1 / 18

Progress Towards Production of Forward Modules

Progress Towards Production of Forward Modules. Other Clusters UK-V Cluster Component Availability Overall Schedule Prospects. CS Cluster. Qualification modules produced and results presented during SCT week CERN still encountering difficulties with electrical tests

abia
Télécharger la présentation

Progress Towards Production of Forward Modules

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Progress Towards Production of Forward Modules • Other Clusters • UK-V Cluster • Component Availability • Overall Schedule • Prospects

  2. CS Cluster • Qualification modules produced and results presented during SCT week • CERN still encountering difficulties with electrical tests • Krakow encountering difficulties in multi-hybrids testing using pseudo-optical via AERO • Request for qualification imminent

  3. CE Cluster • Qualification modules produced at NIKHEF presented during SCT week • Issues relating to bad channel numbers now partially resolved • Long Term Test now completed and all modules pass • .Redundancy test requires software mods • Request for qualification imminent • Freiburg and MPI still at pre-qualification stage.

  4. UK-V Cluster UK-N • Qualification modules assembled at Manchester and metrology results presented during SCT week • 4 bonded at Liverpool and electrical results presented. • Module showing high currents now holding volts at 350V 660nA to 340V and 1.1µA at 350V on standard SCTDAQ test (current slowly falling at 350V) • 5th module constructed (improved XY parameters), now bonded at Liverpool and completing electrical testing • Glasgow have provisionally passed pre-qualification based on two modules wire-bonded there. • First Glasgow qualification module provided by Manchester and success critical for qualification.

  5. UK-V Cluster Valencia • Effort switched to pre-qualification on middle modules • Jigs & bonding programme prepared for middle modules • Outers metrology results presented during SCT week • Concerns on S-curves in electrical tests of pre-qualification modules now largely overcome • Electrical testing cross-checked with Liverpool and metrology cross-checked with Geneva, Liverpool and MPI

  6. Component Availability • Hybrids and spines available for new modules continue to be in short supply

  7. Component Availability • Hybrid production slowed due to quality control issues (1/3 needing bonding rework from May, 1/4 needing bonding rework from June) • Weak bond related problems being addressed • Next batch to be 20 dummy hybrids to fully check quality • 2-3 weeks before next delivery of useable hybrids • Agreement to get reworked hybrids as soon as possible to speed up production

  8. Component Availability • Hans-Guenther and Alex were asked (26/6/03) to prepare a schedule for spines, assuming ISTC contract starts 1st August and AlN delivered by then.

  9. Schedule Looking tighter than ever! • Original agreed responsibilities by institute/cluster

  10. Schedule Module availability attempts to match the disk delivery schedule

  11. Disc Schedule

  12. Fan-in Schedule Official Hybrid Schedule

  13. Spines

  14. Prospects • Qualification is proving much slower than hoped • Sites are very nervous about getting started in a production mode • Electrical testing proving difficult and very time consuming • Problems (mostly minor) still being encountered on some quality issues and being solved Modules suitable for tracking particles with the required low noise occupancies and within the specified tolerances are being regularly produced in all 3 forward clusters

More Related