EVLA Front-End CDR

EVLA Front-End CDR. Cryogenic & Vacuum Systems. Cryogenics &Vacuum Systems Overview. EVLA Required Cryogenics and Vacuum System Upgrades Design Parameters Gas flow system Vacuum system Hardware Compressors Drivers. EVLA Upgrades. EVLA upgrades to the receiver system include:

wycliff
Télécharger la présentation

EVLA Front-End CDR

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EVLA Front-End CDR Cryogenic & Vacuum Systems EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006

  2. Cryogenics &Vacuum SystemsOverview • EVLA Required Cryogenics and Vacuum System Upgrades • Design Parameters • Gas flow system • Vacuum system • Hardware • Compressors • Drivers EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006

  3. EVLA Upgrades • EVLA upgrades to the receiver system include: • S-Band (New) • Ka-Band (New) • C-Band (relocated out of the “A” rack) • Ku-Band (relocated out of the “A” rack) The impact is, a higher gas flow rate and a higher volume vacuum requirement. EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006

  4. Gas Flow System Design Parameters • Three Types of Coldheads used in system • Type 1020 Coldhead: 28 scfm • Type 350 Coldhead: 17 scfm • Type 22 Coldhead: 9 scfm EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006

  5. Gas FlowSystem Design Parameters • EVLA gas flow requirements dictated that a third helium compressor be installed. • Compressor A circuit requires 43 scfm • S(350), Ku(350), Q(22) • Compressor B circuit requires 43 scfm • X(22), K(350), Ka(350) • Compressor C circuit requires 45 scfm • L(1020), C(350) EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006

  6. Compressor B Helium Compressors Compressor A Compressor C EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006

  7. Vacuum System Design Parameters • EVLA vacuum requirements resulted in the smaller of the two VLA pumps being replaced with a larger unit. • Vacuum Pump A circuit • X, C, S, Ku • Vacuum Pump B circuit • Ka, K, Q, L EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006

  8. Vacuum SystemPump Controlled by the card cage EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006

  9. HardwareCompressors • Compressor modifications justification: • CTI discontinued the 3 HP piston type compressor. • Refurbished CTI 1020R compressors are $11,500 each. • CTI 1020R compressors were rated at 51 scfm, but had a higher gas discharge temperature than NRAO compressors • NRAO modified and built a compatible compressor at a cost of $4600, which is rated at 48scfm. EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006

  10. HardwareDrivers • Coldhead Drivers • New Scott-T boxes • Designed, tested and installed • Designed to work with the new receiver card cages • Not compatible with the old style card cage • Each Scott-T will drive up to 4 coldheads • Interim • Used the old style coldhead drivers until new card cages are installed EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006

  11. New Scott-T Boxes HardwareColdheadDrivers EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006

  12. Summary • Discussed the additional Helium gas flow need for EVLA, that resulted in the addition of a third circuit. • Discussed the new Scott-T coldhead drivers. • Discussed cost savings related 1020R compressor modifications. • 87% of Cryo budget has been expended to date; • Purchased 104 model 350 coldheads • Purchased 30 Helium compressors • Remaining budget is sufficient to cover ancillary hardware. EVLA Front-End CDR – Cryogenic & Vacuum Systems April 24, 2006