1 / 9

The Planning Lock Process

The Planning Lock Process. Richard D Smith. Introduction into the Lock Process. The planning process within the Railway Environment has been developed over many years, it has recently been improved to include the DWWP process.

acollins
Télécharger la présentation

The Planning Lock Process

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Planning Lock Process Richard D Smith

  2. Introduction into the Lock Process • The planning process within the Railway Environment has been developed over many years, it has recently been improved to include the DWWP process. • The DWWP process, depending on how its implemented is often seen as an additional activity in the planning process. • The Lock Process has been developed to link the normal Railway planning activities with the DWWP process and with the Last Planner process. • It’s a simple system that defines when certain deliverables are required and more importantly what needs to be updated and re-briefed should any changes occur.

  3. Introduction into the Lock Process Last plan session (2nd) Last plan session (1st) Last plan session (3rd) Requirements (Scope) Execution Scheduling Planning Lock 6 Lock 5 Lock 4 Lock 3 Lock 2 Lock 1 T-40 Review T-16 Review T-12 Review T-6 Review T-4 Review T-2 Review (GO-NO-GO) T+1 PDR (weekly) T-8 Review Start Planning Weekly Updates The lock process is flexible and can be used for any size or shape of project, upon initiation the lock deliverables should be reviewed and the Project Manager will agree which deliverables are relevant Engineering integration meetings (weekly) White Board (weekly)

  4. Lock Process (lock 6) Last planners sessions are conducted with site delivery resources to ensure that the correct staging of the works are undertaken together with adequate possession durations being requested. Last plan session (1st) • Work exits the lock 6 with :- • Work scope confirmed • Staging complete • Disruptive possessions • Haulage requirements The scope requirements are agreed, together with the proposed delivery method Requirements (Scope) Lock 6 T-40 Project Possession Strategy Box plan SNE Possession Strategy Box plan Route Master Plan Start Planning Local de-confliction Programme de-confliction Route de-confliction and lock down Weekly Updates Engineering integration sessions are conducted that review design and construction interfaces Engineering integration meetings (weekly)

  5. Lock Process (lock 5&4) 2nd Last planner session with site delivery resources to ensure to review the staging of the works and the detailed delivery programme (input in the hour x hour programme) Last plan session (2nd) • Work exits the lock5 with :- • Lock6 deliverables • Signal box opening arrangements • Wheels free requirements • Critical resource requirements • TSR requirements • Site access requirements • Haulage requirements • OTM / Tamper requirements • Rotr possession requirements • Environmental implications DWWP 1st deliverability review, to ensure that the works are RAG’d correctly Planning Lock 5 Lock 4 T-12 Exit the lock with a full review of deliverables T-40 Review T-16 Review Weekly Updates • Work exits the lock4 with :- • Lock6&5 deliverables • Hour by hour programme • QSRA Engineering integration meetings (weekly)

  6. Lock Process (lock 3, 2, &1) Final Last planner session with site delivery resources to update the programme based on any changes Last plan session (3rd) DWWP 2nd deliverability review, to review the overall readiness for the works Scheduling Lock 3 Lock 2 Lock 1 T-2 DWWP 3rd deliverability review, to review the overall readiness for the works to commence T-6 Review T-4 Review T-8 Review T-12 Review Weekly Updates • Work exits the lock3 with :- • Lock6,5 & 4 deliverables • Lockdown of the OTM resources • Lockdown of haulage • ES & COSS confirmed • Signal box openings confirmed • Crossing attendant confirmed • Work exits the lock2 with :- • Lock6,5, 4 & 3 deliverables • Hour by Hour programme locked • DWWP actions closed • On call arrangements • Severe weather plan • PICOP confirmed • Work exits the lock1 with :- • Lock6, 5, 4, 3 & 2 deliverables • Contingency / mitigation plan • Hold points • Final DWWP actions closed • Task briefing sheet produced • Go / No Go decision

  7. Execution PDR session to understand lessons from the executed works Changes during the lock process :- Any changes that are introduced need to be reviewed against the lock deliverables to ensure robust communication is undertaken. Changes post lock 1 are only allowed following the authorisation of the Senior Project Manager Works are executed both prep works, core works and any follow up activity Execution • Briefing products • Task briefing sheet • Activity charts • Hour by hour programme • Contingency / mitigation plan • Train movements • On call arrangements DWWP Go / No Go decision given to the project to proceed T-2 Review (GO-NO-GO) T+1 PDR (weekly) Weekly Updates White board briefing session to brief the team on the works and the delivery method and outputs White Board (weekly)

  8. Lock Planning Process Last plan session (2nd) Last plan session (1st) Last plan session (3rd) Requirements (Scope) Execution Scheduling Planning Lock 6 Lock 5 Lock 4 Lock 3 Lock 2 Lock 1 T-40 Review T-16 Review T-12 Review T-6 Review T-4 Review T-2 Review (GO-NO-GO) T+1 PDR (weekly) T-8 Review Start Planning Weekly Updates The lock process is flexible and can be used for any size or shape of project, upon initiation the lock deliverables should be reviewed and the Project Manager will agree which deliverables are relevant Engineering integration meetings (weekly) White Board (weekly)

  9. Lock Process Lock Process

More Related