1 / 53

IPRF-03-1 Project

IPRF-03-1 Project. Progress on:. Best Practices Guide for In-Pavement Lighting, Portland Cement Concrete Pavement. Sponsored by: FAA, in Cooperative Agreement with Innovative Pavement Research Foundation (IPRF). Ornulv (Arnie) Sonsteby, P.E. Penn State/FAA Airport conference 2008

Mia_John
Télécharger la présentation

IPRF-03-1 Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IPRF-03-1 Project Progress on: Best Practices Guide for In-Pavement Lighting, Portland Cement Concrete Pavement Sponsored by: FAA, in Cooperative Agreement with Innovative Pavement Research Foundation (IPRF) Ornulv (Arnie) Sonsteby, P.E. Penn State/FAA Airport conference 2008 Hershey, PA

  2. Fact -- A 2-mile “low visibility” runway may have 800+ in-pavement lights. A a major airport may have 5,000 or more in-pavement lights. This represents a significant airport investment -- for initial installation, and out-year maintenance.

  3. Why this Document? Pavements and In-Pavement lights have different criteria based on function Light base is a penetration in otherwise uniform pavement with planned joints Installation of light base is KEY to meeting light tolerances

  4. Concrete Encasement and Rebar Cage Light base is Interface with pavement Anchor during Paving operation Strengthens Installation

  5. Key Pavement Tolerances Guidance: FAA AC 150-5320-6 • Promote Drainage • Smoothness for Traffic PURPOSE: • Height • Smoothness +/- 1/2” inch (deviation from design profile) +/- 1/4” inch in 16 feet

  6. Light bases “set in space”

  7. Light bases with pavementheight reference

  8. Difficult Joint Conflicts • Transverse joints, OK • Longitudinal joint difficult TDZ Lights: • Close spacing • Arcs oblique to joints TW CTL Lights: • Close spacing • Longitudinal joint conflict In-Pavement RGL & Stop Bar Lights:

  9. C L RW Centerline and TDZ Lights TDZ Contraction Joint (typ) Construction Joint (typ) 20’ Typ PCC Panel 18.75’ R/W RW CL

  10. C L Lead-off / Lead-on Lights Contraction Joint (typ) Typ PCC Panel 18.75’ 20’ Construction Joint (typ) LOF / LON R/W RW CL

  11. Resolving Joint Conflicts 2’ clear from joint Requirement --- In design --- • Coordinate pavement joints with required light locations • Use allowable tolerances to de-conflict • Last resort – use Boxout

  12. Key Lighting Tolerances Guidance: FAA AC 150-5345-30 (also UFC 5-535-01) • Visual signal (pattern) • Photometric requirements • Resistance to snow plows • Minimal impact on “ride” PURPOSE: • Layout • Azimuth • Height • Level varies for each system +/- 1/2 deg (relative to pavement elevation on low side) +0”/-1/16” None given (Engineer decide)

  13. Height Check HEIGHT of fixture edge at low side of pavement

  14. Height Straightedge: ~ 7’L x 6”-8”H Notch 1”x14” for Size B base • Check HEIGHT at fixture edge on low side of pavement • Check for obstruction in beam direction

  15. Azimuth +/- 1/2 deg Line of lights BEAM • Aim is usually parallel to line of lights, or RW/TW centerline • Some lights are “toed-in”, e.g.: • RW edge lights (3.5 deg toe-in) • TDZ lights (4 deg toe-in) • Unidirectional TW center lights on an arc are aimed into curve (to 4th light ahead) Orientation of light base bolt holes is key to azimuth aim

  16. Level +/- ? Lights to be installed level. (no tolerance in AC) Tilting light into grade blocks more light beam

  17. Resolving Joint Conflicts Resolving TDZ Lights --- • 2’ minimum separation should always be used with CONTRACTION joints. • Structurally, < 2’ may be OK with CONSTRUCTION joints (may require FAA “deviation from standards”. • Consider accepting 1.5’ separation from longitudinal construction joint (preferred over boxout).

  18. Resolving Joint Conflicts Contraction Joints --- • Do not install light base closer than 2’ to a contraction joint. • The contraction crack that forms as part of the concrete hydration process will typically propagate to a pavement penetration if < 2’ from joint. • If coordination and tolerances can’t resolve, boxout is only option.

  19. Resolving Joint Conflicts Construction Joints --- • < 2’ to a construction joint can work, provided: • Provisions are made for paving machine clearances • Load transfer is considered • Rebar cage should not cross joint. • If closer than 12” to joint and a dowel bar is within 12”, omit dowel bar or adjust dowel spacing (not considered detrimental to load transfer efficiency). • If 2 dowels must be omitted, extend concrete encasement for light base (anchor) across the joint to support joint edge of the 2 panels.

  20. Boxout at PCC Construction Joint Use WWF in all panels adjacent to boxout Change to construction joint when boxout is used on a planned contraction joint. Size of boxout increases as location of the light base moves away from joint.

  21. Boxout at PCC Joint Intersection Use WWF in all panels adjacent to boxout

  22. Full Depth Partial Panel Replacement Size of boxout increases as location of the light base moves away from joint. Change to construction joint when used on a planned contraction joint.

  23. Installation Quality • Successful installation is DIRECTLY dependent upon installation of the light base. • Quality is a function of: • Good design and construction documents • Good craftsmanship by the installer • Attentive Quality Control. • QC is even more important where time constraints require accelerated construction.

  24. Impact of Deficient installation For contractor --- Setting a light base too close to a joint, or out-of-tolerance wrt location, height relative to surface, azimuth, and level, may require removal and replacement.

  25. Capabilities Bad news – Installed bases are rejected. Good news – Problem is identified prior to paving!

  26. Impact of Deficient installation For User --- • Failure to meet light tolerances=> deficient photometrics • Failure to meet pavement performance requirements=> increased maintenance

  27. SUMMARY • Coordinate between disciplines (pavement, electrical, survey) • In Design & during Construction • Check frequently • Catch errors early

  28. Emerging Trends in Airfield Design and Construction Joe Vigilante, P.E. Penn State/FAA Airport Conference 2008 Hershey, PA

  29. Emerging Trends Runway Status Lights (RWSL) LED Lights Pre-Purchase Material

  30. Runway Status Lights (RWSL) • FAA Engineering Brief – EB-64A • Draft AC150/5340-30D – Appendix 7, Runway Status Light System (RWSL) • www.rwsl.net

  31. System Components • FAA Ground Surveillance System • Interfaces with Airport Surface Radar (ASDE) and Localized Transponders/Radar • Field Lighting Control System (FLCS) • In-pavement Lights with Local Control Units

  32. Field Lighting Control System (FLCS) • Runway Entrance Lights (REL) • Single Row of In-pavement Lights Parallel to TW Centerline • Take-off Hold Lights (THL) • Two Rows of In-pavement Lights Parallel to RW Centerline

  33. Runway Entrance Lights(REL) ANGLED CONFIGURATION LAYOUT

  34. Runway Entrance Lights(REL) • Pavement and Lighting Tolerances • Coordinating Lights with Paving Joints • Importance of Quality Control PERPENDICULAR CONFIGURATION LAYOUT

  35. Take Off/Hold Lights PROPOSED LOCATIONS

  36. Design Layout RWSL CONDUITS IN KERF: TCL, REL & RWSL TDZ RCL TCL RWSL TCL REL CONDUITS IN KERF: TCL, RCL & RWSL RWSL CONDUITS IN KERF: RCL & RWSL RCL TDZ CONSTRUCTABILITY

  37. Rundown • RWSL: • Moving Forward – Think – Coordinate • Designs are Being Completed – Heading into Paving Season • Critical to Install Infrastructure

  38. LED Airfield Lights • Various Fixtures – (+/-) 8 Years • Technology Continuously Improving • Range of Regional Installations

  39. Various LED Fixtures

  40. Various LED Fixtures

  41. Introducing LEDs to an Incandescent Field • Northeast Moving Cautiously • More Requests • One Step at a Time

  42. Choosing the One • Other than Primary Airfield Lights • Short Taxiway • Low Traffic or Cargo Usage • Buy-in From Facility

  43. The Candidate • Dead-End Cargo Carrier Taxiway • Approximately 3,600-ft.-long • 70 Taxiway Centerline Lights

  44. The View

  45. The Plan • Mix of FAA-certified Manufacturers • No Heaters • Segregated Circuit • Baseline Photometric Test

  46. Pre-Purchase Material • Goal – Procure Long Lead Time Items and Time Critical Items • Quick Start to Construction • Aids in Construction Phasing • Shorter Shutdowns

  47. Definitions • Pre-Order – Procurement of Material by the Airport • Stockpile – On-Site Supply of Material to Minimize Ordering During Construction • Material Examples • Light Bases • Series Lighting Cable • CCR Line-Ups

  48. The Process • Identify Material • Purchasing Bill of Material • Coordinate Receiving and Storage

  49. Advantages • Speed-Up Construction Start • Reduce RW/TW Closures • Light Systems Energized Quicker

  50. Disadvantages • Pavement Design • Additional Procurement Step • Higher Cost – Over-Purchase of Material

More Related