 Upstream and Downstream Design 95% Review 5 October 2012 Record of Decision (ROD) Signed 31 Mar 2013 Control Structure: Bulkhead Gates Installed 15 July 2014 Contract Complete 3 October 2014 Cut off Wall (schedule being refined) NTP 1 April 2013 Contract Complete (NLT) 16 January 2014 Chute and Stilling Basin & Approach Channel: NTP 30 August 2013 Contract Complete 30 October 2017 • Contract Complete (Commissioning and Testing) 30 October 2017

  17. Control Structure • Status: 14%Complete • Rockbolting & Blasting • Accelerated Schedule due 28 Dec 11 • Bulkhead Gates installed 15 July 2014

  18. Project Partnering Agreement – Department of Water Resources Signed 11-Feb-05 Amendment 1 signed 24-Aug-09 Amendment 2 signed 28-Apr-10 Amendment 3 – Acceleration of Funds Memorandum of Agreement – Bureau of Reclamation Signed 22-Aug-06 Land Use Agreement – Bureau of Reclamation Signed 16-Sep-10 Memorandum of Agreement – Sacramento Area Flood Control Agency (Restoration) Amendment signed 24-Jul-08 Project Partnering Agreements Partner Commitments: • October 2017 Optimal Completion • Aggressive and Realistic • Weighs risks and rewards developed by Task Force • We will continue to actively seek opportunities to accelerate the schedule if/when options arise within funding limits

  19. Current Schedule Milestones Final Design and Deliverables: Chute and Stilling Basin 65% Review 30 November 2011 (A: 30 Oct 2011 Cutoff wall/Rock Plug Decision Point 10 November 2011 (A) Cofferdam 35% Review 14 November 2011 (A: 10 Nov 2011) Approach Channel 65% Review 17 February 2012 • Administrative Draft EIS 13 March 2012 • Cut-off Wall 95% Review 13 April 2012 Upstream and Downstream Design 95% Review 5 October 2012 RTA Follow-On Phases 7 December 2012 Record of Decision (ROD) Signed 31 Mar 2013 Control Structure: Bulkhead Gates Installed 15 July 2014 Tainter Gates Installed 15 August 2014 Contract Complete 3 October 2014 Cut off Wall NTP 1 April 2013 Contract Complete (NLT) 16 January 2014 Chute and Stilling Basin & Approach Channel: NTP 30 August 2013 Contract Complete 30 October 2017

  20. Current Schedule Critical Path Final Design and Deliverables: Record of Decision (ROD) Signed 31 Mar 2013 • Cut-off Wall: • NTP 1 April 2013 • Construction Complete (NLT)** 16 January 2014 Control Structure: Bulkhead Gates Installed 15 July 2014 Approach Channel: Start Rock Plug Excavation** 16 January 2014 Walls and Slabs 24 June 2016 Wet Excavation 21 September 2017 Chute and Stilling Basin : Chute and Stilling Basin work will run concurrently with Approach Channel work with Approach Channel driving the critical path Contract Complete (Commissioning and Testing) 30 October 2017 ** Cut-off Wall schedule currently being refined

  21. Control Structure • Status: 14%Complete • Rockbolting and Blasting. • Accelerated Schedule due 28 Dec. Milestone Dates May 07ROD 24 Sep 10Contract award (Continuing Contract/design bid build) 6 Dec 10 NTP 16 Sep 11 Design revision 4 modification award 31 Oct 11 Design revision 1, 3 & 5 modification award 30 Nov 11 Design revision 2 and 6 modification award 28 Dec 11 Recovery Schedule due 15 Jul 14 Bulkhead Gate Completion (critical path) 15 Aug 14 Tainter Gate Completion (not critical) 2 Sep 14 Substantial Completion (not critical) 3 Oct 14 Construction Complete (not critical)

  22. Funding History

  23. Control Structure • Status: 14%Complete • Rockbolting and Blasting • Accelerated Schedule due 28 Dec 11 Milestone Dates 6 Dec 10 NTP 28 Dec 11 Recovery Schedule due 15 Jul 14 Bulkhead Gate Completion 15 Aug 14 Tainter Gate Completion 3 Oct 14 Construction Complete