Metro North County Transit Center. Presentation to City of Ferguson – April 22, 2014. Introductions. John Nations – President and CEO John Wagner – Project Manager Economic Development Lance Peterson – Director of Service Planning Jeremy Dotson – Project Manager.
E N D
Metro North County Transit Center Presentation to City of Ferguson – April 22, 2014
Introductions • John Nations – President and CEO • John Wagner – Project Manager Economic Development • Lance Peterson – Director of Service Planning • Jeremy Dotson – Project Manager
Metro North County Public Transit Needs • High Ridership in North St. Louis County • 20% of Metro Ridership in North St. Louis County • Lack of Transit Hubs in North St. Louis County • Realignment to “Hub and Spoke” Approach • Goals • Enhance Public Transit Options for Public • Improve Metro Maintenance Capabilities • Encourage Growth of New Ridership
Key Features – Bus Transit Center • Development of Bus Transit Center • Provide 68 User Parking Spaces • Service 10 Bus Berths • Covered, Indoor Waiting Areas • Conference Room • Sign and Shelter Crew Storage • Security • Retail • Public Washroom Facilities
Key Features – Bus Maintenance Facility • Development of Bus Maintenance Facility • Bus Maintenance • Dispatch Center • Indoor Bus Storage • 164,300 Square Feet Gross Area • 145,000 Square Feet Footprint • Exterior • Glass • Architectural Composite Metal Panel • CMU Block – Pattern by Arts in Transit
Bus Maintenance Facility First Floor Layout • Storage • 70 Bus • 25 Call-A-Ride • Maintenance • 10 Repair Bays • 3-Bus Pit • Fuel Area • Chassis Wash • Bus Wash
Bus Maintenance Building First Floor Layout – Maintenance Area
Bus Maintenance Building Second Floor Layout
Schedule • Construction Documents • Phase I Bus Transit Center • May, 2014 • Phase II Bus Maintenance • August, 2014 • Construction Schedule • Phase I Bus Transit Center • Late Summer, 2014 • Phase II Bus Maintenance • TBD (Subject to Funding Availability)