An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LEADERS IN CORROSION PREVENTION AND SEALING TECHNOLOGY Denso Products for Civil Engineering Specifications for the Water Industry P1 and P2

  2. Just what are P1 and P2 Specifications?

  3. CIVIL ENGINEERING SPECIFICATION FOR THE WATER INDUSTRY5th EDITION5.14 Protection of Ferrous Pipes, Joints and Fittings 1. Ferrous pipes, joints and fittings shall be cleaned and all loose rust removed before protection is applied.2. External protection for joints and fittings shall comprise:

  4. P.1The application of a thin continuous coating of petroleum paste over the whole area to be protected as a primer. Where bolt heads, nuts, flanges and other projections arise a profiling mastic shall be used to give a smooth external profile. The joint or fitting shall be wrapped with a protective tape. The minimum application shall be a spiral wrap using 55% overlap. The tape shall extend along 150mm of the barrel of the pipe on each side of the joint or fitting.

  5. orP.2The application of a continuous coating of bitumen primer over the whole area to be protected. Where bolt heads, nuts, flanges and other projections arise a profiling mastic shall be used to give a smooth external profile. The joint or fitting shall be wrapped with a self adhesive, cold applied, rubber bitumen tape with a PVC backing. The minimum application shall be a spiral wrap using 55% overlap. The tape shall extend along 150mm of the barrel of the pipe on each side of the joint or fitting.

  6. For both P1 and P2 Specifications: General Surface Preparation of Pipe Joints Important: Before products can be applied, the joint area must be cleaned…

  7. Clean the joint and adjacent pipe thoroughly so that they are free from loose scale, rust, dirt etc.

  8. P1Civil Engineering Specification for the Water Industry Application Method….

  9. Step 1:Apply a coat of Denso Paste to the joint and surrounding pipe

  10. Step 2:Apply Denso Profiling Mastic, working into all hollows and voids, to create a smooth contour for tape wrapping

  11. Step 3: Spirally apply Denso Tape using a 55% overlap to create a double wrap. Smooth out all air pockets and wrinkles.

  12. Step 4: Thefinished P1 Pipe Joint Protection

  13. P2Civil Engineering Specification for the Water Industry Application Method….

  14. Step 1:Apply a coat of Denso Primer D to the joint and surrounding pipe

  15. Step 2:Apply Denso Profiling Mastic, working into all voids and gaps, to create a smooth contour for tape wrapping

  16. Step 3:Spirally apply Densoclad Tape using a 55% overlap to give a double layer. Smooth down tape making sure there are no air pockets or wrinkles.

  17. Step 4: The finished P2 Pipe Joint Protection.

  18. A Few Completed Projects…

  19. Northumbrian Water, Teeside: Refurbishment of Conduit 58

  20. Northumbrian Water, Teeside

  21. Thames Water, Ashford Common Water Treatment Works.

  22. Thank You for Your Attention

More Related