1 / 29

CAUSES OF CLAIMS AND AVOIDANCE

CAUSES OF CLAIMS AND AVOIDANCE. N D Sharma. CLAIM. A Claim is a request for reimbursement of cost and / or time from one Party to another. This may be for a progress payment or a variation, or something else

sissy
Télécharger la présentation

CAUSES OF CLAIMS AND AVOIDANCE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CAUSES OF CLAIMS AND AVOIDANCE N D Sharma

  2. CLAIM A Claim is a request for reimbursement of cost and / or time from one Party to another. This may be for a progress payment or a variation, or something else Under the Contract either party may have a claim’ (PPMO SBD does not envision Employer’s Claim)

  3. CLAIMS Contract provides for procedures making contractual claims by the contractor arising out of including: •  A response to events which the contractor was not required to anticipate • For additional payment or additional time • The legal/contractual consequence of events

  4. CLAIMS Contractual Claims include: • Additional work claims – cost & profit • Damages claims – cost only • Neutral risk claims – time only Common Legal (outside the Contract) Claims: • Claims in tort • Ex- Gratia

  5. CLAIMS Claims may be arising out of several factor including: • Manner in which contract was secured (Low bidding ) • The Engineer and roles in designing • The level of definition of the scope of works • Political aspects • Legal / contractual

  6. CAUSES OF CLAIMS • Inability to recognize all the risks and failure to deal adequately with those including their sharing amongst the contracting parties • Risks being either ignored or dealt with arbitrarily • Employer’s tendency to own all the rights and shift risks and obligations to the contractor • Inadequate pre-bid investigations; developing projects hastily not knowing the potential risks

  7. RISKS OWNERSHIP

  8. RISKS OWNERSHIP

  9. RISKS OWNERSHIP

  10. RISKS OWNERSHIP

  11. RISKS OWNERSHIP

  12. RISKS OWNERSHIP

  13. RISKS OWNERSHIP

  14. CAUSES Of CLAIMS • Awards of contracts going to very low rate bidding contractors, looking for opportunity to put in claims leading to disputes. • Inefficient contract administration on the part of the Employer/Purchaser • Force-Majeure conditions not recognized. • Failure on the part of the actors of the contract to timely discharge their duties and meet contractual obligations

  15. CLAIM TIMELINE • If the Contractor considers himself to be entitled to an EOT or addition payment or both, he must give notice to the Engineer as soon as practicable and “not later than28 days after the Contractor became aware, or should have become aware, of the event or circumstance” giving rise to the claim. If he fails to make claim on time he is not entitled to it.

  16. CAUSES OF CLAIMS AND AVOIDANCE AVOIDANCE OF CLAIMS

  17. AVOIDANCE OF CLAIMS • Parties must know their contracts well; • ‘Every contract is unique’; though this saying is somewhat diluted by the introduction of SBDs, elaborate regulations (PPR) and the PPA • Parties must understand that they are at par as sovereign partners of the contract, to be regulated by their contract and the governing law.

  18. AVOIDING CLAIMS Avoidance of Claims through Contract Administration • Drawings, information and ‘Holds’ • Approvals • Ground conditions • Relationships • Consultants’ performance • Access to works • Public authority / government bodies • Payment • The manner in which early problems are dealt with • Performance of nominated sub-contractors

  19. AVOIDING CLAIMS Avoidance of Claim Situations by Contractor’s Actions: • carefully review the bidding documents including drawings and specifications; • price the job adequately to make fair profit; • manage and perform contract with due diligence; • respect specifications and instructions;

  20. AVOIDING CLAIMS Avoidance of Claim Situations by Contractor’s Actions: • use materials, plant as specified and ensure quality; • take care of works in progress by appropriate measures; • comply with all applicable laws, regulations including safety related;

  21. AVOIDING CLAIMS Avoidance of Claim Situations by Contractor’s Actions: • inform the Employer in advance whenever an event occurs which is likely to increase the cost of the works and or the time of completion; • remedy defects well before expiry of the defect liability/ defect notification or warranty period; and • present claims, if any, in a timely manner.

  22. AVOIDING CLAIMS Avoidance of Claim Situations Good documentation: CONTRACTOR’S PROGRAM • Reflect Contract requirements • Include Contract milestones • Show sequence of works • Incorporate resource and other constraints • Supported by Method Statement

  23. AVOIDING CLAIMS Employer’s Actions at. thé Procurent Stage: • inform and instruct bidders on the procedure for preparation and submission of bids; • describe the standards required; • inform bidders of the criteria for evaluating bids; and • also inform that the only bidder having the experience and capacity to execute the

  24. AVOIDING CLAIMS Employer’s Actions at. thé Procurent Stage: • in the case of works, provide detailed site investigation report and other information related to the site of which the Employer is in possession • define the conditions of contract and method of payments; • describe procedures for acceptance of final products ; • and for issuance of contract amendments

  25. AVOIDING CLAIMS Employer’s Actions at. thé Procurent Stage: • define adequately quality control procedures • inform about the rights and duties of the parties and the remedy against defaulter • provide for amicable settlement, adjudication and arbitration mechanisms for settlement of disputes FIDIC- Based conditions stipulate that: • an independent Engineer, empowered with authority to administer the contract with some pre-disclosed restrictions, will supervise the contract.

  26. AVOIDING CLAIMS Employer’s Actions at. thé Procurent Stage: • the Employer has produced a design for the work through a competent Engineer • the possession of site and access thereto will be made available as specified in the documents or within reasonable time so that the activities as scheduled would not be adversely affected

  27. EMPLOYER’S CLAIM Employer’s Claim: • Entitlement: under any Clause of the contact or otherwise in connection with the Contract. • No time bar for the notice (should be given as early practicable- can be given by the Employer or by the Engineer • Engineer to refer to engineer for determination!

  28. Engineer's Supremacy • Employer is denied to set off against or make any deduction from a certified amount or otherwise claim against the Contractor unless done in accordance with the contract provisions under Clause

  29. HANDLING OF CLAIMS Employer and Contracor’s Joint Actions: • Keep good record systems and agree on facts • Respond to challenges / issues promptly • Monitor progress • Establish claims systems and procedure • Review resourcing • Do not assume everything will come good at the end of the day • Settle amicably or go for adjudication

More Related