An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Post Award – Activities >Post Award – Issues >

  2. POST AWARD Activities

  3. Post Award Activities • Contract signing • CPG Submission • Release of Initial Advance (Supply) • Finalization of L2 Network • Detailed Engineering , Drawing Approval & Type Testing • Sub-vendor / Sub-Contractor’s Approval • Quality Plan Approval

  4. Post Award Activities • Inspection and Despatch Clearance • Physical Execution of Work at Site • Project Monitoring • Opening of LC, Processing of Bills and Release of Payment • Technical Approval of Quantity Variation including New Items • Amendment(s) to the contract • Time Extension and Liquidated Damages

  5. Post Award Activities • Contract signing • The formal contract agreement to be signed between POWERGRID and Contractor in two original copies appending other documents like GCC, Tech.Spec and SCC .

  6. Post Award Activities • CPG Submission • To submit to Corporate Contracts for Corp. Packages and Regional Contracts for Site Packages. • CPG to be scrutinized by CC Contracts and sent to Corp.Fin for verification with bank. • Accepted CPG to be forwarded to Regional Finance under intimation to CC Contracts.

  7. Post Award Activities Release of Initial Advance (Supply) • For release of initial advance, the following formalities to be completed : • Unconditional Acknowledgement of LOA. • Submission of CPG and Invoice • Submission of BG for equivalent amount • Finalization of L2 Network.

  8. Post Award Activities Finalization of L2 Network • Responsibility: CMG for CC Packages. • :Reg.PMD for Site Packages • The L2 Network will cover finalization of sub-vendor, quality plan, Engineering activities, Inspection, Manufacturing and supply, civil, erection, testing & commi-ssioning. • Revision in quantities in L2 Network with the approval of ED Region.

  9. Post Award Activities • Detailed Engineering , Drawing Approval & Type Testing • The detailed Engineering activities shall be : Drawing approval, approval of design calculations and receipt of other technical details, witness & approval of type test.

  10. Post Award Activities • Sub-vendor / Sub-Contractor’s Approval • Responsibility : Corp.QA&I for non-QR supply items of Corp.Packages. • Regional Engg / FQA for supply items of site packages. • Sub-contractor proposed by the main contractor for erection / civil portion of Corp.Packages shall be finalized by Region after verifying sub-contractor’s qualification / experience.

  11. Post Award Activities • Quality Plan Approval • Responsibility : Corp.QA&I. • The manufacturing quality plan for a particular equipment / material is generally valid for a period of three years.

  12. Post Award Activities • Inspection and Despatch Clearance • CIP : It is clearance of stage inspection either accepting or rejecting the material. • MICC : issued for billable items as per LOA.

  13. Post Award Activities Physical Execution of Work at Site • L3 Network shall be developed at site for monitoring of day-to-day activities. • Execution site to ensure that only material cleared under category-A CIP is cleared for erection.

  14. Post Award Activities Project Monitoring • Monthly progress reports to be submitted by PMD to ED/Region highlighting the progress of the following activities : • Engg. activities • Sub-vendor approval • Inspection status • Supply status • Site activities • Payment status • Budgetary targets • Status of BGs and Contract Closing

  15. Post Award Activities • Opening of LC, Processing of Bills and Release of Payment • Responsibility :- • Concerned Site & Regional Finance for Corporate Packages. • Concerned Execution site & local Finance for Regional Packages. • LCs to be opened for a quarter on revolving basis. • LC charges to be borne by the Contractor. • Payments in foreign currency : to be made by IF Section/CC.

  16. Post Award Activities • Technical Approval of Quantity Variation including New Items. • Corp.Engg.for corporate packages and Regional Engg.for Regional packages. • Variation may be due to change in quantities as per site requirement or change in scope of work. • All such variations to be processed in two stages – 1st technical approval; 2nd administrative approval for issue of change of order. • Once construction drawings are issued to site, technical approval is deemed to have been accorded.

  17. Post Award Activities • Amendment(s) to the contract • Regional Contracts for Corp.Packages and Regional/Site Contracts for site packages. • On receipt of technical approval, administrative approval to be taken for issue of change order as per DOP. • All Amendments to be signed by not below Manager.

  18. Post Award Activities • Time Extension and Liquidated Damages • The delay in the performance of contract may be on account of (a) Reasons attributable to the owner (b) Reasons due to force majeure conditions (c) Reasons attributable to contractor. • Liquidated Damages is to recover any loss and not a penalty.

  19. Post Award Activities • Completion, Testing, Commissioning and Taking over. • Revised Cost Estimate • Dispute Resolution and Arbitration • Contract Closing

  20. IMPORTANTPOST AWARD - ISSUES

  21. Important Post Award – Issues-1 • Correspondence Desc • Record of Bank Guarantees Desc • Release of Payment – Pending contract amendment Desc • Advancement of Supplies Desc • Performance Certificate to contractors Desc • Issue of Project Authority Certificate Desc

  22. Important Post Award – Issues - 2 • Insurance Desc • Checking of Conductor Length – in respect of consignment received in Transmission Line Stores Desc • POWERGRID’s overhead charges Desc • Completion, Commissioning, Taking Over and release of last payment Desc

  23. Important Post Award – Issues - 3 • Communication with GOI / MOP/ Funding Agencies etc., Desc • Reference to / Clarification Desc • Documents/Files concerning post – award contract execution Desc • Cancellation of Contract Desc • Negative Price Variation Desc • Payment Terms – Advance Payment Desc

  24. Important Post Award – Issues - 4 • Change of Name • Quantity Variation Provisions Desc • Reference Contract Price Desc • Packages Involving More than One Region Desc • Turnkey Contract Desc • Project Manager Desc • Tree Compensation Desc • Audit Co-ordination Desc • Discrepancies in Documents Desc

  25. Important Post Award – Issues - 5 • Retention Period of Contract Documents Desc • Taxes and Duties Desc • Miscellaneous Desc

  26. Correspondence • As per Contract to be followed • Each and every communication received from the contractor that requires response is to be replied promptly • Communication not to include any commitment/liability beyond contractual provision without approval of competant authority • LOA reference and name of the contract to be mentioned • Commercial aspects / issues raised to be prompty and expediously settled. BACK

  27. Records of BGs • Custodian - Finance Department. To maintain proper records • Finance to release status of BGs once in every quarter to trigger off action by all concerned for extention/encashment / release. • Action to be taken at least one month in advance

  28. Records of BGs • If No response from any department, finance to take action on its own for validity extention along with conditional claim. • Approving authority CC Packages – Extension /ED ( Region )

  29. Records of BGs Advance BG • Validity upto 90 days after scheduled TOC. • To be reduced on half yearly basis • Extension is not required after adjustment of total advance. • BG to be released within three months after adjustment of advance. • Proposal for reduction / release to be initiated by Regional / Site Finance. • Incase of extension, the Department seeking extension to put up proposal and ED(Region) to approve.

  30. Records of BGs Contract Performance Guarantee • C.P.G. to be reduced to half after issue of TOC • Execution site to send the proposal along with contractor’s request. • CC packages – AGM/GM to approve Site packages – DGM to approve • Due to considerable recovery if reduction is not possible to obtain approval of ED(Region) for CC packages and AGM/GM for site packages. • Release immediately after warranty period. • All efforts to be made to complete all contract closing formalities before warranty / defect liability period. • If any formalities pending and contractor is not responsible, CPG to be released with approval of ED or AGM/DGM. • The above is only for cases where the formalities takes more than three months after warranty period.

  31. Records of BGs B.G. against final payment / progressive payment • For retention of any BG beyond stipulated period requires approval of ED(Region) / GM or AGM as the case may be. BACK

  32. Tree Compensation • Approval for estimate to be taken before releasing the payment. • Revise if it is expected to exceed the original approval. • Proper record to be maintained. • All trees are to be removed including the saplings. • While handing over the line to O&M, certificate stating that all the trees and saplings are removed and the compensation has already been paid. BACK

  33. Release of payment pending contract amendment To avoid impediment to progress. • After technical approval for the quantities exceeding LOA – pay 90% • Pending approval for new items – pay 75% • Communication to the contractor to go ahead with the works pending issue of amendment. • Action to be taken for early issue of amendment. BACK

  34. Advancement of supplies POWERGRID requirements: • Transfer / diverting of material from one project to other due to urgent requirement. • Initial delay in award for supply contract. • For completion of project ahead of schedule • Obtain approval of Regional Head. • Pay PV at actuals

  35. Advancement of supplies Contractor’s requirement: • To take care POWERGRID interest also. • Disruption due to force majeure conditions like labour problem, riotous condition in the area of production. • Transporters strike. • Any other reason. • Allowed by considering availability of funds, storage space etc. • Approving authority – Director (Projects) • 30 days of advancement alone without any approval. • Warranty as per original contract. BACK

  36. Performance Certificate • Only for completed works: • To be issued for CC packages – CS • To be issued for site packages – Site C&M • Obtain details from site • Issue in prescribed format after approval ED(CS) / ED(Region) as the case may be. • To be issued only to lead partner with copies to other partners. • Partners wise portion can be indicated separately. BACK

  37. Issue of PAC and EDEC • As per exim policy to be issued by region, ED(Region) to issue. • Import content limited to LOA. Price variation can also be considered. • Contractor to make request to CC(CS) to finalise draft PAC and send to region. • Excise Duty Exemption Certificate – Same Procedure to be followed BACK

  38. Insurance • Transit / Marine Insurance for supply of material for supply / supply cum erection / turnkey contracts. • Storage cum erection / installation for supply cum erection / turnkey contracts. • Transit insurance to be valid upto 60 days of receipt of material at stores. • Storage cum erection insurance for owners as well as contractors supplied materials. • Reimbursement limited to owner’s material.

  39. To ensure adequate coverage • For imported material – 165% of CIF value + PV at 10% p.a. on CIF Cost (Maximum of 30% or Limited to as per contract) • Domestic supplies – FOR destination value + ED + ST + other levies + PV i.e. 130% of FOR destination price. • If any adjustment is required for PV, the same is to be taken care of.

  40. Valid upto 20% extra time over the schedule period to avoid extension. • Additional validity if delay is expected in the beginning itself. • Competitive bids to be taken by the contractor. • For Turnkey, supply cum erection, erection contracts – the same methodology to be adopted for insured value for material supplied by the contractor. • To avail discount composite policy to be taken. • If delay in supply of OSM, contractor who can take policy for his supplies with approval of GM / AGM. • Policy in the name of POWERGRID • Pending claim, the agency to make good the material lost including OSM • If policy extended due to fault of contractor, the extra liability to be recovered under LD. BACK

  41. Checking conductor length • Supplier to follow the procedure. • Contractor to weigh 20% of drums – expenses will be borne by the owner • Any shortage to be brought to the notice of supplier within 45 days to take action for lodging claim / to take necessary action. • TOC to be released against undertaking. BACK

  42. POWERGRID OVERHEAD CHARGES • POWERGRID supplied material / equipments when contractor fails/having constraints • Material to be supplied subjected to availability. • Recovery as per norms. BACK

  43. Black listing / Banning Business • Forgery of fraudulent practices including misrepresentation of facts. • Willful indulgence in supply of substandard material whether or not pre-despatch inspection carried out or not. • Repeated failure in fulfilling contractual obligation willfully. • Established litigant nature of the contractor to derive undue benefit. • Proposal to be initiated from concerned department / region. • Clearance by ED(CS)/ED(OS)/ED(Region)/ ED(QA&I)/ED(ENGG). • To be vetted by law and approved by CMD. • Showcause notice to be issued. • Approval from funding agencies wherever required. BACK

  44. Completion, Commissioning and takingover Completed but could not be commissioned - No source of supply, bays are not ready. • Possible to commission within 4 months. • Final payment to be released after commissioning and CPG to be extended accordingly. Commissioning not possible within 4 months • To release balance payment due as per contract. • BG to be furnished for the final payment. • Initially valid for 12 months or 3 months after expected date of commissioning (if it can be anticipated) • Request from contractor and approval by ED(Region) If the commissioning is not possible within validity period of BG. BG to be extended upto a period of 3 years from the date of readiness. • CPG to be extended 1 year beyond the validity of BG i.e. upto 4 years. • TOC only after commissioning in line with the above.

  45. Where system cannot be commissioned within a period of 3 years and reason not attributable to the contractor. • Take over the system with the approval of CMD. • BG for the final payment to be after TOC. • The CPG to be valid for a period of one year from the date of taking over. • Reimbursement of the additional charges incurred by the contractor. • (a) BG charges • (b) CPG charges for extended period • (c) Insurance charges • Obtain approval of ED(reg)

  46. Till taking over, the agency will be the custodian of the project. • To make arrangement for watch and ward • Mobilize team for commissioning as and when required.

  47. In cases where system commissioning is possible at reduced parameters: • In case of commissioning of the system possible within a year, the commissioning of the system at reduced voltage need not be considered. • If system demands for commissioning, the same may be resorted to with approval of Director(Proj). • In case commissioning of the asset not possible within one year, commission at reduced voltage with approval of Director (Proj). • Release the final payment against BG. To be extended upto two years after commissioning at reduced voltage. • CPG to be extended beyond one year of BG validity. • TOC to be issued. • BG charges etc. are to be reimbursed as stated earlier against documentary evidence with the approval of ED(REG). • Till system is taken over, contractor to provide watch and ward. Mobilize team for commissioning when it is required. If commissioning of the link or sub-station possible through other links at specified parameters, the system will be accepted as commissioned. • Any other case to be dealt separately.

  48. Other issues. • Pending commissioning, other contract closing formalities to be concluded. • Advance BG linked to TOC to be released after system is made ready and entire advance is adjusted. • Till the above become part of the contract, this can be utilized as guidelines for ongoing works. • Fore closure of contractor with the approval of CMD. BACK

  49. Communication with GOI / MOP / Funding Agencies • Corporate Planning will coordinate. BACK

  50. Reference to / Clarifications • Avoid unnecessary reference to other departments/offices, specially in routine matters for which the powers are delegated in DOP. • Concerned should study the contract documents and take decision in their areas of responsibility. • Deal effectively with the contractor and safeguard the interest of POWERGRID. • Inadequate understanding shall not be accepted as ground for reference. • Genuine contradiction/shortcoming in terms and conditions in various documents. The concerned responsibility centre will promptly attend to even though the region is responsible for post award. • CC packages, relevant portions of the bid to be made available to region by CC/CS if required for sorting out any issue. BACK