1 / 7

Transmission Charging

Transmission Charging. Electricity Regional Initiative Steering Group 26 November 2007. T ransmission N etwork U se o f S ystem Charges Principles. TNUoS charges are designed to: Reflect the cost of installing, operating and maintaining the transmission system

akando
Télécharger la présentation

Transmission Charging

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Transmission Charging Electricity Regional Initiative Steering Group 26 November 2007

  2. Transmission Network Use of System ChargesPrinciples • TNUoS charges are designed to: • Reflect the cost of installing, operating and maintaining the transmission system • Provide economic and locational signals to Tx system users reflecting the incremental costs of supplying infrastructure. • Charges consist of: • A Locational Element • A Residual Element • TNUoS charges set to recover Allowed Revenue • Set by the Authority at the time of the TO Price Control

  3. Transmission Network Use of System ChargesPracticalities • For Generation • Locational & Residual charge based on registered Transmission Entry Capacity (TEC) • For Demand • Locational & Residual charge based on peak demand over the Triad period (for half-hourly metered users) • Triad Charging mechanism – the 3 highest peak system demands recorded between Nov & Feb, separated by 10 days • For interconnectors • Treated in the same way as Generation and Demand • Generation Charges based on registered TEC (connected capacity in MWs) • Demand – based on exports over the Triad period (MWhs)

  4. Electricity Transmission Access ReviewWhat is it considering? • 2007 Energy White Paper announced review of Transmission Access arrangements • To better support the timely and cost-effective connection of renewable generation • Transmission Access Review is investigating an incremental model in which: • Generators could hold long-term access (TEC) or short-term access • Allows for the sharing of existing rights between existing and new generators • Allow everyone to connect provided they are prepared to pay the constraint costs they cause, by offering additional short-term access products:

  5. Transmission Access ReviewWhat could this mean for Generation? • Generators using long-term access continue to pay LRMC (asset related cost) based on capacity (MW)? • Locational element • Generators using short-term access should pay SRMC (congestion related cost) based on utilisation (MWh)? • New charge • Everyone should pay residual (based on MWh)? • Commodity based energy charge (Generation equivalent to Interconnector Import)

  6. Transmission Access ReviewWhat could this mean for Demand? • Users continue to pay LRMC (asset related cost) based on capacity (Triad MW)? • Should the residual element be treated differently? • Charge based on MWh? • Charge based on MWh between 4pm and 7pm Nov to Feb? (Demand equivalent to Interconnector Export)

  7. Transmission Access ReviewNext steps • Transmission Access Review is being led by Ofgem & BERR • Next steps • Interim report Dec 2007 • Final report May 2008

More Related