1 / 12

Substation L1/ MCC L1 Update #2

Substation L1/ MCC L1 Update #2. July ??,2012. Status of Procurement. Substation All approval drawings submitted Testing is expected to take place August 8-10 Delivery will occur soon after testing is completed MCC All approval drawings submitted

wynn
Télécharger la présentation

Substation L1/ MCC L1 Update #2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Substation L1/ MCC L1 Update #2 July ??,2012

  2. Status of Procurement • Substation • All approval drawings submitted • Testing is expected to take place August 8-10 • Delivery will occur soon after testing is completed • MCC • All approval drawings submitted • Expected arrival date of Mid to Late August (55-75 working days after approval drawings reach factory floor) • Drawings approved on 5/30/2012 • Cable • All cable delivered • Stored in LINAC • 350 MCM will be stored at warehouse until installation is closer • Panelboard • Delivered • Needs to be assembled

  3. Status of Procurement (Cont.) • Safety Switches • Delivered • Stored in LINAC • Cable Supports • Delivered • Stored in LINAC • Support Structures • Will be built out of unistrut • Assembly has not yet begun • Support frames will be built in house • Junction Box • Drawing is complete • Fabrication companies have yet to respond • Since only one needs to be ordered it is unlikely that a company will construct this enclosure • Will be submitting the drawing to the machine shop soon

  4. Project Schedule • Currently at a stand still • Complexity • Safety issues • Install should still be okay for originally planned September install • General Cleanup 2-3 weeks prior to shutdown of substation • Temporary electrical power will be setup the weekend prior • It could take riggers several days to remove and install substations • Small clearances • Large weights • May be several more days if given okay to shore the floor

  5. Issues • Substantial Weight Increase • 10,500 lbs. vs. 17,700 lbs. • Gallery floor has a very low load limit (350 lbs./sq. ft.) • This could effect everyday operations • Fork lifts, Tour groups, Removing equipment from downstairs • Could be wrong • Stevenson has no suitable indoor crane • Ceiling height is too low for carrydeck crane • 55,000 lbs. • Shoring the floor may not be a possibility • Much of the transformer will need to be dismantled • Secondary bus bars, frame, sheet metal • Increases electrician time

  6. Suggestions • FESS has been notified that it needs to begin looking into ways to fix this issue • Cut a hole in the ceiling • Has been done at other sites around the lab • Install outside • Requires Federal to make outdoor gear • Engineering Expense • Siemens subcontract issue • Expensive cable runs • Rigging job would be simplified • Aesthetics committee

  7. Temporary Power Plan • “Siphon” power from panel DHP-L2-2 Circuit #1 • Cable will be run on temporary supports • 4 conductor 350 mcm cable is heavy (~7 lbs./ft.) and will need an open area to lay • Some cable will be put on the floor but will be covered by a cable bridge • Setup 2 temporary panel board(s) • Run cable to individual loads • DHP panels, MCC loads • DHP panels will be locked out and tagged out • Group lockbox • MCC loads will have configuration control locks • We will check current prior to using any MCC loads to ensure they will not trip off during operation • Power will be provided 24 hours a day

  8. Installation Costs • 1 Crew of Riggers (4-6 men) • Unknown Cost • Will remain unknown until a plan is put in place by FESS • 2 Week of Electricians • $100/manhour x 2 electricians x 80 hours = $16,000 • Cable • 2/0 - $3,500 • 2 – $3,700 • House Power • $4,200 for panelboard • $2,000 for assembly • Miscellaneous Stock purchases • $2,100 Total Cost : $31,500 -> excluding rigging Previous Estimate: $23,000 -> excluding rigging Increase can be attributed to increased electrician time and panelboard cost

  9. Commissioning • Visual Inspection • Hi-Pot • Disconnect panel boards from temporary power • Reconnect panel boards • DHP-L1-1 will be turned on first • Fire alarms • Lighting • Etc. • DHP-L1-2 • DHP-L1-3

  10. What Will Become of the Removed Equipment? • Transformer will be kept as a spare • Currently have 1 spare for 8 transformers (5 – high rise, 3 – LINAC) • Transformer will be examined to make sure it is in good working order • Will be stored in Booster parking lot • Will be placed on a truck the same day it is removed to avoid excess rigger fees • Breakers • Will be rebuilt and tested • Used as spares • Primary Switch • Will be rebuilt and tested • Used as a spare

  11. Future PIP Project ???? • Create Site Wide Monitoring Network PIP Project PIP Project Not PIP Note: CG-1 has been moved from PIP schedule, and will now be handled by headquarters

  12. What we will do • Move Spare to F0 • All tests that are performed on newtransformers will be performed on spare • Oil samples • Order new substation Booster Y-BE2 Update Y-BW2 Y-BE2 • What we did • Current measurements • Voltage measurements • Thermal imaging scans • Listened • Disconnected all loads