1 / 8

11 T Dipole Status at CERN Dec-12

11 T Dipole Status at CERN Dec-12. M. Karppinen. Construction Status. 2 Cu-coils and 1 Nb 3 Sn (WST strand) have been wound and cured : No issues with cable stability, winding tension typically around 30 kg.

zizi
Télécharger la présentation

11 T Dipole Status at CERN Dec-12

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 11 T Dipole Status at CERN Dec-12 M. Karppinen

  2. Construction Status • 2 Cu-coils and 1 Nb3Sn (WST strand) have been wound and cured: • No issues with cable stability, winding tension typically around 30 kg. • Cu-coil being prepared for a shortened reaction cycle to check the tooling and the procedures. It will also give the first idea of the high-T resistance of the S2-glass braiding. • WST coil will be reacted in Jan-13 and used for mechanical models. • Cored cable made of LARP 54/61 is being insulated with S2-glass-Mica and winding will commence on the 2nd half of Jan. • Tooling: • Reaction furnace commissioning in progress. • Vacuum impregnation system delayed again due to problems with heater wire feed-throughs. We are looking into alternative solutions to pot the first coils (vac. bag). • Impregnation tooling and reaction tooling complete. • Collaring tooling ordered, coil assy tooling delivered.

  3. Mechanical model • FNAL modified practice coil section are presently used. Issues with asymmetric coil geometry and incorrect pole angle. • Collar pressing surfaces show plastic deformation and the long collar mid-plane will be adapted to avoid top and bottom halves lining up. • Awaiting for WST coil with more accurate geometry. To adapt (-0.2..0.3) Defrom.

  4. Status of Topics Requested by Sponsors • Magnet test protocol: • First draft of test program including warm and cold test has been sent to FNAL. • Contact between Hugo (cold test), Lucio(magnetic measurements) and Guramestablished. • Quench protection studies: • Draft of the studies made by Bernhard using ROXIE has been circulated and it has published at CERN as an internal note. • Studies on inter-layer heaters in progress. • Trial of inter-layer heater concepts underway. • FNAL studies are in progress. • A video meeting with this topic is planned for early January.

  5. Status of Topics... • Structural analysis: • Two out of 4 concepts have been analysed at CERN: CERN coil with CERN coldmass, FNAL coils with CERN cold mass. • The FE-modeling features, material properties etc. were discussed during FNAL visit and the models were updated accordingly. • Both cases can be made with practical shims and the stress level stay well within a safe range coils and other components. • FNAL coils with two alternative coldmass concepts were discussed. Further optimisation is in progress in view of a mechanical model. • It was agreed that FNAL would analyse the variant with CERN coils in FNAL coldmass. • A video meeting is planned on this topic on 18 December.

  6. CERN Procurement Status (1/2) • Collars: • Full set (2-m-long collared coil) of collars at CERN. Dimensional control confirmed very good dimensional accuracy. • An order for fin-blanking of 3 sets with 2 optional sets has been raised and press tool is being made. • Yoke laminations: • Full 1-in-1 yoke has been delivered and dimensionally inspected at CERN. • 2nd 1-in-1 yoke has been ordered and expected by May-13. • 2-in-1 yoke order has been raised. Delivery of 8 off lamination sets (3 lams) is expected in Feb-13, 300 mm worth of lams for mechanical model by End of Mar-13, the 2-m-long yoke by Jun/Jul-13. • Outer shells: • Order placed and base material delivery expected in Mar-13. • Welding trials (1 m) in Apr-13.(TBC) • 2-m-long 1-in-1 shells in May, 2-in-1 in July.(TBC)

  7. Procurement (2/2) • Wedge profiles made from ODS-alloy: • Wedges 1-2 delivered. Dimensional accuracy very good. • Wedges 3-5 completed and being delivered. • End spacers: • 5 sets of CNC-machined keys and saddles ordered. • 5 sets of intermediate SLS spacers being ordered. • Pole wedges: • 2 sets of Ti-wedges ordered. • End plates: • Tendering started for 1-in-1 and 2-in-1 plates.

  8. SC-strand • CERN expect delivery of 30 km RRP 132/169 by X-mas. • Cabling trial planned provisionally early Jan-13. • Extracted strand measurement by Mid-Feb. • Cabling of 1..3 unit lengths for CERN 2 m coil towards End-Feb. • Cable Insulation by Mid-Mar • 15 km of 108/127 in stock at CERN • Cabling of one unit length to fit in the cabling schedule. This could be supplied to FNAL once 132/169-cable has been validated.

More Related