An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Drexel RockSAT Full Mission System Testing Report • Kelly Collett • Christopher Elko • Danielle Jacobson • April 24, 2012

  2. FMSTR Presentation Contents • Section 1: Mission Overview • MissionStatement • Mission Objectives • Expected Results • System Modifications • Functional Block Diagrams

  3. FMSTR Presentation Contents • Section 2: Subsystem Test Reports • Subsystems Overview • Structural System (STR) • Piezoelectric Actuator System (PEA) • Electrical Power System (EPS) • Visual Verification System (VVS) • Section 3: Conclusions • Plans for Integration • Lessons Learned

  4. Mission Overview Drexel RockSat Team 2011-2012

  5. Mission Statement • Develop and test a system that will use piezoelectric materials to convert mechanical vibrational energy into electrical energy to trickle charge on-board power systems.

  6. Mission Overview • Demonstrate feasibility of power generation via piezoelectric effect under Terrier-Orion flight conditions • Determine optimal piezoelectric material for energy conversion in this application • Classify relationships between orientation of piezoelectric actuators and output voltage • Data will benefit future RockSAT and CubeSAT missions as a potential source of power • Data will be used for feasibility study

  7. Expected Results • Piezoelectric beam array will harness enough vibrational energy to generate and store voltage sufficient to power satellite systems • Anticipate output of 130 mV per piezo strip, based on preliminary testing. • Success dependent on following factors: • Permittivity of piezoelectric material • Mechanical stress, which is related to the amplitude of vibrations • Frequency of vibrations

  8. Changes Since ISTR • Implemented latching relay for g-switch • Added additional 9V battery to power camera

  9. Mechanical Subsystems Christopher Elko

  10. Integration full payload

  11. Integration PEA & STR • All PEA subsystem components fit successfully on lower flight deck • No interference with VVS components • Electronics fit successfully on upper flight deck

  12. Physical Specs full payload • Overall Height: 4.5 inches • Overall Weight (including electronics): 2.42 lb • CG: X = -0.01, Y = 0.27, Z = 0.10 in. • Canister Sharing with Temple • Method of Integration: standoffs • Min. Required Standoff Clearance: 1.0 inch • Combined Weight: 7.06 lb (based on designs) • Combined CG: pending final designs from Temple • CG to be adjusted with systematic ballast placement

  13. Prepare for Takeoff • Written integration procedure: in progress • Full parts list: compiled • Spare parts: procurement in progress • Action Items • More regular interface with Temple • Final construction of BETA

  14. EPS and Software Danielle Jacobson

  15. Electrical Design LED Array PEA I PEA II PEA III PEA IV Rectifier + Capacitor Rectifier + Capacitor Rectifier + Capacitor Rectifier + Capacitor Camera Internal Memory Arduino Microcontroller Accelerometer I SD Card Memory Accelerometer II 9V Battery Legend 9V Battery Wallops G-Switch New / updated part Power connection Data connection

  16. EPS test summary • All electronics performed favorably • Integration went smoothly • Activation system still in need of latching relay • Mechanical solution introduces a troubling single point of failure • Once activated, closes circuit until reset • Currently on order

  17. Data as collected Conclusion A bit messy…let’s take a closer look…

  18. Data piezoelectric output 5V Reference Input Pendulum beam generates highest voltage followed by diving board orientation; balance beam lowest (low G’s?) Observations

  19. Data accelerometers High-load vibration testing needed to fully characterize correlation between voltage output and acceleration (Wallops) Conclusion

  20. Data correlations Z-Axis Acceleration As acceleration in beam oriented direction increases, generated voltage also increases!!! It works!!! Observations

  21. Battery Power • Before full system test: ~ 9.3 V • Voltage after full system test: ~ 8.1 V • ΔV over 30-minute test: ~ 1.2 V • Estimated operation time until failure: 1.5+ hr

  22. Software • Software is running as planned • Data collection rates are solid • No inconsistencies

  23. VVS Updates Kelly Collett

  24. VVS status update

  25. VVS on a serious note… • Camera wired to 9V Battery • Originally running from Arduino 5 V output • Moved so Arduino can have its own power source

  26. VVS test summary • Camera will not function on auxiliary battery • Works when hooked up to the Li-Ion battery, but not the 9V • Odd, since it worked with the 9V power supply during ISTR testing

  27. VVS troubleshooting • Attempted changing resistors in the voltage regulator circuit • Resistor ratio (R2/R1) = 1.96 • 2.2/1.2, V = 3.7 V (It worked this time!) • 3.5/1.5, V = 4.5 V (It worked for a little while this time) • 7.35 / 3.7, NOTHING • Voltage going into circuit is too high? • 9 V, perhaps drop to 5 V? • Currently coming out of circuit at 4.5 V or higher

  28. Conclusions

  29. Action Items • STR & PEA • Finish any machining for BETA supports, mounts, etc. • Laser-cut BETA decks • Reconstruction – estimated completion date: 4/29/2012 • EPS • Vibe testing at Wallops to determine actual accelerations from test data • Latching relay to be integrated this week; clean up wiring • VVS • Don’t burn the camera…yet • Determine voltage issue • Integration • Communicate with Temple…

  30. Issues and Concerns • Camera • Latching relay • Spotty communication with Temple

  31. Final Thoughts

  32. Acknowledgements • Kyle Dooleyfor assistance with electronics and circuitry troubleshooting • Dan Lofaro for lending us his precision solder kit

  33. Thank you! Questions?